Concept de urgenta pentru aria Mixing - Emergency concept for Mixing
1. Scop
Concept de urgent pentru Mixing extins cu procedura 190-GEN-PLT-CVT, care define te
procesul de comunicare cu ET (Engineering Tires) n cazul unor defecte majore.
1. Purpose
Emergency concept for Mixing extended with the PLT-GEN-190-CVT that defines thecommunication with ET (Engineering Tires) in case of major defects
2. Domeniu de aplicatie
Aria Mixing
2. Area of applicationMixing Area
3. Responsabilitatile pentru activitatea principala
Operator utilaj pentru anuntarea defectului, muncitori si ingineri hotline din ServiciulTehnic pentru eliminarea defectului, Sequencing si Productie pentru reducereapierderilor
3. Responsibilities for main activity
The machine operator for announcing the defect, workers and engineers PlantEngineering for repairs, Sequencing and Production for reducing the losses.
4. Descrierea activitatii principale4.1.Comunicare la nivel de fabricaConceptul de urgenta stabileste procedura si prioritatile pentru o reactie prompta dinpartea Serviciului Tehnic in caz de avarii. Prioritatile din punct de vedere tehnic suntdefinite conform tabelului din Anexa 1. La intelegere cu departamentele Sequencing siProductie se pot redefini prioritatile si in functie de utilajele care produc pt. OECustomer. Etapele de parcurs sunt prezentate detailat in schema logica din Anexa 2.
4.2 Comunicare cu ET
Urmeaz s fie folosit n scopul de a evita oprirea prelungit a produciei n fabricaafectat. Un defect major al unei maini sau al unui sistem este caracterizat prin:
- Defectare care va cauza oprirea fabricii;- Defectarea unei maini cheie, repornirea necesita suport de la centrala;
Defectarea unei masini care va reduce producia zilnic cu mai mult de 10%.Comunicarea n cazul unei ntreruperi se va face n baza diagramei de la Anexa 3.Persoanele care trebuie contactate la ET sunt prezentate la Anexa 4.
4. Description of the main activity4.1.Communication at the plant levelThe Emergency concept establishes the procedure and priorities for a prompt reactionfrom Plant Engineering in case of problems occurred on the machines. The prioritiesfrom technical point of view are listed in Annex 1. These can be redefined withSequencing and Production, depending on machines producing for OE Customer. Thesteps to be followed are in the logical scheme, in Annex 2.
4.2 Communication with ET
To be used in order to avoid unnecessary prolonged production stops in affected plant.A major break down of a machine or systems is characterized as :
- Break down which will stop the plant- Break down of key machine which requires central support
Break down which reduces the daily production by more than 10%The communication will be based on the diagram from Appendix 3.Persons to be contacted are presented in Appendix 4.
< Without ORIGINAL stamp any printout of this document is invalid. > Page 1 of 8
-
7/29/2019 Concept de Urgenta Pentru Aria Mixing - Emergency Concept for Mixing
2/8
Quality ManagementTimisoara
Category:Work InstructionProcess: Mixing Document No: PLTM-V-MX-G-00-WI -0209-14
Sub-process: General Documents Issue: 2
Task/Phase: Valid from: 12.07.2011
Author: Nimara, Muntean Process/Sub process Owner: Nimara
Concept de urgenta pentru aria Mixing - Emergency concept for Mixing
Concluzi ile ntreruperi i se vor complecta n formularul din Anexa 5. Documentation according to template from Appendix 5.
Lista reviziilor Revision List
Nr.reviziei Data Subiect Issue No. Date Subject
1 31.03.2011 Transferat in CT.DS 1 31.03.2011 Transfer in CT.DS
2 12.07.2011 extins cu procedura 190-GEN-PLT-CVT 2 12.07.2011 extended with the PLT-GEN-190-CVT
< Without ORIGINAL stamp any printout of this document is invalid. > Page 2 of 8
-
7/29/2019 Concept de Urgenta Pentru Aria Mixing - Emergency Concept for Mixing
3/8
Quality ManagementTimisoara
Category:Work InstructionProcess: Mixing Document No: PLTM-V-MX-G-00-WI -0209-14
Sub-process: General Documents Issue: 2
Task/Phase: Valid from: 12.07.2011
Author: Nimara, Muntean Process/Sub process Owner: Nimara
Concept de urgenta pentru aria Mixing - Emergency concept for Mixing
Anexa 1/ Annex 1
CONCEPT DE URGENTAPENTRU
ARIA MIXING
EMERGENCY CONCEPTFOR
MIXING AREA
PRIORITATE MAIN BUC. ARIA PRIORITY MACHINE PCS. AREA
1 MIXER 3 MIXING 1 MIXER 3 MIXING
2 INSTALATIE ANTI-TACK 1 MIXING 2ANTI-TACK
INSTALLATION1 MIXING
3SISTEM CINTARIRE
CHIMICALE1 MIXING 3
SMALL CHEMICAL
WEIGHING SYSTEM1 MIXING
4 INSTALATIE POMPAREULEI MES
1 MIXING 4 MES OIL PUMPINSTALLATION
1 MIXING
< Without ORIGINAL stamp any printout of this document is invalid. > Page 3 of 8
-
7/29/2019 Concept de Urgenta Pentru Aria Mixing - Emergency Concept for Mixing
4/8
Quality ManagementTimisoara
Category:Work InstructionProcess: Mixing Document No: PLTM-V-MX-G-00-WI -0209-14
Sub-process: General Documents Issue: 2
Task/Phase: Valid from: 12.07.2011
Author: Nimara, Muntean Process/Sub process Owner: Nimara
Concept de urgenta pentru aria Mixing - Emergency concept for Mixing
Anexa 2/ Annex 2
Anexa 2/ Annex 2
< Without ORIGINAL stamp any printout of this document is invalid. > Page 4 of 8
-
7/29/2019 Concept de Urgenta Pentru Aria Mixing - Emergency Concept for Mixing
5/8
Quality ManagementTimisoara
Category:Work InstructionProcess: Mixing Document No: PLTM-V-MX-G-00-WI -0209-14
Sub-process: General Documents Issue: 2
Task/Phase: Valid from: 12.07.2011
Author: Nimara, Muntean Process/Sub process Owner: Nimara
Concept de urgenta pentru aria Mixing - Emergency concept for Mixing
Anexa3/ Annex 3 FLOW CHART IN ET
< Without ORIGINAL stamp any printout of this document is invalid. > Page 5 of 8
-
7/29/2019 Concept de Urgenta Pentru Aria Mixing - Emergency Concept for Mixing
6/8
Quality ManagementTimisoara
Category:Work InstructionProcess: Mixing Document No: PLTM-V-MX-G-00-WI -0209-14
Sub-process: General Documents Issue: 2
Task/Phase: Valid from: 12.07.2011
Author: Nimara, Muntean Process/Sub process Owner: Nimara
Concept de urgenta pentru aria Mixing - Emergency concept for Mixing
Anexa 4/ Annex 4 CONTACT PERSONS IN ET
< Without ORIGINAL stamp any printout of this document is invalid. > Page 6 of 8
-
7/29/2019 Concept de Urgenta Pentru Aria Mixing - Emergency Concept for Mixing
7/8
Quality ManagementTimisoara
Category:Work InstructionProcess: Mixing Document No: PLTM-V-MX-G-00-WI -0209-14
Sub-process: General Documents Issue: 2
Task/Phase: Valid from: 12.07.2011
Author: Nimara, Muntean Process/Sub process Owner: Nimara
Concept de urgenta pentru aria Mixing - Emergency concept for Mixing
Main contact Standbye
MECLuigi Pomini Stefan Wiener +49 16090407877 +49 16093909930
C&DGerald Heinrich Matthias Cattau+49 1604726878 +49 1604767200
TTDReinhard von Horstig+49 1704506487
Anexa5 Annex 5 MAJOR BREAKDOWN ESCALATION
< Without ORIGINAL stamp any printout of this document is invalid. > Page 7 of 8
-
7/29/2019 Concept de Urgenta Pentru Aria Mixing - Emergency Concept for Mixing
8/8
Quality ManagementTimisoara
Category:Work InstructionProcess: Mixing Document No: PLTM-V-MX-G-00-WI -0209-14
Sub-process: General Documents Issue: 2
Task/Phase: Valid from: 12.07.2011
Author: Nimara, Muntean Process/Sub process Owner: Nimara
Concept de urgenta pentru aria Mixing - Emergency concept for Mixing
< Without ORIGINAL stamp any printout of this document is invalid. > Page 8 of 8