Manopera utilaj:

Sapatura, umplutura,nivelare, incarcare pamant= 45 ore buldoexcavator

Demontare gard ( smulgerea stalpilor), transport = 5 ore buldoexcavator

Transport pamant= 10 ore camion

Compactare balast,piatra sparta = 20 ore cilindru compactor

Materiale:

Ballast 10 cm =30 mc

Piatra Sparta 0-63, 27 cm =85 mc

Folie = 320 mp

Beton C16/20, 18 cm = 55 mc platforma

Beton C12/15= 3 mc fundatii gard

Plasa sudata Φ6-100x100= 350mp=30 buc

Cofrag 15 mp= 0.5 mc lemn

Categorii de lucari:

-demontarea gardului existent 65 ml, ( demontare plase, demontare stalpi, spart beton stalpi 3 mc)

-sapatura pamant la cota 120 mc, cu incarcare pamant si transport

-compactare pamant

-umplutura, nivelare,compactare strat ballast

-umplutura, nivelare, compactare strat piatra Sparta

-cofrare limita platforma

-turnare, nivelare, finisare beton

-montare gard (stalpi, plase), cu forare gropi, turnare fundatii ( 65 ml= 3mc beton)