NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) PANA LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII DETALII PROCEDURA 1 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA 30+550 59+100 ASOCIEREA TRAMECO SA – VAHOSTAV -SK A.S. – DRUMURI BIHOR SA – DRUM ASFALT SRL – EAST WATER DRILLINGS SRL SECTIUNEA 3C, SUBSECTIUNEA 3C2 CHIRIBIS - BIHARIA SUBSECTIUNEA 3C2: CHIRIBIS - BIHARIA 28.55 0.50% 0% 14.09.2020 - EMITERE ORDIN DE INCEPERE PENTRU ETAPA DE PROIECTARE (PROIECT TEHNIC) MARTIE 2022 (CONFORM CONTRACT) IUNIE 2022 (CONFORM PROGRAM) ANUL 2022 6 LUNI - ETAPA DE PROIECTARE; 18 LUNI - ETAPA DE EXECUTIE LUCRARI; 120 LUNI - PERIOADA DE GARANTIE 326.51 MIL. LEI FARA TVA CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 11.08. 2020. A FOST TRANSMISA CATRE ANTREPRENOR ADRESA CU ORDINUL DE INCEPERE PENTRU DATA DE 14.09.2020. A FOST ACORDAT DREPTUL DE ACCES IN SANTIER ANTREPRENORULUI. DURATA CONTRACTULUI ESTE DE 144 DE LUNI DIN CARE: 6 LUNI - ETAPA DE PROIECTARE; FINALIZARE PUNCT DE REFERINTA NR. 1 IN 09.11.2020. 18 LUNI - ETAPA DE EXECUTIE LUCRARI 120 LUNI - PERIOADA DE GARANTIE 2 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA 8+700 38+760 ASOCIEREA S.C. SPEDITION UMB S.R.L. – S.C. TEHNOSTRADE S.R.L. – S.C. ELECTROMONTAJ S.A SECTIUNEA 3A SI SECTIUNEA 3B, SUBSECTIUNEA 3A2: NADASELU - MIHAIESTI SI 3B1: MIHAESTI ZIMBOR SUBSECTIUNEA 3A2 NADASELU - MIHAIESTI KM 8+700 - 25+500+ 3B1, MIHAIESTI – ZIMBOR KM 0+000 - 13+260 30.06 0% 0% 25.01.2021 2023 ANUL 2023 1.390,614 MIL. LEI FARA TVA SEMNARE CONTRACT PROIECTARE SI EXECUTIE IN DATA DE 28.12.2020. PRETUL PE KM DE AUTOSTRADA ESTE DE CCA. 46,261,293.92 LEI FARA TVA, REPREZENTAND CCA. 9,383,629 EURO FARA TVA. DURATA CONTRACTULUI ESTE DE 96 DE LUNI, DIN CARE: • 12 LUNI PERIOADA DE PROIECTARE, • 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR, • 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR. AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3A2 IN LUNA APRILIE2021. PROIECT TEHNIC IN CURS DE ELABORARE PENTRU 3A2 - TERMEN ESTIMAT AVIZARE PROIECT TEHNIC: IULIE 2021 PENTRU SECTORUL 3B1 - AVIZARE DTAC SI OBTINERE AUTORIZATIE DE CONSTRUIRE : IUNIE 2021 3 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA 66+500 80+054 NUROL INSAAT VE TICARET S.A SECTIUNEA 3B, SUBSECTIUNEA 3B5 NUSFALAU - SUPLACU DE BARCAU SUBSECTIUNEA 3B5: NUSFALAU - SUPLACU DE BARCAU 13.55 0% 15% 01.02.2021 FEBRUARIE 2023 FEBRUARIE 2023 384.14 MIL. LEI FARA TVA CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN 30.09.2020; 6 LUNI PERIOADA DE PROIECTARE ; 18 LUNI PERIOADA DE EXECUTIE ; 120 LUNI PERIOADA DE GARANTIE LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 12 STRUCTURI (4 PASAJE SI 8 PODURI), RESPECTIV UN NOD RUTIER LA KM 67+500 FINALIZARE ETAPA PROIECTARE (PTE) - IULIE 2021 4 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA 13+260 25+500 ASOCIEREA SC SA&PE CONSTRUCT SRL - SC SPEDITION UMB SRL - SC TEHNOSTRADE SRL SECTIUNEA 3B, SUBSECTIUNEA 3B2: ZIMBOR - POARTA SALAJULUI SUBSECTIUNEA 3B2: ZIMBOR - POARTA SALAJULUI 12.24 0% 0% 31.05.2021 - ORDIN DE INCEPERE 2023 ANUL 2023 680.40 MIL. LEI FARA TVA CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 01.07.2020; DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE: 12 LUNI PERIOADA DE PROIECTARE, 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR, 120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR A FOST CONSTITUITA GARANTIA DE BUNA EXECUTIE A LUCRARILOR, ORDINUL DE INCEPERE A LUCRARILOR EMIS IN DATA DE 10.08.2020 A FOST SUSPENDAT PANA LA EMITEREA HG PENTRU DECLANSAREA PROCEDURII DE EXPROPRIERE 5 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA 0+000 4+500 S.C. STRABAG S.R.L. SECTOR 1C: TG. MURES - OGRA LOT 1 - TARGU MURES - UNGHENI (4.5 KM) + DRUM DE LEGATURA (4.7 KM) 9.2 57.40% 42.45% ORDIN DE INCEPERE PENTRU EXECUTIE - 22 IULIE 2020 2022 (CONFORM CONTRACT) 2021 - CONFORM ESTIMARE ANTREPRENOR/ CNAIR SA ANUL 2022 192.06 MIL. LEI FARA TVA 1. CONTRACT DE EXECUTIE SEMNAT IN DATA DE 29.05.2020. 2. AUTORIZATIE DE CONSTRUIRE VALABILA PENTRU ACEST SECTOR. 3. DURATA DE REALIZARE A ACESTUI CONTRACT ESTE URMATOAREA: 18 LUNI - PERIOADA DE EXECUTIE A LUCRARILOR; 108 LUNI (9 ANI) - PERIOADA DE GARANTIE A LUCRARILOR; LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 3 PODURI SI PASAJE PE DRUMURI DE LEGATURA, 6 PODURI SI PASAJE PE AUTOSTRADA, PRECUM SI DOUA NODURI RUTIERE PENTRU CONECTAREA AUTOSTRAZII LA RETEAUA DE DRUMURI EXISTENTA. 6 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA BRASOV - TARGU MURES - CLUJ - ORADEA 21+500 37+191 ASOCIEREA SC STRACO GRUP SRL & SPECIALIST CONSULTING SRL & SC TOTAL ROAD SRL TRONSON OGRA - CAMPIA TURZII (2A3 CHETANI - CAMPIA TURZII) LOT 3 15.691 37.86% 41.97% 04.05.2016 18.09.2020 - NOD CHETANI (1.3 KM) - DESCHIDEREA TRAFICULUI 2021 - INTARZIERI MAJORE ALE CONTRACTULUI DE PROIECTARE SI EXECUTIE - CONTRACT REZILIAT REZILIAT 279.74 MIL. LEI FARA TVA IN DATA DE 11.03.2021 S-A TRANSMIS ANTREPRENORULUI INSTIINTAREA DE REZILIERE A CONTRACTULUI. PROCEDURA DE REZILIERE A FOST SUSPENDATA IN URMA DECIZIEI TRIBUNALULUI BUCURESTI. DUPĂ DECIZIA INSTANȚEI PRIVIND REZILIEREA, PROCEDURA VA FI RELUATĂ URMÂND SĂ FIE PARCURSE URMĂTOARELE ETAPE: - FINALIZARE CAIET DE SARCINI, REFERAT DE NECESITATE SI TRANSMITERE LA DIRECTIA ACHIZITII PUBLICE; - FINALIZARE DOCUMENTATIE DE ATRIBUIRE (CRITERII DE CALIFICARE, MODEL CONTRACT, FACTORI EVALUARE); - TRANSMITERE DOCUMENTATIE DE ATRIBUIRE SPRE VALIDARE LA ANAP; PUBLICARE ANUNT DE PARTICIPARE IN SICAP; - DEPUNERE OFERTE; - ANALIZA SI EVALUAREA OFERTELOR CU STABILIREA OFERTANTULUI CASTIGATOR; - COMUNICAREA REZULTATULUI PROCEDURII DE ACHIZITIE PUBLICA; CONTESTATII; - SEMNARE CONTRACT. 7 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA DE CENTURA A MUNICIPIULUI BUCURESTI (A0) 47+600 52+070 ASOCIEREA S.C. SA&PE CONSTRUCT S.R.L. - S.C. SPEDITION UMB S.R.L. - S.C. TEHNOSTRADE S.R.L. SECTOR NORD LOT 4 4.47 0% 0% 31.08.2020 2023 DURATA CONTRACTULUI ESTE DE 90 LUNI SI CUPRINDE 12 LUNI PERIOADA DE PROIECTARE, 18 LUNI PERIOADA DE EXECUTIE A LUCRARILOR SI 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR. ESTIMAT 2023 312.63 MIL. LEI FARA TVA CONTRACT SEMNAT IN DATA DE 31.08.2020. ESTIMAT EMITERE ORDIN DE INCEPERE A ETAPEI DE PROIECTARE (ELABORARE PROIECT TEHNIC) - TRIM. IV 2021 8 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA DE CENTURA A MUNICIPIULUI BUCURESTI (A0) 20+000 39+000 ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L. SECTOR NORD LOT 2 19 0% 0% 2021 2024 831.92 MIL. LEI FARA TVA IN DATA DE 12.05.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL ""PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 2 KM 20+000 - KM 39+000”, CU OFERTANTUL DECLARAT CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L. VALOAREA CONTRACTULUI: 831.920.653,34 LEI FARA TVA. LUNGIME: 19 KM SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE. DURATA CONTRACTULUI ESTE DE 154 LUNI, DIN CARE: 12 LUNI PERIOADA DE PROIECTARE, 22 LUNI PERIOADA DE EXECUȚIE A LUCRĂRILOR 120 LUNI PERIOADA DE GARANȚIE A LUCRĂRILOR 9 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA DE CENTURA A MUNICIPIULUI BUCURESTI (A0) 69+000 85+300 ALSIM ALARKO SANAYI TESISLERI VE TICARET A.S. SECTOR SUD LOT 2: VIDRA - BRAGADIRU 16.3 17.36% 22.78% - PROGRES FINANCIAR (INCLUSIV AVANS LUCRARI SI ACTUALIZARI PRETURI) 10.04.2019 - ORDIN DE INCEPERE A ACTIVITATII DE PROIECTARE 18.08.2020 - ORDIN INCEPERE LUCRARI KM 69+000 - KM 70+700 FEBRUARIE 2023 FEBRUARIE 2023 750.85 MIL. LEI FARA TVA ORDIN DE INCEPERE A LUCRARILOR 18.08.2020 ETAPA 1: KM 69+000 - KM 70+700 DECIZIA PENTRU EXPROPRIERI AFERENTA HG 675/2020 A FOST EMISA IN DATA DE 15.10.2020 A FOST ACORDAT AVANSUL PENTRU EXECUTIE LUCRARI (15% DIN VALOAREA LUCRARILOR) ORDINUL DE INCEPERE PENTRU ETAPA 2, CONSTAND IN INTREG ALINIAMENTUL LOTULUI 2, A FOST EMIS IN DATA DE 29.10.2020, DATA DE INCEPERE FIIND 05.11.2020 (14,6 KM) A FOST PUBLICAT IN MONITORIUL OFICIAL HG NR. 1139/30.12.2020 PRIVIND IMOBILELE AFLATE PE CULOARUL SUPLIMENTAR, INCLUSIV DECIZIA DE EXPROPRIERE NR. 378/17.02.2021. IN DATA DE 12.03.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 11 PENTRU ETAPA III, EXPROPRIERI SUPLIMENTARE 10 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA DE CENTURA A MUNICIPIULUI BUCURESTI (A0) 52+070 69+000 ALSIM ALARKO SANAYI TESISLERI VE TICARET A.S. SECTOR NORD - KM 52+070 – KM 52+770; SECTOR SUD - KM 52+770 – KM 69+000 LOT 1: GLINA - VIDRA 16.93 3.69% 19.73% - PROGRES FINANCIAR (INCLUSIV AVANS LUCRARI) 03.10.2019 - DATA DE INCEPERE A ACTIVITATII DE PROIECTARE IUNIE 2023 ANUL 2023 830.68 MIL. LEI FARA TVA A FOST EMISA AUTORIZATIA DE CONSTRUIRE NR. 66/25.11.2020 A FOST APROBAT PROIECTUL TEHNIC DE EXECUTIE IN DATA DE 11.02.2021. ORDIN DE INCEPERE LUCRARI 01.03.2021 11 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA DE CENTURA A MUNICIPIULUI BUCURESTI (A0) 85+300 - 100+765 SUD 0+000 - 2+500 NORD ASOCIEREA AKTOR TECHNICAL SOCIETE ANONYME (AKTOR S.A.) - S.C. EURO CONSTRUCT TRADING 98 S.R.L. SECTOR SUD - KM 85+300 - KM 100+765; SECTOR NORD - KM 0+000 + KM 2+500 LOT 3: BRAGADIRU - JOITA 17.965 0.00% 1,03% (PROGRES FINANCIAR INCLUSIV AVANS PROIECTARE) 23.05.2019 - DATA DE INCEPERE A ACTIVITATII DE PROIECTARE DECEMBRIE 2022 DECEMBRIE 2022 853.42 MIL. LEI FARA TVA IN PREZENT ANTREPRENORUL A REUSIT SA FINALIZEZE DECLARATIA DE PROIECTARE (INREGISTRAND INTARZIERI MAJORE IN ACTIVITATEA DE PROIECTARE), FIIND PENALIZAT CONFORM CONTRACTULUI PENTRU NEINDEPLINIREA PUCTULUI DE REFERINTA NR 1 (FINALIZAREA DECLARATIEI DE PROIECTARE). PAC A FOST ANALIZAT SI APROBAT IN CADRUL CTE CNAIR IN DATA DE 11.06.2021. LA DATA PREZENTEI, ANTREPRENORUL ELABOREAZA PTE. 12 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA SEBES - TURDA 17+000 41+250 ASOCIEREA AKTOR TECHNICAL SOCIETE ANONYME (AKTOR S.A.) - S.C. EURO CONSTRUCT TRADING 98 S.R.L. SANTIMBRU - AIUD LOT 2 24.25 85.90% 76.98% 02.12.2014 APRILIE 2022 - CONFORM GRAFIC DE LUCRARI ESTIMARE DESCHIDERE TRAFIC - NOIEMBRIE 2021 549.33 MIL. LEI FARA TVA CONTRACT PROIECTARE SI EXECUTIE CU INTARZIERI MAJORE INREGISTRATE, DATORATE SLABEI MOBILIZARI A CONSTRUCTORULUI DIN ANII ANTERIORI, DAR SI DIN PREZENT, DATORATA LIPSEI RESURSELOR FINANCIARE PROPRII PENTRU SUSTINEREA SANTIERULUI; PE ROLUL INSTANTELOR, SE AFLA DOUA DOSARE PRIVIND CONTESTATII ALE UNOR EXECUTARI SILITE PENTRU IMOBILELE NECESARE EXECUTIEI LUCRARILOR. STADIU PROCESUAL: FOND. IN DATA DE 18.06.2021, ANTREPRENORUL SI-A ASUMAT SOLUTIA FINALA IN VEDEREA STABILIZARII NECESARE IN ZONA KM 19+300 1. AUTOSTRĂZI SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021 1.1. AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI - IUNIE 2021

Upload: others

Post on 05-Nov-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021 1

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

1 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADAAUTOSTRADA BRASOV - TARGU MURES - CLUJ -

ORADEA30+550 59+100

ASOCIEREA TRAMECO SA – VAHOSTAV -SK A.S. – DRUMURI BIHOR

SA – DRUM ASFALT SRL – EAST WATER DRILLINGS SRL

SECTIUNEA 3C, SUBSECTIUNEA 3C2

CHIRIBIS - BIHARIA

SUBSECTIUNEA 3C2: CHIRIBIS -

BIHARIA28.55 0.50% 0%

14.09.2020 - EMITERE ORDIN DE

INCEPERE PENTRU ETAPA DE

PROIECTARE (PROIECT TEHNIC)

MARTIE 2022 (CONFORM

CONTRACT)

IUNIE 2022 (CONFORM PROGRAM)

ANUL 2022 6 LUNI - ETAPA DE

PROIECTARE; 18 LUNI - ETAPA DE

EXECUTIE LUCRARI; 120 LUNI -

PERIOADA DE GARANTIE

326.51 MIL. LEI FARA TVA

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 11.08. 2020.

A FOST TRANSMISA CATRE ANTREPRENOR ADRESA CU ORDINUL DE INCEPERE PENTRU DATA DE 14.09.2020. A FOST ACORDAT DREPTUL DE ACCES IN

SANTIER ANTREPRENORULUI.

DURATA CONTRACTULUI ESTE DE 144 DE LUNI DIN CARE:

6 LUNI - ETAPA DE PROIECTARE; FINALIZARE PUNCT DE REFERINTA NR. 1 IN 09.11.2020.

18 LUNI - ETAPA DE EXECUTIE LUCRARI

120 LUNI - PERIOADA DE GARANTIE

2 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADAAUTOSTRADA BRASOV - TARGU MURES - CLUJ -

ORADEA8+700 38+760

ASOCIEREA S.C. SPEDITION UMB S.R.L. – S.C. TEHNOSTRADE S.R.L. –

S.C. ELECTROMONTAJ S.A

SECTIUNEA 3A SI SECTIUNEA 3B,

SUBSECTIUNEA 3A2: NADASELU -

MIHAIESTI SI 3B1: MIHAESTI

ZIMBOR

SUBSECTIUNEA 3A2 NADASELU -

MIHAIESTI KM 8+700 - 25+500+

3B1, MIHAIESTI – ZIMBOR KM 0+000 -

13+260

30.06 0% 0% 25.01.2021 2023 ANUL 2023 1.390,614 MIL. LEI FARA TVA

SEMNARE CONTRACT PROIECTARE SI EXECUTIE IN DATA DE 28.12.2020. PRETUL PE KM DE AUTOSTRADA ESTE DE CCA. 46,261,293.92 LEI FARA TVA,

REPREZENTAND CCA. 9,383,629 EURO FARA TVA.

DURATA CONTRACTULUI ESTE DE 96 DE LUNI, DIN CARE:

• 12 LUNI PERIOADA DE PROIECTARE,

• 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,

• 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.

AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3A2 IN LUNA APRILIE2021. PROIECT TEHNIC IN CURS DE ELABORARE PENTRU 3A2 - TERMEN

ESTIMAT AVIZARE PROIECT TEHNIC: IULIE 2021

PENTRU SECTORUL 3B1 - AVIZARE DTAC SI OBTINERE AUTORIZATIE DE CONSTRUIRE : IUNIE 2021

3 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADAAUTOSTRADA BRASOV - TARGU MURES - CLUJ -

ORADEA66+500 80+054 NUROL INSAAT VE TICARET S.A

SECTIUNEA 3B, SUBSECTIUNEA 3B5

NUSFALAU - SUPLACU DE BARCAU

SUBSECTIUNEA 3B5: NUSFALAU -

SUPLACU DE BARCAU13.55 0% 15% 01.02.2021 FEBRUARIE 2023 FEBRUARIE 2023 384.14 MIL. LEI FARA TVA

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN 30.09.2020;

6 LUNI PERIOADA DE PROIECTARE

; 18 LUNI PERIOADA DE EXECUTIE

; 120 LUNI PERIOADA DE GARANTIE

LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 12 STRUCTURI (4 PASAJE SI 8 PODURI), RESPECTIV UN

NOD RUTIER LA KM 67+500

FINALIZARE ETAPA PROIECTARE (PTE) - IULIE 2021

4 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADAAUTOSTRADA BRASOV - TARGU MURES - CLUJ -

ORADEA13+260 25+500

ASOCIEREA SC SA&PE CONSTRUCT SRL - SC SPEDITION UMB SRL - SC

TEHNOSTRADE SRL

SECTIUNEA 3B, SUBSECTIUNEA 3B2:

ZIMBOR - POARTA SALAJULUI

SUBSECTIUNEA 3B2: ZIMBOR -

POARTA SALAJULUI12.24 0% 0% 31.05.2021 - ORDIN DE INCEPERE 2023 ANUL 2023 680.40 MIL. LEI FARA TVA

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 01.07.2020;

DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE:

12 LUNI PERIOADA DE PROIECTARE,

24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,

120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR

A FOST CONSTITUITA GARANTIA DE BUNA EXECUTIE A LUCRARILOR, ORDINUL DE INCEPERE A LUCRARILOR EMIS IN DATA DE 10.08.2020 A FOST

SUSPENDAT PANA LA EMITEREA HG PENTRU DECLANSAREA PROCEDURII DE EXPROPRIERE

5 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADAAUTOSTRADA BRASOV - TARGU MURES - CLUJ -

ORADEA0+000 4+500 S.C. STRABAG S.R.L. SECTOR 1C: TG. MURES - OGRA

LOT 1 - TARGU MURES - UNGHENI

(4.5 KM) + DRUM DE LEGATURA (4.7

KM)

9.2 57.40% 42.45%ORDIN DE INCEPERE PENTRU

EXECUTIE - 22 IULIE 2020

2022 (CONFORM CONTRACT)

2021 - CONFORM ESTIMARE

ANTREPRENOR/ CNAIR SA

ANUL 2022 192.06 MIL. LEI FARA TVA

1. CONTRACT DE EXECUTIE SEMNAT IN DATA DE 29.05.2020.

2. AUTORIZATIE DE CONSTRUIRE VALABILA PENTRU ACEST SECTOR.

3. DURATA DE REALIZARE A ACESTUI CONTRACT ESTE URMATOAREA:

18 LUNI - PERIOADA DE EXECUTIE A LUCRARILOR;

108 LUNI (9 ANI) - PERIOADA DE GARANTIE A LUCRARILOR;

LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 3 PODURI SI PASAJE PE DRUMURI DE LEGATURA, 6

PODURI SI PASAJE PE AUTOSTRADA, PRECUM SI DOUA NODURI RUTIERE PENTRU CONECTAREA AUTOSTRAZII LA RETEAUA DE DRUMURI EXISTENTA.

6 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADAAUTOSTRADA BRASOV - TARGU MURES - CLUJ -

ORADEA21+500 37+191

ASOCIEREA SC STRACO GRUP SRL & SPECIALIST CONSULTING SRL &

SC TOTAL ROAD SRL

TRONSON OGRA - CAMPIA TURZII

(2A3 CHETANI - CAMPIA TURZII)LOT 3 15.691 37.86% 41.97% 04.05.2016

18.09.2020 - NOD CHETANI (1.3 KM) -

DESCHIDEREA TRAFICULUI

2021 - INTARZIERI MAJORE ALE

CONTRACTULUI DE PROIECTARE SI

EXECUTIE - CONTRACT REZILIAT

REZILIAT 279.74 MIL. LEI FARA TVA

IN DATA DE 11.03.2021 S-A TRANSMIS ANTREPRENORULUI INSTIINTAREA DE REZILIERE A CONTRACTULUI.

PROCEDURA DE REZILIERE A FOST SUSPENDATA IN URMA DECIZIEI TRIBUNALULUI BUCURESTI.

DUPĂ DECIZIA INSTANȚEI PRIVIND REZILIEREA, PROCEDURA VA FI RELUATĂ URMÂND SĂ FIE PARCURSE URMĂTOARELE ETAPE:

- FINALIZARE CAIET DE SARCINI, REFERAT DE NECESITATE SI TRANSMITERE LA DIRECTIA ACHIZITII PUBLICE;

- FINALIZARE DOCUMENTATIE DE ATRIBUIRE (CRITERII DE CALIFICARE, MODEL CONTRACT, FACTORI EVALUARE);

- TRANSMITERE DOCUMENTATIE DE ATRIBUIRE SPRE VALIDARE LA ANAP;

PUBLICARE ANUNT DE PARTICIPARE IN SICAP;

- DEPUNERE OFERTE;

- ANALIZA SI EVALUAREA OFERTELOR CU STABILIREA OFERTANTULUI CASTIGATOR;

- COMUNICAREA REZULTATULUI PROCEDURII DE ACHIZITIE PUBLICA;

CONTESTATII;

- SEMNARE CONTRACT.

7 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADAAUTOSTRADA DE CENTURA A MUNICIPIULUI

BUCURESTI (A0) 47+600 52+070

ASOCIEREA S.C. SA&PE CONSTRUCT S.R.L. - S.C. SPEDITION UMB

S.R.L. - S.C. TEHNOSTRADE S.R.L. SECTOR NORD LOT 4 4.47 0% 0% 31.08.2020

2023

DURATA CONTRACTULUI ESTE DE 90

LUNI SI CUPRINDE 12 LUNI

PERIOADA DE PROIECTARE, 18 LUNI

PERIOADA DE EXECUTIE A

LUCRARILOR SI 60 DE LUNI

PERIOADA DE GARANTIE A

LUCRARILOR.

ESTIMAT 2023 312.63 MIL. LEI FARA TVACONTRACT SEMNAT IN DATA DE 31.08.2020.

ESTIMAT EMITERE ORDIN DE INCEPERE A ETAPEI DE PROIECTARE (ELABORARE PROIECT TEHNIC) - TRIM. IV 2021

8 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADAAUTOSTRADA DE CENTURA A MUNICIPIULUI

BUCURESTI (A0) 20+000 39+000

ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) -

SPEDITION UMB - TEHNOSTRADE S.R.L.SECTOR NORD LOT 2 19 0% 0% 2021 2024 831.92 MIL. LEI FARA TVA

IN DATA DE 12.05.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL ""PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM

100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 2 KM 20+000 - KM 39+000”, CU OFERTANTUL DECLARAT CASTIGTOR, ASOCIEREA SC SA &

PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.

VALOAREA CONTRACTULUI: 831.920.653,34 LEI FARA TVA.

LUNGIME: 19 KM

SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE.

DURATA CONTRACTULUI ESTE DE 154 LUNI, DIN CARE:

12 LUNI PERIOADA DE PROIECTARE,

22 LUNI PERIOADA DE EXECUȚIE A LUCRĂRILOR

120 LUNI PERIOADA DE GARANȚIE A LUCRĂRILOR

9 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADAAUTOSTRADA DE CENTURA A MUNICIPIULUI

BUCURESTI (A0)69+000 85+300 ALSIM ALARKO SANAYI TESISLERI VE TICARET A.S. SECTOR SUD LOT 2: VIDRA - BRAGADIRU 16.3 17.36%

22.78% - PROGRES FINANCIAR

(INCLUSIV AVANS LUCRARI SI

ACTUALIZARI PRETURI)

10.04.2019 - ORDIN DE INCEPERE A

ACTIVITATII DE PROIECTARE

18.08.2020 - ORDIN INCEPERE

LUCRARI KM 69+000 - KM 70+700

FEBRUARIE 2023 FEBRUARIE 2023 750.85 MIL. LEI FARA TVA

ORDIN DE INCEPERE A LUCRARILOR 18.08.2020 ETAPA 1: KM 69+000 - KM 70+700

DECIZIA PENTRU EXPROPRIERI AFERENTA HG 675/2020 A FOST EMISA IN DATA DE 15.10.2020

A FOST ACORDAT AVANSUL PENTRU EXECUTIE LUCRARI (15% DIN VALOAREA LUCRARILOR)

ORDINUL DE INCEPERE PENTRU ETAPA 2, CONSTAND IN INTREG ALINIAMENTUL LOTULUI 2, A FOST EMIS IN DATA DE 29.10.2020, DATA DE INCEPERE

FIIND 05.11.2020 (14,6 KM)

A FOST PUBLICAT IN MONITORIUL OFICIAL HG NR. 1139/30.12.2020 PRIVIND IMOBILELE AFLATE PE CULOARUL SUPLIMENTAR, INCLUSIV DECIZIA DE

EXPROPRIERE NR. 378/17.02.2021.

IN DATA DE 12.03.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 11 PENTRU ETAPA III, EXPROPRIERI SUPLIMENTARE

10 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADAAUTOSTRADA DE CENTURA A MUNICIPIULUI

BUCURESTI (A0)52+070 69+000 ALSIM ALARKO SANAYI TESISLERI VE TICARET A.S.

SECTOR NORD - KM 52+070 – KM

52+770; SECTOR SUD - KM 52+770 –

KM 69+000

LOT 1: GLINA - VIDRA 16.93 3.69%19.73% - PROGRES FINANCIAR

(INCLUSIV AVANS LUCRARI)

03.10.2019 - DATA DE INCEPERE A

ACTIVITATII DE PROIECTAREIUNIE 2023 ANUL 2023 830.68 MIL. LEI FARA TVA

A FOST EMISA AUTORIZATIA DE CONSTRUIRE NR. 66/25.11.2020

A FOST APROBAT PROIECTUL TEHNIC DE EXECUTIE IN DATA DE 11.02.2021.

ORDIN DE INCEPERE LUCRARI 01.03.2021

11 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADAAUTOSTRADA DE CENTURA A MUNICIPIULUI

BUCURESTI (A0)

85+300 -

100+765 SUD

0+000 - 2+500

NORD

ASOCIEREA AKTOR TECHNICAL SOCIETE ANONYME (AKTOR S.A.) -

S.C. EURO CONSTRUCT TRADING 98 S.R.L.

SECTOR SUD - KM 85+300 - KM

100+765; SECTOR NORD - KM 0+000

+ KM 2+500

LOT 3: BRAGADIRU - JOITA 17.965 0.00%1,03% (PROGRES FINANCIAR

INCLUSIV AVANS PROIECTARE)

23.05.2019 - DATA DE INCEPERE A

ACTIVITATII DE PROIECTAREDECEMBRIE 2022 DECEMBRIE 2022 853.42 MIL. LEI FARA TVA

IN PREZENT ANTREPRENORUL A REUSIT SA FINALIZEZE DECLARATIA DE PROIECTARE (INREGISTRAND INTARZIERI MAJORE IN ACTIVITATEA DE

PROIECTARE), FIIND PENALIZAT CONFORM CONTRACTULUI PENTRU NEINDEPLINIREA PUCTULUI DE REFERINTA NR 1 (FINALIZAREA DECLARATIEI DE

PROIECTARE).

PAC A FOST ANALIZAT SI APROBAT IN CADRUL CTE CNAIR IN DATA DE 11.06.2021.

LA DATA PREZENTEI, ANTREPRENORUL ELABOREAZA PTE.

12 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA SEBES - TURDA 17+000 41+250ASOCIEREA AKTOR TECHNICAL SOCIETE ANONYME (AKTOR S.A.) -

S.C. EURO CONSTRUCT TRADING 98 S.R.L.SANTIMBRU - AIUD LOT 2 24.25 85.90% 76.98% 02.12.2014

APRILIE 2022 - CONFORM GRAFIC DE

LUCRARIESTIMARE DESCHIDERE TRAFIC -

NOIEMBRIE 2021549.33 MIL. LEI FARA TVA

CONTRACT PROIECTARE SI EXECUTIE CU INTARZIERI MAJORE INREGISTRATE, DATORATE SLABEI MOBILIZARI A CONSTRUCTORULUI DIN ANII ANTERIORI,

DAR SI DIN PREZENT, DATORATA LIPSEI RESURSELOR FINANCIARE PROPRII PENTRU SUSTINEREA SANTIERULUI;

PE ROLUL INSTANTELOR, SE AFLA DOUA DOSARE PRIVIND CONTESTATII ALE UNOR EXECUTARI SILITE PENTRU IMOBILELE NECESARE EXECUTIEI

LUCRARILOR. STADIU PROCESUAL: FOND.

IN DATA DE 18.06.2021, ANTREPRENORUL SI-A ASUMAT SOLUTIA FINALA IN VEDEREA STABILIZARII NECESARE IN ZONA KM 19+300

1. AUTOSTRĂZI

SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021

1.1. AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI - IUNIE 2021

Page 2: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021 1

13 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA SEBES - TURDA 0+000 17+000ASOCIEREA IMPRESA PIZZAROTTI & C SPA POMPONIO

CONSTRUCTII SRLLANCRAM - SANTIMBRU LOT 1 17 96.01%

93.86 % (DIN VALOAREA DE

CONTRACT ACCEPTATA)02.12.2014

DESCHIDERE TRAFIC - 03.12.2020

FINALIZARE CONTRACT: AUGUST

2021

DESCHIDERE TRAFIC (RESPECTIV 14,8

KM AUTOSTRADA, BRETELE 5,6 - NOD

RUTIER SEBES, BRETELE - 1,3 NOD

RUTIER ALBA IULIA NORD, RESPECTIV

NOD RUTIER ALBA IULIA SUD IN

DATA DE 03.12.2020.

541.73 MIL. LEI FARA TVA

CONFORM GRAFICULUI DE LUCRARI INAINTAT DE ANTREPRENOR CONTRACTUL SE VA FINALIZA IN LUNA IUNIE 2021, DUPA FINALIZAREA LUCRARILOR A

CELOR 2.2 KM DE AUTOSTRADA, A PASAJULUI PESTE CF 201A DE LA KM 15+350 CALEA 2, NODULUI RUTIER SEBES CU 4 BRETELE RESPECTIV BRETEA

NR.1,2,3,4 SI STRUCTURI AFERENTE ACESTOR BRETELE, RESPECTIV NOD RUTIER ALBA IULIA NORD CU BRETELE 2 SI 4, AFLATE IN EXECUTIE.

DESCHIDEREA TRAFICULUI PE TOATA LUNGIMEA SECTORULUI DE AUTOSTRADA VA AVEA LOC DOAR DUPA FINALIZAREA LUCRARILOR SI PE LOTUL 2,

DEOARECE DESCARCAREA TRAFICULUI ESTE POSIBILA DOAR PRIN NODUL ALBA IULIA NORD DE LA KM 15+500.

14 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 91+761 122+110 ASTALDI SPA (ITALIA) CURTEA DE ARGES - PITESTI SECTIUNEA 5 30.35 0% 1.34%

IUNIE 2020 - EMITERE ORDIN ETAPA

DE PROIECTARE, AUTORIZATIA DE

CONSTRUIRE NR.31/17.06.2021

2025 IN CF CU PREVEDERILE CTR

DURATA DE REALIZARE A ACESTUI

CTR ESTE DE 60 DE LUNI, RESPECTIV:

12 LUNI PERIODA DE PROIECTARE SI

48 DE LUNI PENTRU EXECUTIA

LUCRARILOR. PERIOADA DE

GARANTIE A LUCRARILOR OFERTATA

DE ASTALDI SPA ESTE DE 120 DE LUNI

ANUL 2025 1710 MIL. LEI FARA TVA

22.06.2020 – ORDIN DE INCEPERE FAZA PROIECTARE (12 LUNI)

CONTRACT DE SERVICII NR.92/58937/11.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 5 – CURTEA DE ARGES – PITESTI KM 92+600-

KM 122+950" SEMNAT CU ASOCIAREA EGIS INTERNATIONAL S.A.S – SEARCH CORPORATION S.R.L.- ITALROM INGINERIE INTERNATIONALA S.R.L.-

METROUL S.A, A INLOCUIT SUPERVIZORUL DRDP BUCURESTI INCEPAND CU DATA DE 01.10.2020

In data de 30.12.2020 a fost publicata Hotararea de Guvern nr.1134 pentru realizarea exproprierilor pentru suprafetele de teren aflate pe aza localităţilor

Budeasa, Curtea de Argeș, Mălureni și Municipiul Pitești, din județul Argeș.

17.02.2021 - S-A EMIS DECIZIA DE EXPROPRIERE NR. 377/2020 PENTRU IMOBILELE DE PE RAZA LOCALITATILOR BUDEASA, CURTEA DE ARGES,

MALURENI SI MUN. PITESTI

PROCEDURA DE EXPROPRIERE INTERGAL FINALIZATA

15 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 0+000 13+170 PORR CONSTRUCT SRL LOT 1: KM 0+000 - KM 13+170SECTIUNEA 1: SIBIU - BOITA (KM

0+000 - KM 14+150), LOT 113.17 42.45% 35.83%

29.05.2019 - EMITERE ORDIN DE

INCEPERE ETAPA DE PROIECTARE,

30.03.2020 - EMITERE ORDIN DE

INCEPERE ETAPA EXECUTIE LUCRARI

28.05.2023 ANUL 2023 612.65 MIL. LEI FARA TVA

PROIECTUL TEHNIC A FOST FINALIZAT SI APROBAT DE CATRE CNAIR SA IN DATA DE 01.04.2020.

AUTORIZATIA DE CONSTRUIRE A FOST EMISA IN DATA DE 09.03.2020.

CONTRACT DE SERVICII NR. 92/61673/22.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 1 –SIBIU – BOITA KM 0+000-KM 14+150""

ASOCIEREA TPF INGINERIE S.R.L. - SEPTEMBRIE CONSULTING S.R.L. A INLOCUIT SUPERVIZORUL DRDP BUCURESTI INCEPAND CU DATA DE 19.10.2020

16 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI DRUM NATIONAL POD BRAILA ASOCIEREA ASTALDI S.P. A - IHI INFRASTRUCTURE SYSTEM CO. LTD.POD SUSPENDAT PESTE DUNARE IN

ZONA BRAILA1

DRUM BRAILA-JIJILA - 19,095 KM;

DRUM DE LEGATURA CU DN22

SMARDAN-MACIN - 4,328 KM

39.00% 48.66% 21.12.2018

SECTIUNEA 2 DECEMBRIE 2021

TOTAL CONTRACT: ESTIMAT

DECEMBRIE 2022

DECEMBRIE 2021 SECTIUNEA 2

PODUL SUSPENDAT 1.996 MLD. LEI FARA TVA CONTRACT IN DERULARE.

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

1AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE

LUCRARIAUTOSTRADA

AUTOSTRADA BRASOV - TARGU MURES - CLUJ -

ORADEA4+200 30+550

SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE

ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE

SECTIUNEA 3C, SUBSECTIUNEA 3C1

SUPLACUL DE BARCAU - CHRIBIS

SUBSECTIUNEA 3C1: SUPLACU DE

BARCAU - CHIRIBIS *KM 4+200

COINCIDE CU KM 80+054.044 DIN

3B5

26.35 0% 0% 2021 2023 ANUL 2023 465.14 MIL. LEI FARA TVA DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL DE MAI JOS

http://www.cnadnr.ro/

sites/default/files/AUTO

STRADA_BRA%C8%98O

V_T%C3%82RGU%20M

URE%C8%98_CLUJ_ORA

DEA_CALENDAR.pdf

2AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE

LUCRARIAUTOSTRADA

AUTOSTRADA BRASOV - TARGU MURES - CLUJ -

ORADEA25+500 66+500

SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE

ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE

SECTIUNEA 3B,SUBSECTIUNEA 3B3:

POARTA SALAJULUI - ZALAU (KM

25+500- KM 40+637) +

SUBSECTIUNEA 3B4: ZALAU -

NUSFALAU (KM 40+660- KM

66+500), INCLUSIV TUNEL RUTIER

MESES

SUBSECTIUNEA 3B3: POARTA

SALAJULUI - ZALAU (KM 25+500 - KM

40+637) +

SUBSECTIUNEA 3B4: ZALAU -

NUSFALAU (KM 40+660 - KM

66+500), INCLUSIV TUNEL RUTIER

MESES

41 2021 2025 ANUL 2025

3926.81 MIL. LEI FARA TVA, DIN

CARE VALOAREA TUNELULUI MESES

ESTE DE 1075.36 MIL LEI FARA TVA

DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL DE MAI JOS

http://www.cnadnr.ro/

sites/default/files/AUTO

STRADA_BRA%C8%98O

V_T%C3%82RGU%20M

URE%C8%98_CLUJ_ORA

DEA_CALENDAR.pdf

3AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE

LUCRARIAUTOSTRADA

AUTOSTRADA DE CENTURA A MUNICIPIULUI

BUCURESTI (A0) 2+500 20+000

SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE

ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIESECTOR NORD LOT 1 17.5 0% 0% 2020 2023 ANUL 2023

842.14 MIL. LEI FARA TVA (VALOARE

ESTIMATA PROCEDURA DE LICITATIE)

746.763.568,57 LEI, FARA TVA

(VALOARE OFERTA CASTIGATOARE)

http://www.cnadnr.ro/

sites/default/files/AUTO

STRADA_DE_CENTURA_

A_MUNICIPIULUI_BUC

URE%C8%98TI_CALEND

AR.pdf

4AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE

LUCRARIAUTOSTRADA

AUTOSTRADA DE CENTURA A MUNICIPIULUI

BUCURESTI (A0) 39+000 47+600

SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE

ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIESECTOR NORD LOT 3 8.5 0% 0% 2020 2024 466.28 MIL. LEI FARA TVA

http://www.cnadnr.ro/

sites/default/files/AUTO

STRADA_DE_CENTURA_

A_MUNICIPIULUI_BUC

URE%C8%98TI_CALEND

AR.pdf

5AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE

LUCRARIAUTOSTRADA AUTOSTRADA SIBIU - PITESTI 44+500 81+900

SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE

ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIECORNETU - TIGVENI SECTIUNEA 3 37.4 0% 0% 2021 2025 4784.02 MIL. LEI FARA TVA

TERMEN DEPUNERE OFERTE PROCEDURA DE ATRIBUIRE CONTRACT DE PROIECTARE SI EXECUTIE - 27.11.2020

PANA LA TERMENUL LIMITA AU DEPUS OFERTE 15 AGENTI ECONOMICI.

VALOAREA ESTIMATA A CONTRACTULUI ESTE DE 5.324.779.469,00 LEI FARA TVA.

DURATA CONTRACTULUI ESTE DE: 14 LUNI PERIOADA DE PROIECTARE, 59 LUNI PERIOADA DE EXECUTIE ŞI 60 LUNI PERIOADA DE GARANTIE A

LUCRARILOR.

TRASEUL ARE O LUNGIME DE 37.4 KM

SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE.

PRINCIPALELE LUCRARI ALE ACESTEI SECTIUNI SUNT:

• 95 DE PODURI SI PASAJE

• TUNEL CU DOUA GALERII INDEPENDENTE IN LUNGIME DE 1.7 KM/ GALERIE

• NOD RUTIER CORNETU SI NOD RUTIER VALENI

• ECODUCT IN ZONA LOCALITATII CALINESTI

http://www.cnadnr.ro/

sites/default/files/AUTO

STRADA_SIBIU_PITE%C

8%98TI_CALENDAR.pdf

6AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE

LUCRARIAUTOSTRADA AUTOSTRADA SIBIU - PITESTI 13+170 44+500

SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE

ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIESECTIUNEA 1, LOT 2 SI SECTIUNEA 2

SECTIUNEA 1: SIBIU - BOITA, LOT 2 SI

SECTIUNEA 2: BOITA - CORNETU31.33 0% 0% 2021 2025 ANUL 2025 4081.78 MIL. LEI FARA TVA

http://www.cnadnr.ro/

sites/default/files/AUTO

STRADA_SIBIU_PITE%C

8%98TI_CALENDAR.pdf

7AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE

LUCRARIAUTOSTRADA AUTOSTRADA SIBIU - PITESTI 81+900 91+761

SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE

ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIETIGVENI - CURTEA DE ARGES SECTIUNEA 4 9.86 0% 0% 2021 2025

ESTIMAT 2025 IN FUNCTIE DE DATA

LA CARE VA FI FINALIZATA

PROCEDURA DE ATRIBUIRE

2000.17 MIL. LEI FARA TVA

IN DATA DE 04.03.2021 AU FOST TRANSMISE ADRESELE DE COMUNICARE A REZULTATULUI PROCEDURII DE ATRIBUIRE A CONTRACTULUI.

OFERTANTUL DESEMNAT CASTIGATOR ESTE S.C. PORR CONSTRUCT S.R.L., CU PRETUL DE 1.678.873.121,77 LEI FARA TVA.

AU FOST DEPUSE 2 CONTESTATII

CONTRACTUL VA FI SEMNAT IN FUNCTIE DE SOLUTIA INSTANTEI

http://www.cnadnr.ro/

sites/default/files/AUTO

STRADA_SIBIU_PITE%C

8%98TI_CALENDAR.pdf

8AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE

LUCRARIAUTOSTRADA AUTOSTRADA PLOIESTI - BUZAU 0+000 63+250

SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE

ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIEPLOIESTI - BUZAU 63.25

ORDIN DE INCEPERE 12.11.2018 -

ETAPA PROIECTARE2021 1146.6 MIL. LEI FARA TVA

A FOST LANSATA PROCEDURA DE LICITATIE PENTRU ATRIBUIREA CONTRACTULUI DE EXECUTIE LUCRARI 01.06.2021. TERMEN DE DEPUNERE A

OFERTELOR 04.08.2021

http://www.cnadnr.ro/

sites/default/files/A7%2

0PLOIE%C8%98TI%20-

%20BUZ%C4%82U.pdf

1.2. AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI - IUNIE 2021

Page 3: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021 1

9AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE

LUCRARIAUTOSTRADA AUTOSTRADA LUGOJ - DEVA 27+620 56+220

SE VA STABILI IN URMA FINALIZARII PROCEDURII DE LICITATIE

ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE

MARGINA - HOLDEA

SECTIUNEA E (KM 47+090 - KM

56+220) SI FINALIZARE SECTIUNEA D

LOT 228.6 (9.13 KM SECTIUNEA E SI

FINALIZARE SECTIUNE D)27.11.2013

1. FINALIZAT SECT. A - C (KM 27+620 -

KM 43+060);

2. SECTIUNEA E SI REST DE EXECUTAT

DIN SECTIUNEA D (KM 43+060 - KM

56+220) - ESTIMAT DECEMBRIE 2023

ANUL 2025

1560.50 MIL LEI FARA TVA -

REPREZINTA VAL ESTIMATA TOTALA,

CARE CONTINE ATAT VAL ESTIMATA

A LUCRARILOR, CAT SI VAL

POSIBILELOR LUCRARI NOI SIMILARE

AU FOST DEPUSE NOUA CANDIDATURI PENTRU REALIZAREA ACESTEI PORTIUNI, DINTRE CARE SASE APARTIN UNOR ASOCIERI DE FIRME:

AKTOR S.A. (GRECIA)

ASOCIEREA SC ALSIM ALARKO SANAYI TESISLERI VE TICARET A.Ș – MAKYOL INSAAT SANAYI TURIZM VE TICARET A.S. (TURCIA)

ASOCIEREA FCC CONSTRUCCION SA – GULERMAK AGIR SANAYI INSAAT VE TAAHHUT A.S. (SPANIA – TURCIA)

ASOCIEREA IMPRESA PIZZAROTTI & CSPA – PIZZAROTTI SA – RETTER PROJECT MANAGEMENT SRL (ITALIA – ROMANIA)

ASOCIEREA TERNA SA – INTRACOM CONSTRUCTIONS SOCIETE ANONYME TECHNICAL AND STEEL CONSTRUCTIONS (INTRAKAT) (GRECIA)

KOLIN INSAAT TURIZM SANAYI VE TICARET ANONIM SIRKETI (TURCIA)

ASOCIEREA MAPA INSAAT VE TICARET A.S. – CENGIZ INSAAT SANAYI VE TICARET A.S. (TURCIA)

ASOCIEREA RIZZANI DE ECCHER SPA – OZGUN INSAAT TAAHHUT SANAYI VE TICARET LIMITED STI – CIPA SPA (ITALIA – TURCIA)

STRABAG SRL (ROMANIA)

DETALII PRIVIND CALENDARUL PROCEDURII SE VOR VIZUALIZA LA LINK-UL DE MAI JOS:

http://www.cnadnr.ro/

sites/default/files/AUTO

STRADA_LUGOJ_DEVA_

CALENDAR.pdf

10AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE

LUCRARIAUTOSTRADA DRUM DE LEGATURA A3 0+000 18+960

PROCEDURA DE LICITATIE ATRIBUIRE CONTRACT PROIECTARE SI

EXECUTIE IN DERULARE

LEGATURA CENTURA ORADEA

(GIRATIA SANTANDREI) -

AUTOSTRADA A3 (BIHARIA)

18.96 0% 0% 2020 2023 DECEMBRIE 2023 546.4 MIL. LEI FARA TVA DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL ALATURAT

http://www.cnadnr.ro/

sites/default/files/DRU

MURI_NA%C8%9AIONA

LE_%C8%98I_VARIANTE

_DE_OCOLIRE_CALEND

AR.pdf

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

1 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA BRASOV - BACAU 0+000 165+000

SEARCH CORPORATION& PRIMACONS GRUP SRL - CONTRACT

PROIECTARE ELABORARE STUDIU DE FEZABILITATE SI PROIECT

TEHNIC

(VALOARE CONTRACT PROIECTARE: 20.093.359,86 LEI FARA TVA)

BRASOV - BACAU LOT 1 165 0% 0%

22.05.2020 - DATA SEMNARII

CONTRACTULUI DE PRESTARI

SERVICII DE PROIECTARE (STUDIU DE

FEZABILITATE SI ELABORARE PROIECT

TEHNIC)

10.07.2020 - ORDIN INCEPERE ETAPA

DE PROIECTARE

2023 - FINALIZARE PROIECTARE

(SF+PT)

ANUL 2023 - FINALIZARE

PROIECTARE (SF+PT)8858.21 MIL. LEI FARA TVA

DURATA CONTRACTULUI ESTE DE 30 LUNI.

ORDINUL DE INCEPERE: 10.07.2020

PRESTATORUL A ELABORAT ANALIZA MULTICRITERIALA PRIVIND ALEGEREA ALTERNATIVELOR DE TRASEU, ETAPA 1.

A FOST AVIZAT IN CTE CNAIR SA - ANALIZA MULTICRITERIALA ETAPA 1.

AU FOST FINALIZATE STUDIILE DE TEREN AFERENT PROIECTULUI PRELIMINAR (STUDII TOPOGRAFICE SI GEOTEHNICE).

ESTE IN DERULARE ANALIZA MULTICRITERIALA NR. 2

2 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA A1 SI A3 SEARCH CORPORATION SRL

ELABORARE STUDIU DE FEZABILITATE

SI PROIECT TEHNIC DE EXECUTIE

PENTRU 6 NODURI RUTIERE PE A1 SI

A3 IN ZONA DE VEST A ROMANIEI

A1(KM 326+155) - DJ

704(CUGHIR),A1(KM 362+813) - DC

129(SANTUHALM),A1(KM 485+030 -

DJ 609E(RECAS),A1(KM 450+210) - DJ

609(BETTHAUSEN),A1(KM 528+509) -

DJ 682G(CRUCENI),A3(KM 39+940) -

DN1P(SPINUS)

0% 0% 22.04.2021 22.06.2022

CONTRACT SEMNAT IN DATA DE 17.03.2021

ORDINUL DE INCEPERE A ACTIVITATII DE PROIECTARE A FOST EMIS IN DATA DE 22.04.2021

DURATA CONTRACTULUI ESTE DE 14 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI, DIN CARE:

-6 LUNI PENTRU ELABORAREA STUDIULUI DE FEZABILITATE,

- 4 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA LUCRARILOR DE CONSTRUIRE,

- 3 LUNI PENTRU ELABORAREA PROIECTULUI TEHNIC DE EXECUTIE SI

- 1 LUNI PENTRU ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFICIARULUI.

A AVUT LOC SEDINTA DE INCEPUT IN DATA DE 22.04.2021. A FOST TRANSMIS RAPORTUL DE INCEPUT. AU FOST FORMULATE OBSERVATII LA RAPORTUL

DE INCEPUT.A FOST APROBAT RAPORTUL DE INCEPUT.

3 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADAAUTOSTRADA TARGU NEAMT - IASI -

UNGHENI0+000 100+140 SC CONSITRANS S.R.L.

TARGU NEAMT - IASI (LETCANI) -

UNGHENI100.14

2021 -SERVICII DE PROIECTARE FAZA

S.F. + P.A.C. + P.T.E. SECTIUNE TARGU

NEAMT - IASI-UNGHENI

2023 - FINALIZARE PROIECTAREANUL 2025 - PERIOADA ESTIMATA

DESCHIDERE TRAFIC PENTRU

PRIMELE SECTIUNI

58.83 MIL. LEI FARA TVA (VALOARE

CONTRACT

COMPLETARE/REVIZUIRE/ACTUALIZA

RE S.F. SI ELABORARE P.A.C. + P.A.D.

+ P.T.E)

IN DATA DE 08.04.2021 A FOST SEMNAT CONTRACTUL DE SERVICII „COMPLETARE/ REVIZUIRE/ ACTUALIZARE STUDIU DE FEZABILITATE SI ELABORARE

P.A.C., P.A.D. SI P.T.E. PENTRU OBIECTIVUL „AUTOSTRADA TARGU-NEAMT – IASI – UNGHENI” CU SC CONSITRANS S.R.L.

PRETUL CONTRACTULUI ESTE DE 58.830.448,35 LEI FARA TVA

IN DATA DE 07.05.2021 A AVUT LOC SEDINTA DE INCEPUT

DURATA DE REALIZARE A SERVICIILOR DE PROIECTARE ESTE DUPA CUM URMEAZA:

12 LUNI PENTRU REALIZAREA STUDIULUI DE FEZABILITATE;

5 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA EXECUTARII LUCRARILOR DE CONSTRUIRE (PAC) SI OBTINEREA AUTORIZATIEI DE

CONSTRUIRE;

5 LUNI PENTRU REALIZAREA PROIECTULUI TEHNIC DE EXECUTIE (PTE)

4 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA SIBIU - BRASOV 0+000 68+050CONSITRANS

(VALOARE CONTRACT PROIECTARE: 16.313.855,49 FARA TVA)SIBIU - FAGARAS LOT 1 68.05 22.00% ORDIN DE INCEPERE 11.05.2015

TRIM III 2021/ FINALIZARE

PROIECTARE FAZA REVIZUIRE STUDIU

DE FEZABILITATE

FINALIZARE PROIECTARE (EMITERE

ACORD DE MEDIU) - TRIM. III 20215170 MIL. LEI FARA TVA

CONTRACT REVIZUIRE STUDIU DE FEZABILITATE IN DERULARE - STUDIUL DE FEZABILITATE A FOST AVIZAT IN CADRUL CTE, PROCEDURA DE MEDIU IN

DERULARE

5 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA SIBIU - BRASOV 0+000 48+410 FAGARAS - BRASOV LOT 2 48.41 0% 0% 2021 2023 17.712 MIL LEI FARA TVA

http://www.cnadnr.ro/

sites/default/files/STUD

II_DE_FEZABILITATE_%

C8%98I_PROIECTE_TEH

NICE_CALENDAR.pdf

6 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA TARGU MURES - TARGU NEAMT 0+000 211+000PROIECTANT: INGENIERIA ESPECIALIZADA OBRA CIVIL E

INDUSTRIAL SATARGU MURES - TARGU NEAMT LOT 1 211 52% 11% 28.05.2019

25.07.2021 (CONFORM ACT

ADITIONAL LA CTR DE PRESTARI

SERVICII)

ANUL 2021 - FINALIZARE

PROIECTARE

2025 - PERIOADA ESTIMATA PENTRU

DESCHIDEREA PRIMELOR SECTIUNI

17.58 MIL. LEI FARA TVA

IN DATA DE 28.05.2019 A FOST SEMNAT CONTRACTUL DE SERVICII 92/36788 AFERENT „COMPLETARE STUDIU DE FEZABILITATE PENTRU AUTOSTRADA

TARGU MURES – TARGU NEAMT”.

TERMEN INITIAL DE FINALIZARE A REVIZUIRII STUDIULUI DE FEZABILITATE - 25.01.2021.

CONTRACT DE REVIZUIRE SF IN DERULARE

IN DATA DE 31.07.2020 A FOST SEMNAT ADITIONALUL NR. 1, PRIN CARE SE PRELUNGESTE TERMENUL DE FINALIZARE AL SERVICIILOR DE PROIECTARE

CU 6 LUNI.

TERMEN DE FINALIZARE CONFORM ACT ADITIONAL - 25.07.2021

EMITEREA DECIZIEI ETAPEI DE INCADRARE INITIALE ANPM IN DATA DE 18.09.2020.

IN DATA DE 31.09.2020 A AVUT LOC SEDINTA PENTRU AVIZAREA IN CTE / CNAIR A TRASEULUI CORECTAT CONFORM CONSTRANGERILOR IDENTIFICATE.

PENTRU FINALIZAREA AVIZARII CTE A FOST SOLICITATA COMPLETAREA DOCUMENTATIEI.

IN DATA DE 05.11.2020 A FOST AVIZAT TRASEUL FINAL IN COMISIA CTE CNAIR.

IN DATA DE 27.01.2021 A FOST APROBAT STUDIU TOPOGRAFIC. MASURATORI TOPOGRAFICE CU TEHNOLOGIA LIDAR

IN DATA DE 25.03.2021 A FOST APROBAT STUDIUL GEOTEHNIC AFERENT TRONSON: DITRAU - TARGU NEAMT, SECTOR 4 KM 95+600 – KM 118+800.

AU FOST FINALIZATE INVESTIGATIILE IN SITU PE JUD. MURES SI JUD. HARGHITA SI AU FOST AVIZATE STUDIILE ARHEOLOGICE ETAPA 2 JUD. HARGHITA

SI JUD. MURES

- IN DATA DE 16.04.2021 A FOST INAINTATA O VARIANTA PRELIMINARA A STUDIULUI DE FEZABILITATE

AU FOST FINALIZATE INVESTIGATIILE IN SITU PE JUD. NEAMT SI JUD. IASI SI AU FOST AVIZATE STUDIILE ARHEOLOGICE ETAPA 2 JUD. NEAMT SI JUD. IAS

7 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA TIMISOARA - MORAVITA 0+000 60+000

SEARCH CORPORATION & EGIS ROMANIA- CONTRACT PROIECTARE

ELABORARE SF SEMNAT IN DATA DE 4 MARTIE 2020

(VALOARE CONTRACT PROIECTARE: 8.727.474,68 FARA TVA)

TIMISOARA – MORAVITA LOT 1 60 04.03.2020 - ELABORARE SF

MAI 2022 - TERMEN FINALIZARE

PROIECTARE; PERIOADA

CONTRACTUALA DE PRESTARE A

SERVICIILOR - 24 LUNI

MAI 2022 - TERMEN FINALIZARE

PROIECTARE141.6 MIL. LEI FARA TVA

ETAPA DE PROIECTARE (ELABORARE STUDIU DE FEZABILITATE) IN DERULARE.

S-A AVIZAT IN CTE-CNAIR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU, ETAPA 1

A FOST TRANSMISA DOCUMENTATIA AMC ETAPA 2. DOCUMENTATIA IN CURS DE ANALIZA LA BENEFICIAR SI LA EXPERTII JASPERS.IN DATA DE

27.05.2021 RESPECTIV 02.06.2021 A FOST ORGANIZATA O SEDINTA DE ANALIZA CU EXPERTII JASPERS.PRESTATORUL IMPLEMENTEAZA OBSERVATIILE

JASPERS

8 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA BACAU - PASCANI 0+000 77+394

INGINERIA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL SA -

CONTRACT ELABORARE SF SI PT IN DERULARE

(VALOARE CONTRACT PROIECTARE: 16.950.944,23 FARA TVA)

BACAU - PASCANI LOT 1 77.283 0% 21%ORDIN DE INCEPERE 01.03.2019 -

ETAPA PROIECTARE2021

ANUL 2021 - FINALIZARE ETAPA

PROIECTARE1750.27 MIL. LEI FARA TVA

ETAPA DE PROIECTARE (ELABORARE STUDIU DE FEZABILITATE) IN DERULARE

S-A AVIZAT IN CTE-CNAIR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU, ETAPA 1 SI ETAPA 2 (AMC1 + AMC2).

SE EFECTUEAZA INVESTIGATII GEOTEHNICE - PROCENT DE REALIZARE 95%.

SE EFECTUEAZA INVESTIGATII ARHEOLOGICE - IN CURS DE ANALIZA RAPORTUL DE DIAGNOSTIC INTRUZIV.

S-AU OBTINUT TOATE CELE 3 CERTFICATE DE URBANISM.

IN PREZENT SUNT IN CURS DE OBTINERE AVIZELE.

PRESTATORUL A INAINTAT STUDIUL DE FEZABILITATE -Au fost emise observatiiA FOST ANALIZAT IN CADRUL CTE SIGURANTA CIRCULATIEI PROIECTUL-IN CURS DE IMPLEMENTARE OBSERVATII.

9 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA BUZAU - FOCSANI 0+000 82+440CONSITRANS - CONTRACT ELABORARE SF SI PT

(VALOARE CONTRACT PROIECTARE: 13.933.291,10 LEI, FARA TVA)BUZAU - FOCSANI 82.44 10.35%

ORDIN DE INCEPERE 12.11.2018 -

ETAPA PROIECTARE2021 FINALIZARE 2021 1270.62 MIL. LEI FARA TVA

CONTRACT PROIECTARE IN DERULARE - ETAPA ELABORARE STUDIU DE FEZABILITATE ANALIZA MULTICRITERIALA ETAPA 1 SI ETAPA 2.

A FOST AVIZAT IN CADRUL CTE CNAIR STUDIUL SI RAPORTUL ALTERNATIVELOR DE TRASEU (AMC 1 SI AMC 2)

INVESTIGATIILE GEOTEHNICE AU FOST REALIZATE IN PROPORTIE DE 100%. IN CURS DE ELABORARE TESTELE DE LABORATOR.

A FOST AVIZAT IN CADRUL COMISIEI TEHNICE PENTRU SIGURANTA CIRCULATIEI NODURILE RUTIERE SI DOTARILE AUTOSTRAZII.

A FOST INAINTAT STUDIUL DE FEZABILITATE - IN CURS DE ANALIZA

10 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA FOCSANI - BACAU 0+000 96+052CONSITRANS - CONTRACT ELABORARE SF SI PT

(VALOARE CONTRACT PROIECTARE: 20.123.408,52 LEI, FARA TVA)FOCSANI - BACAU 96.052 0% 0.37%

ORDIN DE INCEPERE 10.01.2019 -

ETAPA PROIECTARE2021

ANUL 2021 - FINALIZARE ETAPA

PROIECTARE1927.35 MIL. LEI FARA TVA

ETAPA DE PROIECTARE (ELABORARE STUDIU DE FEZABILITATE) IN DERULARE.

S-A AVIZAT IN CADRUL CTE CNAIR SA - STUDIUL SI RAPORTUL ALTERNATIVELOR DE TRASEU (ANALIZA MULTICRITERIALA ETAPA 1 SI ANALIZA

MULTICRITERIALA ETAPA 2).

AU INCEPUT INVESTIGATIILE ARHEOLOGICE.

STUDIILE GEOTEHNICE IN CURS DE REALIZARE-PROCENTUL DE REALIZARE ESTE DE 61%.

STUDIUL ARHEOLOGIC ETAPA NR. 2 A FOST TRANSMIS LA MINISTERELE DE CULTURA DE PE RAZA JUDETELOR VRANCEA SI BACAU IN VEDEREA OBTINERII

AVIZELOR.

IN DATA DE 09.03.2021 AU FOST ANALIZATE IN CADRUL COMISIEI TEHNICE PENTRU SIGURANTA CIRCULATIEI NODURILE RUTIERE SI DOTARILE

AUTOSTRAZII

IN DATA DE 05.05.2021 A FOST INAINTAT STUDIUL DE FEZABILITATE SUB FORMA DRAFT- Au fost emise observatii

1.3. AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) - IUNIE 2021

Page 4: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021 1

11 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 44+800 68+000

SECTIUNEA 6, CONEXIUNE DN 73C CU

AUTOSTRADA SIBIU - PITESTI (NOD

TIGVENI) SI MODERNIZARE DN 73C

(KM 44+800 – KM 68+000)

SECTIUNEA 6 23.2 0% 0% 2020 2021ANUL 2021 - FINALIZARE

PROIECTARE4364.7 MIL. LEI FARA TVA

http://www.cnadnr.ro/

sites/default/files/STUD

II_DE_FEZABILITATE_%

C8%98I_PROIECTE_TEH

NICE_CALENDAR.pdf

12 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADAAUTOSTRADA BAIA MARE - DEJ - BISTRITA -

VATRA DORNEI - SUCEAVA

BAIA MARE - DEJ - BISTRITA - VATRA

DORNEI - SUCEAVA

LOT 1 BAIA MARE - BISTRITA

LOT 2 BISTRITA - VATRA DORNEI

LOT 3 VATRA DORNEI - SUCEAVA

335 2020 2022 ANUL 2022 6681.19 MIL. LEI FARA TVA

IN DATA DE 10.03.2021, CNAIR A SEMNAT CONTRACTELE PENTRU LOTURILE 2 SI 3, CU URMATORII ANTREPRENORI:

LOTUL 2: BISTRITA - VATRA DORNEI - SC EXPLAN SRL., CU PRETUL DE 15.793.026,12 LEI FARA TVA.

LOTUL 3: VATRA DORNEI – SUCEAVA - ASOCIEREA BEST CONSULTING & DESIGN SRL – INGENIERIA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL, CU PRETUL

DE 14.475.000,00 LEI FARA TVA.

PENTRU FIECARE DINTRE CELE TREI LOTURI, DURATA CONTRACTULUI ESTE DE 18 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI.

LOTUL 1: BAIA MARE – BISTRITA

A FOST DESEMNATA CASTIGATOARE ASOCIEREA SEARCH CORPORATION – EGIS INTERNATIONAL SAS – EGIS ROMANIA S.A. – SC FORMIN S.A., CU PRETUL

DE 15.206.688,64 LEI FARA TVA.

A FOST DEPUSA O CONTESTIE PENTRU LOTUL 1

DETALII STADIU PROCEDURA DE ATRIBUIRE IN LINK-UL DE MAI JOS.

http://www.cnadnr.ro/

sites/default/files/STUD

II_DE_FEZABILITATE_%

C8%98I_PROIECTE_TEH

NICE_CALENDAR.pdf

13 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA PLOIESTI - BRASOV SC CONSITRANS S.R.L.

PLOIESTI - BRASOV (FARA VARIANTA

DE OCOLIRE COMARNIC SI SECTOR

RASNOV - CRISTIAN)

97.3 0% 0%

2021 - DEMARARE SERVICII DE

PROIECTARE FAZA S.F. + P.A.C. +

P.T.E.

2023 - FINALIZARE SERVICII DE

PROIECTARE FAZA S.F. + P.A.C. +

P.T.E.

1000.8 MIL. LEI FARA TVA

CONTRACT IN DERULARE.

S-AU EFECTUAT VIZITE IN TEREN CU REPREZENTANTI DIN PARTEA BENEFICIARULUI SI DIN PARTEA PRESTATORULUI PENTRU IDENTIFICAREA

EVENTUALELOR CONSTRANGERI.

A FOST APROBAT DE CATRE BENEFICIAR RAPORTUL DE INCEPUT SI RAPORTUL DE PROGRES NR. 1.

https://ploiesti-

brasov.ro/

14 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADAPOD PESTE PRUT LA UNGHENI

S.C. EXPERT PROIECT 2002 S.R.L. POD PESTE PRUT LA UNGHENI 1 80% 45%

2016 - DEMARARE PROIECTARE POD

UNGHENI; 2020 - DEMARARE

PROIECTARE SECTIUNEA IASI -

UNGHENI

2021 - FINALIZARE PROIECTARE FAZA

SF, DEMARARE SERVICII DE

PROIECTARE SI EXECUTIE POD

UNGHENI

ANUL 2024 - DESCHIDERE TRAFIC

POD PESTE PRUT LA UNGHENI0.8 MIL. LEI FARA TVA

2.POD UNGHENI - STUDIU DE FEZABILITATE FINALIZAT CU EXCEPTIA ACORDULUI DE MEDIU ;

PROCEDURA DE MEDIU IN DERULARE

OBTINERE DEROGARE DE LA ART ART. 23 ALIN. (2) SI ALE ART. 27 ALIN. (1) DIN ORDONANTA DE URGENTA A GUVERNULUI

NR. 57/2007 PRIVIND REGIMUL ARIILOR NATURALE PROTEJATE, PRIN OUG NR. 105/2020, SEMNARE MEMORANDUM IN VEDERE PROMOVARII

ACORDULUI BILATERAL ROMANIA-MOLDOVA NECESAR OBTINERII ACORDULUI DE MEDIU.

ESTE IN PREGATIRE LA MTIC ACORDUL BILATEARAL ROMANIA-MOLDOVA.

IN DATA DE 24.08.2020 A FOST EMISA DECIZIA ETAPEI DE EVALUARE INITIALA DE CATRE A.N.P.M. IASI.

IN DATA DE 24.08.2020 A FOST EMISA DECIZIA ETAPEI DE INCADRARE INITIALA NR. 133/2020 ANMP .

PENTRU CONTINUAREA PROCEDURII DE OBTINERE A ACORDULUI DE MEDIU S-A TRANSMIS MEMORIUL DE PREZENTARE CATRE APM IASI.

IN DATA DE 22.02.2021 A FOST EMISA DECIZIA ETAPEI DE INCADRARE NR. 15 DE CATRE APM IASI.

15 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA A4 16+700 16+700 SEARCH CORPORATION SRL

ELABORARE STUDIU DE FEZABILITATE

SI PROIECT TEHNIC DE EXECUTIE

PENTRU NOD RUTIER CUMPANA A4

(KM 16+700)-DN 39E

0% 0% 26.10.2020 26.06.2021 674,39 MIL LEI FARA TVA

CONTRACT SEMNAT IN DATA DE 23.09.2020.

ORDINUL DE INCEPERE A ACTIVITATII DE PROIECTARE A FOST EMIS IN DATA DE 26.10.2020

DURATA CONTRACTULUI ESTE DE 8 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI, DIN CARE:

-3 LUNI PENTRU ELABORAREA STUDIULUI DE FEZABILITATE,

- 2 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA LUCRARILOR DE CONSTRUIRE,

- 1 LUNI PENTRU ELABORAREA PROIECTULUI TEHNIC DE EXECUTIE SI

- 1 LUNI PENTRU ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFICIARULUI.

A AVUT LOC SEDINTA DE INCEPUT IN DATA DE 26.10.2020.

S-A EMIS ORDINUL ADMINISTRATIV NR. 1 - APROBARE EXPERTI NON CHEIE.

A FOST TRANSMISA DE CATRE PRESTATOR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU ETAPA 1-S-AU TRANSMIS OBSERVATII.

A FOST RELUATA ACTIVITATEA PROIECTANTULUI INCEPAND CU DATA DE 16.04.2021

A FOST AVIZATA IN CADRUL CTE CNAIR IN DATA DE 20.05.2021 ANALIZA MULTICRITERIALA ETAPA 1

16 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADAAUTOSTRADA BAIA MARE - DEJ - BISTRITA -

VATRA DORNEI - SUCEAVASC EXPLAN SRL BISTRITA - VATRA DORNEI LOT 2 83 2021 2022 ANUL 2022

15,79 MIL LEI FARA TVA (VALOARE

PROIECT SF)

IN DATA DE 10.03.2021, A FOST SEMNAT CONTRACTUL NR. 92/19393 – ELABORARE S.F DRUM DE MARE VITEZA BISTRITA-SUCEAVA: LOT 2 BISTRITA –

VATRA DORNEI.

DURATA CONTRACTULUI ESTE DE 18 LUNI.

ORDINUL DE INCEPERE AL CONTRACTULUI ESTE 22.04.2021.

IN DATA DE 04.06.2021 A AVUT LOC SEDINTA CU REPREZENTANTII PRIMARIILOR UNITATILOR ADMINISTRATIV TERITORIALE INTERSECTATE DE

VARIANTELE DE TRASEU, IN VEDEREA IDENTIFICARII CONSTRANGERILOR. - 14 LUNI ELABORARE STUDIU DE FEZABILITATE;

- 3 LUNI PREGATIRE DOCUMENTATIE DE ATRIBUIRE A CONTRACTULUI DE PROIECTARE SI EXECUTIE LUCRARI SI ACORDAREA SERVICIILOR DE ASISTENTA

TEHNICA BENEFIICIARULUI IN PERIOADA DERULARII PROCEDURII DE LICITATIE SI IN VEDEREA DEPUNERII SI APROBARII APLICATIEI DE FINANTARE DIN

FONDURI STRUCTURALE;

- 1 LUNA INTOCMIREA RAPORTULUI DE FINALIZARE A SERVICILOR;

17 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADAAUTOSTRADA BAIA MARE - DEJ - BISTRITA -

VATRA DORNEI - SUCEAVA

ASOCIEREA BEST CONSULTING & DESIGN S.R.L. – INGENIERIA

ESPECIALIZADA OBRA CIVIL E INDUSTRIAL S.A.VATRA DORNEI-SUCEAVA LOT 3 107 2021 2022

14,47 MIL LEI FARA TVA (VALOARE

PROIECT SF)

IN DATA DE 15.03.2021, A FOST SEMNAT CONTRACTUL NR. 92/20422 ELABORARE S.F DRUM DE MARE VITEZA BISTRITA-SUCEAVA: LOT 3 VATRA DORNEI-

SUCEAVA.

DURATA CONTRACTULUI ESTE DE 18 LUNI.

ORDINUL DE INCEPERE AL CONTRACTULUI ESTE 28.04.2021.

IN DATA DE 10.03.2021, A FOST SEMNAT CONTRACTUL NR. 92/19393 – ELABORARE S.F DRUM DE MARE VITEZA BISTRITA-SUCEAVA: LOT 2 BISTRITA –

VATRA DORNEI.

DURATA CONTRACTULUI ESTE DE 18 LUNI.

ORDINUL DE INCEPERE AL CONTRACTULUI ESTE 22.04.2021.

IN DATA DE 04.06.2021 A AVUT LOC SEDINTA CU REPREZENTANTII PRIMARIILOR UNITATILOR ADMINISTRATIV TERITORIALE INTERSECTATE DE

VARIANTELE DE TRASEU, IN VEDEREA IDENTIFICARII CONSTRANGERILOR.

- 14 LUNI ELABORARE STUDIU DE FEZABILITATE;

- 3 LUNI PREGATIRE DOCUMENTATIE DE ATRIBUIRE A CONTRACTULUI DE PROIECTARE SI EXECUTIE LUCRARI SI ACORDAREA SERVICIILOR DE ASISTENTA

TEHNICA BENEFIICIARULUI IN PERIOADA DERULARII PROCEDURII DE LICITATIE SI IN VEDEREA DEPUNERII SI APROBARII APLICATIEI DE FINANTARE DIN

FONDURI STRUCTURALE;

- 1 LUNA INTOCMIREA RAPORTULUI DE FINALIZARE A SERVICILOR;

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

1 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES DRUM EXPRES BRAILA - GALATI 0+000 11+088ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) -

SPEDITION UMB - TEHNOSTRADE S.R.L.BRAILA - GALATI LOT 1 11.08 0% 0%

ORDIN DE INCEPERE 01.07.2021 -

ETAPA PROIECTAREMAI 2024 ANUL 2024 371.42 MIL. LEI FARA TVA

IN DATA DE 15.04.2021, CNAIR A SEMNAT CONTRACTUL PENTRU ""PROIECTAREA SI EXECUTIA DRUMULUI EXPRES BRAILA - GALATI” CU ASOCIEREA SC

SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L.

VALOAREA CONTRACTULUI ESTE DE 371.416.131,09 LEI FARA TVA.

SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE.

DURATA CONTRACTULUI ESTE DE 34 LUNI, DIN CARE 10 LUNI PERIOADA DE PROIECTARE SI 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR. PERIOADA

DE GARANTIE ESTE DE 120 DE LUNI.

http://www.cnadnr.ro/

sites/default/files/DRU

MURI%20EXPRES_PROI

ECTARE_%C8%98I_EXEC

U%C8%9AIE_CALENDAR

.pdf

2 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRESDRUM EXPRES CRAIOVA - PITESTI

0+000 17+700 TIRRENA SCAVI S.P.A. (ITALIA)TRONSON 1 - CRAIOVA - ROBANESTI

(KM 0+000 - KM 17+700)

SECTOR 1: 0+000 - 1+800

SECTOR 2: 1+800 - 10+000

SECTOR 3: 10+000 - 17+700

17.7

24.97% (PROGRES CONSOLIDAT)

SECTOR 1: 12%

SECTOR 2: 10.11%

SECTOR 3: 44.65%

22.89%

27.12.2018 - PROIECTARE;

16.09.2019 - EXECUTIE SECTOR 3 ;

13.07.2020 - EXECUTIE SECTOR 1;

01.03.2021 - EXECUTIE SECTOR 2 -

km 5+245 - km 10+000

TRIM IV 2021 ANUL 2022 358.18 MIL. LEI FARA TVA

SECTOR 1: 0+000 - 1+850

IN DATA DE 03.07.2020 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE.

INCEPAND CU DATA DE 13.07.2020 A FOST EMIS ORDINUL DE INCEPERE EXECUTIE LUCRARI

SECTOR 2: 1+850 - 10+000

A FOST EMISA HG EXPROPRIERE NR. 843/2020 (aporx. de la km 5+190 -km 10+000). IN DATA DE 22.02.2021 A FOST OBTINUTA AUTORIZATIA DE

CONSTRUIRE.

PENTRU RESTUL ZONELE RAMASE NEEXPROPRIATE URMEAZA A FI INTOCMITA DOC. PENTRU HG DE EXPROPRIERE

SECTOR 3: 10+000 - 17+700 – IN EXECUTIE

3 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRESDRUM EXPRES CRAIOVA - PITESTI

17+700 36+200ASOCIEREA SA & PE CONSTRUCT SRL - SC SPEDITION UMB SRL - SC

TEHNOSTRADE SRL - SC CONSITRANS SRL

TRONSON 2 - ROBANESTI - BALS -

VALEA MARE (KM 17+700 - KM

57+550)

Lot 1 km 17+700 - km 36+200

LOT 1: KM 17+700 - KM 36+200 18.5 80.93% 41.81%

21.12.2018 - ACTIVITATEA DE

PROIECTARE, 24.09.2019 - EXECUTIE

(ETAPELE I, II SI III), 21.11.2019 -

EXECUTIE (ETAPA IV)

TRIM IV 2021 ANUL 2022 661.45 MIL. LEI FARA TVA

4 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRESDRUM EXPRES CRAIOVA - PITESTI

36+000 57+500ASOCIEREA SA & PE CONSTRUCT SRL - SC SPEDITION UMB SRL - SC

TEHNOSTRADE SRL - SC CONSITRANS SRL

TRONSON 2 - ROBANESTI - BALS -

VALEA MARE (KM 17+700 - 57+550)

Lot 2 - km 36+200 - km 57+550LOT 2: KM 36+200 - KM 57+550 21.35 80.16% 47.94%

21.12.2018 - ACTIVITATEA DE

PROIECTARE, 24.09.2019 - EXECUTIE

(ETAPELE I, II SI III), 21.11.2019 -

EXECUTIE (ETAPA IV)

TRIM IV 2021 ANUL 2022 792.18 MIL. LEI FARA TVA

5 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES DRUM EXPRES CRAIOVA - PITESTI 57+550 89+300ASOCIEREA SA & PE CONSTRUCT SRL - SC SPEDITION UMB SRL - SC

TEHNOSTRADE SRL

TRONSON 3, VALEA MARE -

COLONESTITRONSON 3 31.75 0% 0% 18.01.2021 2024 ANUL 2024 670.71 MIL. LEI FARA TVA

ANTREPRENORUL A CONSTITUIT GARANTIA DE BUNA EXECUTIE, IN CONFORMITATE CU PREVEDRILE CONTRACTUALE, ACEASTA FIIND APROBATA DE

CATRE C.N.A.I.R. S.A. IN DATA DE 10.11.2020.

DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE:

• 12 LUNI PERIOADA DE PROIECTARE,

• 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,

• 120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.

INCEPAND CU DATA DE 18.01.2021 A FOST EMIS ORDIN DE INCEPERE.

PAC AVIZAT IN CADRUL CTE IN LUNA MARTIE 2021

2.1. DRUMURI EXPRES PROIECTE IN EXECUTIE - IUNIE 2021

2. DRUMURI EXPRES

Page 5: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021 1

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

1 DRUMURI EXPRES PROIECTE IN LICITATIE EXECUTIE DRUM EXPRES DRUM EXPRES CRAIOVA - PITESTI 89+300 121+115TRONSON 4

COLONESTI - OARJA - PITESTITRONSON 4 31.82 0% 0% 2021 2024 ANUL 2024 ESTIMAT 617.08 MIL. LEI FARA TVA

http://www.cnadnr.ro/

sites/default/files/DRU

MURI%20EXPRES_PROI

ECTARE_%C8%98I_EXEC

U%C8%9AIE_CALENDAR

.pdf

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

1 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES BACAU - PIATRA NEAMT 0+000 61+000SEARCH CORPORATION & EGIS ROMANIA

(VALOARE CONTRACT PROIECTARE: 8,923,930.03 LEI, FARA TVA)BACAU - PIATRA NEAMT LOT 1 61 0% 0% MARTIE 2020 - ETAPA PROIECTARE

SEPTEMBRIE 2021 - TERMEN

FINALIZARE PROIECTARE; PERIOADA

CONTRACTUALA DE PRESTARE A

SERVICIILOR - 18 LUNI

IANUARIE 2022 - TERMEN

FINALIZARE PROIECTARE (CONFORM

AA NR. 1 DIN 01.07.2021)

1123.86 MIL. LEI FARA TVA

CONTRACT ELABORARE SF IN DERULARE.

AU FOST TRANSMISE CATRE CNAIR SA VARIANTELE DE TRASEU ANALIZATE IN BAZA STUDIILOR PRELIMINARE - AMC ETAPA 1 REVIZIA 4.

AMC ETAPA 1 REVIZIA 4 A FOST TRANSMIS CATRE CONSULTANTUL JASPERS PENTRU PUNCT DE VEDERE IN DATA DE 02.04.2021. IN DATA DE 18.05.2021

A FOST ORGANIZATA O NOUA SEDINTA CU CONSULTANTII JASPERS. IN DATA DE 07.06.2021 A FOST TRANSMISA CONSULTANTILOR JASPERS

DOCUMENTATIA REVIZUITA DE CATRE PRESTATOR CA URMARE A SEDINTEI DIN DATA DE 18.05.2021.

2 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRESDRUM EXPRES BRAILA - TULCEA (JIJILA -

CATALOI)0+000 59+700

INGINERIA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL SA -

CONTRACT PROIECTARE (ELABORARE STUDIU DE FEZABILITATE SI

PROIECT TEHNIC) SEMNAT IN LUNA MAI 2020.

(VALOARE CONTRACT PROIECTARE: 14.159.206,13 LEI, FARA TVA)

BRAILA - TULCEA LOT 1 59.7 0% 0% IUNIE 2020 - ETAPA PROIECTARE IUNIE 2022 1674.75 MIL. LEI FARA TVA

CONTRACT ELBORARE S.F. IN DERULARE.

DOCUMENTATIA AMC ETAPA 1 REVIZIA 2 A FOST TRANSMISA CONSULTANTILOR JASPERS PENTRU OBSERVATII.

DOCUMENTATIA AMC ETAPA 1 REVIUITA A FOST RETRANSMISA CONSULTANTILOR JASPERS PENTRU OBSERVATII IN DATA DE 10.05.2021.

IN DATA DE 09.06.2021 FOST ORGANIZATA O NOUA SEDINTA CU EXPERTII JASPERS.

IN PREZENT PRESTATORUL IMPLEMENTEAZA OBSERVATIILE DE CATRE EXPERTII JASPERS IN CADRUL DOCUMENTATIEI AMC ETAPA 1.

3 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES BUZAU - BRAILA 0+000 98+000

INGINERIA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL SA -

CONTRACT ELABORARE SF SI PT IN DERULARE

(VALOARE CONTRACT PROIECTARE: 16.591.031,97 LEI, FARA TVA)

BUZAU - BRAILA LOT 1 98 0% 0% 03.04.2020 - ETAPA PROIECTARE APRILIE 2022APRILIE 2022 - TERMEN FINALIZARE

PROIECTARE1805.55 MIL. LEI FARA TVA

CONTRACT ELABORARE SF IN DERULARE.

AMC - ETAPA 1 SE AFLA IN ANALIZA CONSULTANTILOR JASPERS.

DOCUMENTATIA AMC 1 SE AFLA IN CURS DE REVIZUIRE CONFORM OBSERVATIILOR JASPERS.

DOCUMENTATIA AMC 1 REVIZUIT A FOST TRANSMISA CATRE CNAIR, CARE A EMIS NOI OBSERVATII CATRE PRESTATOR.

IN DATA DE 26.05.2021 A FOST ORGANIZATA O NOUA SEDINTA CU CONSULTANTII JASPERS.IN PREZENT PRESTATORUL IMPLEMENTEAZA OBSERVATIILE

DE CATRE EXPERTII JASPERS IN CADRUL DOCUMENTATIEI AMC ETAPA 1.

4 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES CRAIOVA - TARGU JIU ASOCIEREA EGIS ROMANIA S.A. – SEARCH CORPORATION S.R.L CRAIOVA - TARGU JIU 108 0% 0%ORDIN DE INCEPERE 16.04.2021 -

ETAPA PROIECTAREAPRILIE 2023 20.25 MIL LEI FARA TVA

IN DATA DE 17.03.2021 CNAIR A SEMNAT CU OFERTANTUL DECLARAT CASTIGATOR - ASOCIEREA EGIS ROMANIA S.A. – SEARCH CORPORATION S.R.L.

VALOAREA CONTRACTULUI ESTE DE 20.247.133,77 LEI FARA TVA, SURSA DE FINANTARE FIIND DIN FONDURI EUROPENE NERAMBURSABILE.

IN DATA DE 16.04.2021 A FOST SEDINTA DE INCEPUT (ORDINUL DE INCEPERE)

A FOST APROBAT RAPORTUL DE INCEPUT DE CATRE BENEFICIAR. A FOST APROBAT RAPORTUL DE PROGRES NR. 1 DE CATRE BENEFICIAR.

5 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES FOCSANI - BRAILA 0+000 76+000

INGENIERIA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL S.A.

SEMNAT IN DATA DE 19.06.2020

(VALOARE CONTRACT PROIECTARE: 15.001.446,99 LEI, FARA TVA)

FOCSANI - BRAILA 76 0% 15%ORDIN DE INCEPERE 27.07.2020 -

ETAPA PROIECTAREIULIE 2022

ANUL 2022 - FINALIZARE ETAPA

PROIECTARE1400.22 MIL. LEI FARA TVA

CONTRACT SEMNAT IN DATA DE 19.06.2020.

ORDINUL DE INCEPERE 27.07.2020

DURATA CONTRACTULUI ESTE DE 24 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI

ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU, ETAPA 1 (AMC1) FOST AVIZATA IN CTE CNAIR SA.

A FOST APROBATA TEMA PENTRU STUDII ARHEOLOGICE ETAPA1 SI STUDIUL ARHEOLOGIC ETAPA 1.

IN CURS DE ELABORARE ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU ETAPA 2 (AMC 2).

6 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRESDRUM EXPRES OVIDIU (CONSTANTA) -

TULCEA0+000 112+000

SEARCH CORPORATION & EGIS ROMANIA- CONTRACT PROIECTARE

ELABORARE SF SI PROIECT TEHNIC SEMNAT IN DATA DE 13.07. 2020

(VALOARE CONTRACT PROIECTARE: 17.845.626,28 LEI, FARA TVA)

CONSTANTA - TULCEA 112.5 0% 0%ORDIN DE INCEPERE 10.08.2020 -

ETAPA PROIECTAREAug-22

AUGUST 2022 - TERMEN FINALIZARE

PROIECTARE2664.38 MIL. LEI FARA TVA

CONTRACT IN DERULARE.

AMC ETAPA 1 ESTE IN CURS DE REVIZURIRE CONFORM OBSERVATIILOR JASPERS. PRESTATORUL ANALIZEAZA REALIZAREA UNOR DRUMURI DE LEGATURA

CU MUN. TULCEA.

7 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES PASCANI - SUCEAVA 0+000 61+000

SEARCH CORPORATION SRL - EGIS ROMANIA S.A - EGIS

INTERNATIONAL SAS.

CONTRACT PROIECTARE ELABORARE SF SI PROIECT TEHNIC SEMNAT

IN DATA DE 07.09.2020 (VALOARE CONTRACT DE PROIECTARE:

11,721,430.96 LEI FARA TVA)

PASCANI - SUCEAVA 61 0% 0% OCTOMBRIE 2020OCTOMBRIE 2022 - FINALIZARE

ETAPA DE PROIECTARE1304.96 MIL. LEI FARA TVA

CONTRACT IN DERULARE.

IN DATA DE 14.04.2021 A FOST AVIZATA IN CADRUL CTE-CNAIR SA DOCUMENTATIA AMC ETAPA 1. IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA

2. IN DATA DE 16.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 2. DOCUMENTATIA AMC ETAPA 2 ESTE IN ANALIZA LA BENEFICIAR.

8 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES PLOIESTI - GAESTI 0+000 76+000

SEARCH CORPORATION & – MEGA MUHENDISLIK MUSAVIRLIK A.S.

(MEGA ENGINEERING CONSULTING INC.) - CONTRACT PROIECTARE

ELABORARE STUDIU DE FEZABILITATE SI PROIECT TEHNIC DE

EXECUTIE SEMNAT IN DATA DE 25.08.2020 (VAL CTR PROIECTARE:

15.86 MIL LEI FARA TVA)

PLOIESTI - GAESTI 76 0% 0%AUGUST 2020 – DEMARARE ETAPA

DE PROIECTARE

OCTOMBRIE 2022 - FINALIZARE

ETAPA DE PROIECTARE

OCTOMBRIE 2022 - TERMEN

FINALIZARE PROIECTARE1671.37 MIL. LEI FARA TVA

CONTRACT IN DERULARE.

PRESTATORUL A TRANSMIS DOCUMENTATIA ANALIZA MULTICRITERIALA DE TRASEU.

AU FOST EMISE OBSERVATII DIN PARTEA BENEFICIARULUI SI PRESTATORUL A TRANSMIS DOCUMENTATIA REVIZUITA.

IN DATA DE 09.04.2021 ANALIZA MULTICRITERIALA ETAPA 1 A FOST AVIZATA IN CADRUL C.T.E. CNAIR.

A FOST SUSPENDAT CONTRACTUL PENTRU O PERIOADA DE 3 LUNI INCEPAND CU DATA DE 18.05.2021.

9 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES SUCEAVA - SIRET 0+000 40+000

SEARCH CORPORATION SRL - EGIS ROMANIA S.A - EGIS

INTERNATIONAL SAS.

CONTRACT PROIECTARE ELABORARE SF SI PROIECT TEHNIC SEMNAT

IN DATA DE 07.09.2020 (VALOARE CONTRACT DE PROIECTARE:

10,092,839.13 LEI FARA TVA)

SUCEAVA- SIRET 40 0% 0% OCTOMBRIE 2020 OCTOMBRIE 2022 882.9 MIL. LEI FARA TVA

CONTRACT IN DERULARE.

DOCUMENTATIA ANALIZA MULTICRITERIALA DE TRASEU ESTE REVIZUITA CONFORM OBSERVATIILOR BENEFICIARULUI.

IN DATA DE 14.04.2021 A FOST AVIZATA IN CADRUL CTE-CNAIR SA DOCUMENTATIA AMC ETAPA 1. IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA

2. IN DATA DE 16.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 2. DOCUMENTATIA AMC ETAPA 2 ESTE IN ANALIZA LA BENEFICIAR.

10 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES TISITA - ALBITA 0+000 160+000

SEARCH CORPORATION & EGIS ROMANIA- CONTRACT PROIECTARE

ELABORARE STUDIU DE FEZABILITATE SEMNAT IN DATA DE 09.07.

2020

(VALOARE CONTRACT PROIECTARE: 11.057.073,07 LEI FARA TVA)

TISITA - ALBITA 160 0% 0%AUGUST 2020 DEMARARE ETAPA DE

PROIECTARE

OCTOMBRIE 2022 - FINALIZARE

ETAPA DE PROIECTARE

OCTOMBRIE 2022 - TERMEN

FINALIZARE ETAPA DE PROIECTARE3563.3 MIL. LEI FARA TVA

CONTRACTUL IN DERULARE

A FOST TRANSMIS AMC ETAPA 1 SE AFLA IN CURS DE REVIZUIRE CONFORM OBSEVATIILOR BENEFICIARULUI.

PRESTATORUL ANALIZEAZA ETAPIZAREA SI FAZAREA OBIECTIVULUI DE INVESTITII CONFORM CERINTELOR CNAIR SI MTI. IN DATA DE 09.06.2021

PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 2. DOCUMENTATIA AMC ETAPA 2 ESTE IN ANALIZA LA BENEFICIAR.

11 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES OAR - SATU MARE 0+000 10+900

SEARCH CORPORATION SRL

SEMNAT IN DATA DE 10.07. 2020

(VALOARE CONTRACT PROIECTARE: 3.646.308,36 LEI FARA TVA)

SATU MARE - OAR (GRANITA RO/HU) 10.9 0% 3%

AUGUST 2020 - DEMARARE SERVICII

DE PROIECTARE FAZA S.F. + P.A.C. +

P.T.E.

2022 - FINALIZARE SERVICII DE

PROIECTARE FAZA S.F. + P.A.C. +

P.T.E.

ANUL 2022 - TERMEN FINALIZARE

FAZA DE PROIECTARE311.79 MIL. LEI FARA TVA

IN DATA DE 10.07.2020 A FOST SEMNAT CONTRACTUL PROIECTARE SF+PAC/DTAC+PT

DURATA DE REALIZARE A CONTRACTULUI DE SERVICII ESTE DE 18 LUNI

IN DATA DE 10.08.2020 S-A DAT ORDINUL DE INCEPERE.

IN DATA DE 05.03.2021 A FOST AVIZATA IN CADRUL CTE CNAIR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU AMC1 + AMC2 (VARIANTA 1)

INVESTIGATIILE GEOITEHNICE SUNT REALIZATE IN PROCENT DE 70%.

IN DATA DE 17.05.2021 A FOST EMIS CERTIFICATUL DE URBANISM.

12 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES A1 (PITESTI) - MIOVENI 0+000 10+000 SEARCH CORPORATION S.R.L. A1 (PITESTI) - MIOVENI 10 0% 0%ORDIN DE INCEPERE 09.12.2020 -

ETAPA DE PROIECTARE

IULIE 2022 - TERMEN FINALIZARE

ETAPA DE PROIECTARE222.71 MIL. LEI FARA TVA

CONTRACT IN DERULARE.

DOCUMENTATIA AMC ETAPA 1 A FOST ANALIZATA SI S-AU EMIS OBSERVATII.

DOCUMENTATIA REVIZUITA AMC 1 A PRIMIT AVIZUL C.T.E. IN DATA DE 01.04.2021.

IN DATA DE 08.04.2021 A FOST TRANSMISA DOCUMENTATIA AMC ETAPA 2 SI SE AFLA IN ANALIZA IN CADRUL CNAIR.

IN DATA DE 21.04.2021 AU FOST TRANSMISE OBSERVATII ASUPRA DOCUMENTATIEI AMC 2 CATRE PRESTATOR. DOCUMENTATIA AMC ETAPA 2

REVIZUITA CONFORM OBSERVATIILOR FORMULATE DE CATRE BENEFICIAR (SOLICITARE PRIM. PITESTI RECONFIGURARE NOD A1-DEX) A FOST

TRANSMISA BENEFICIARULUI. DOCUMENTATIA ESTE IN CURS DE ANALIZA LA BENEFICIAR. DOCUMENTATIA AMC ETAPA 2 SE VA ANALIZA IN CADRUL CTE-

CNAIR SA.

2.2. DRUMURI EXPRES PROIECTE IN LICITATIE EXECUTIE - IUNIE 2021

2.3. DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) - IUNIE 2021

Page 6: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021 1

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

1 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONALDN79

4+150 107+745 ASTALDI S.P.A. ARAD - ORADEA, KM 4+150 – KM

107+745 103.55 98% 98% 03.02.2009 REZILIAT IN FOLOSINTA 266.31 MIL. LEI FARA TVA

PROBLEME:

CONTRACTUL A FOST REZILIAT DE CATRE BENEFICIAR IN DATA DE 02.10.2020 DATORITA INTARZIERILOR SI NEEXECUTARII LUCRARILOR RAMASE DE

EXECUTAT DE CATRE ANTREPRENOR.

1. NEEXECUTAREA LUCRARILOR PENTRU PODUL DE LA KM 41+635

2. INTARZIEREA FINALIZARII EXECUTIEI LUCRARILOR

2 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN 52 1+350 44+600

ASOCIEREA S.C. ALEXCOR TRADING S.R.L. - IMPRESA DI

COSTRUZIONI ING. E. MANTOVANI S.P.A. – S.C. PEGASUS

ENGINEERING S.R.L.

ALEXANDRIA - TURNU MAGURELE 43.25DATA INCEPERII ACTIVITATII DE

PROIECTARE: 09.06.2020

126.323 MII LEI FARA TVA - VALOARE

PROIECTARE ȘI EXECUȚIE PENTRU

AMBELE SECTOARE

3 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN 52 49+194 52+649

ASOCIEREA S.C. ALEXCOR TRADING S.R.L. - IMPRESA DI

COSTRUZIONI ING. E. MANTOVANI S.P.A. – S.C. PEGASUS

ENGINEERING S.R.L.

TURNU MAGURELE - PORT TURNU

MAGURELE3.455

DATA INCEPERII ACTIVITATII DE

PROIECTARE: 09.06.2020

126.323 MII LEI FARA TVA - VALOARE

PROIECTARE ȘI EXECUȚIE PENTRU

AMBELE SECTOARE

4 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN7 251+475 254+315S.C GEIGER TRANSILVANIA SRL – SERVICII DE PROIECTARE SC

CONSIS PROIECT SRL IN CALITATE DE SUBCONTRACTANT

REALIZARE LARGIRE VALEA OLTULUI

LA 4 BENZI DE CIRCULATIE INTRE KM

251+475 – KM 254+315

2.84 40% 25% 01.11.2019 SEPTEMBRIE 2021 22.141 MIL. LEI FARA TVA A FOST OBTINUTA AC NR. 50 DIN DATA DE 04 SEPTEMBRIE 2020. ORDINUL ADMINITRATIV DE RELUARE A FOST DAT CU 21.09.2020.

5 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN5 7+573 19+220ASOCIEREA EUROCOGEN - FILIALA ANINOASA SRL & ALEANDRI SPA

& BEOZZO COSTRUZIONI SRL & SMART BUILDING PROJET SRL

MODERNIZARE DN 5,

BUCURESTI – ADUNATII COPACENI

KM 7+573 - KM 19+220

DRUM MODERNIZAT - LUCRARI

FINALIZATE IN ANUL 202011.647 98.00% 93.80% 23.04.2015 ESTIMAT SEPTEMBRIE 2021 76.13 MIL. LEI FARA TVA EXECUTIE LUCRARI

6 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN73 13+800 128+250 ASOCIEREA AZVI SA - STRACO GRUP SRL - TRACTEBEL

MODERNIZARE: PITESTI -

CAMPULUNG - BRASOV

KM 13+800 - KM 42+850; KM 54+050

- KM 128+250

103.25 49.82% 51.00% 19.05.2014 DECEMBRIE 2023 275.86 MIL. LEI FARA TVA

A FOST RECEPTIONAT UN SECTOR DE 28,85 KM.

PENTRU RESTUL SECTORULUI CONTRACTUL ESTE IN CURS DE REZILIERE SI SE VA LANSA O PROCEDURA DE LICITATIE AVAND CA OBIECT ACTUALIZAREA

PROIECTULUI PENTRU REST DE EXECUTAT.

DOCUMENTATIA DE ATRIBUIRE PENTRU SERVICII DE ACTUALIAZARE PROIECT FINALIZATA, PROCEDURA DE LICITATIE SUSPENDATA CA URMARE A UNOR

CONTESTATII .

7 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN76 55+425 69+350 ASOCIEREA SC SYLC CON TRANS SRL/HIDROSTROY AD IONESTI - VARFURILE LOT 3 13.93 98.90% 74.35% 15.03.2019

RECEPTIE LA TERMINAREA

LUCRARILOR - PREVIZIUNE

SEPTEMBRIE 2021

55.95 MIL. LEI FARA TVARECEPTIE LA TERMINAREA LUCRARILOR - PREVIZIUNE SEPTEMBRIE 2021, INCLUSIV CONSOLIDAREA ZONELOR CU ALUNECARI KM 65+358 - KM 65+448

DREAPTA SI KM 65+843 - KM 65+996 STANGA

8 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN56 47+000 84+020 MOCHLOS S.A. GALICEA MARE - CALAFAT LOT 2 33.83 100% 91.43% 03.09.2012 16.06.2021 81.94 MIL. LEI FARA TVAPROCESUL VERBAL DE RECEPTIE LA TERMINAREA LUCRARILOR A FOST APROBAT DE DIRECTORUL GENERAL AL CNAIR IN DATA DE 16.06.2021.

9 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN76 69+350 102+660ASOCIEREA SC DRUM ASFALT SRL – VAHOSTAV SK A.S. – TRAMECO

SA – ILE VIOREL CONSTRUCT SRL.VARFURILE - STEI LOT 4 33.31 51.28% 30.65% 29.06.2020

DECEMBRIE 2021 - RECEPTIE LA

TERMINAREA LUCRARILOR

DECEMBRIE 2026 - RECEPTIE FINALA

ANUL 2021 74.78 MIL LEI FARA TVA

CONTRACTUL PENTRU FINALIZAREA LUCRARILOR A FOST SEMNAT IN DATA DE 08.05.2020;

ORDINUL DE INCEPERE A LUCRARILOR A FOST EMIS IN DATA DE 29.06.2020;

PREDARE AMPLASAMENT - 02.07.2020.

10 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN71 0+000 109+905

LOT 1 - ASOCIEREA SC AQUA PARC

SRL - SC MAVGO HOLDING SRL -

HYDROSTROY AD - VDH AD

(VODSTROI 98 AD) - SC BDU MAXI

CONSTRUCT SRL

CONSTRUCTORUL A FOST NOTIFICAT

PENTRU REZILIERE

LOT 1 (SECTOR 1): BALDANA -

TARGOVISTE KM. 0+000 - KM 44+130

LARGIRE LA 4 BENZI DE CIRCULATIE;

LOT 2 (SECTOR 2): TARGOVISTE -

SINAIA KM. 51+041 - KM 109+905 -

DRUM LA 2 BENZI)

102.99 0% 0% 1567.03 MIL. LEI FARA TVA

LOTUL 1 - IN DATA DE 14.01.2021 A FOST INAINTATA NOTIFICAREA DE REZILIERE.

LOTUL 2 - PROCEDURA RELUATA

PROCEDURA DE ACHIZITIE PUBLICA IN DERULARE

http://www.cnadnr.ro/

sites/default/files/DRU

MURI_NA%C8%9AIONA

LE_%C8%98I_VARIANTE

_DE_OCOLIRE_CALEND

AR.pdf

11 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN28B 0+000 76+758ASOCIEREA SC AQUA PARC SRL - SC MAVGO HOLDING SRL -

VAHOSTAV - SK A.S. - TRAMECO SA

MODERNIZARE DN28B, TARGU

FRUMOS – BOTOSANI, KM 0+000 –

KM 76+758

71.512 0% 0%15.07.2020 - ORDIN INCEPERE

PENTRU ETAPA PROIECTAREDECEMBRIE 2023 DECEMBRIE 2023 267.31 MIL LEI FARA TVA

CONTRACT PROIECTARE SI EXECUTIE IN DERULARE - SEMNAT IN DATA DE 20.05.2020

AVIZAT PT CTE DRDP IASI - 09.06.2021 - AVIZAT DTAC DRDP IASI - 10.03.2021; AVIZAT DTAC CNAIR SA - 16.03.2021. AUTORIZATIE DE CONSTRUIRE NR.

21/12.05.2021 EMISA DE MTIC.

12 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN29D 2+800 48+146ASOCIEREA SC AUTOTEHNOROM SRL - SC OPR ASFALT SRL - OBRAS

PUBLICAS-Y REGADIOS SA - SC EVALCONS TECH SRL

MODERNIZARE DN29D BOTOSANI -

STEFANESTI KM 2+800 – KM 18+500

SI KM 18+800 – KM 48+146

45.046 0 0%

22.06.2020 - EMITERE ORDIN DE

INCEPERE PENTRU ETAPA

PROIECTARE

DECEMBRIE 2023 208.44 MIL LEI FARA TVA

IN DATA DE 29.06.2020 A FOST DEPUSA APLICATIA DE FINANTARE PENTRU ANGAJAREA CHELTUIELILOR AFERENTE ACESTUI PROIECT, DIN FONDURI

NERAMBURSABILE, ALOCALTE IN CADRUL POIM 2014 - 2020

CONTRACT PROIECTARE SI EXECUTIE IN DERULARE

IN DATA DE 08.01.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUCTIE

TERMEN DE PREDARE A PROIECTULUI TEHNIC DE EXECUTIE: 28.02.2021

PT - AVIZAT CNAIR SA NR. 5035/26.03.2021

13 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN7 30+950 52+350LARGIRE LA 4 BENZI A DN7, BALDANA-

TITU, KM 30+950-KM 52+35021.4

ESTIMAT SEMNARE CONTRACT IN

IPOTEZA FARA CONTESTATIE:

MARTIE 2021

DECEMBRIE 2023 DECEMBRIE 2023 210.63 MIL. LEI FARA TVA

04.11.2020 A AVUT LOC DEPUNEREA OFERTELOR PENTRU PROCEDURA DE ATRIBUIRE A CONTRACTULUI "PROIECTARE TI EXECUTIE LARGIRE LA 4 BENZI A

DN 7, BALDANA-TITU, KM 30+950 – KM 52+350”.

PANA LA TERMENUL LIMITA AU DEPUS OFERTE URMATORII AGENTI ECONOMICI:

1. ASOCIEREA CLAY WORK BUCHAREST - DIMAKS TURIZM INSAAT ENERJI AKARYAKIT NAK. VE TAS. GIDA TEM. OTOM. OTO. KIR.ITH. IHR.

SAN.VE.TIC.LTD.STI. ISTANBUL;

2. ASOCIEREA COSEDIL SPA – SC BIT INVEST SRL - CHIRULLI ANDREA IMPRESA INDIVIDUALE – SC TOTAL ROAD SRL;

3. ASOCIEREA SC G&M ROAD BUILDING ENGINEERING SRL – SC KIRLIC GROUP SRL – SC BUILDING DESIGN 2000 TOP SRL – SC IRIMAT CONS S.R.L. -

D'AGOSTINO ANGELO ANTONIO COSTRUZIONI GENERALI S.R.L. – SC CONCORDIA CON. STRADE S.R.L – SC SERCONSTRUCT ROADS S.R.L.;

4. ASOCIEREA SC MAVGO HOLDING S.R.L. – SC BDU MAXI CONSTRUCT S.R.L.;

5. OZALTIN INSAAT TICARET VE SANAYI A.S.

VALOAREA ESTIMATA A CONTRACTULUI ESTE CUPRINSA IN INTERVALUL 243.801.103,00 - 289.093.324,00 LEI FARA TVA.

DURATA CONTRACTULUI ESTE DE 6 LUNI PERIOADA DE PROIECTARE TI 20 DE LUNI PENTRU EXECUTIA LUCRARILOR.

COMISIA DE EVALUARE VA ANALIZA OFERTELE IN CONFORMITATE CU PREVEDERILE DOCUMENTATIILOR DE ATRIBUIRE TI CU LEGISLATIA IN VIGOARE IN

DOMENIUL ACHIZITIILOR PUBLICE.

ANALIZA SI EVALUAREA OFERTELOR CU STABILIREA OFERTANTULUI CASTIGATOR: 29.04.2021;

COMUNICAREA REZULTATULUI PROCEDURII: 29.04.2021;

TERMEN DEPUNERE CONTESTATII: 10.05.2021;

ESTIMAT SEMNARE CONTRACT, IN IPOTEZA FARA CONTESTATII: 25.05.2021

14 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN6 132+435 185+230

REABILITARE DN 6, ALEXANDRIA -

CRAIOVA, KM 90+190 - KM 222+182

LOT 2: KM 132+435 - KM 185+230

(RELICITARE)

48.009 2021 2024 ANUL 2024 267.15 MIL. LEI FARA TVA

CONTRACT REALIZARE EXPERTIZA TEHNICA SEMNAT IN DATA DE 06.06.2020

ORDINUL DE INCEPERE A FOST EMIS IN DATA DE 10.07.2020, CU O DURATA CONTRACTUALA DE 90 DE ZILE, TERMEN DE FINALIZARE 08.10.2020

CALENDAR PROCEDURA DE LICITATIE LOTUL 2, KM 132+435 - 185+230 - RELICITARE

DEPUNERE OFERTE: 24.05.2021;

ANALIZA SI EVALUAREA OFERTELOR CU STABILIREA OFERTANTULUI CASTIGATOR: 26.07.2021;

COMUNICAREA REZULTATULUI PROCEDURII DE ACHIZITIE PUBLICA: 26.07.2021;

CONTESTATII: 05.08.2021

ESTIMARE SEMNARE CONTRACT: 20.08.2021

3.1. DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE - IUNIE 2021

3. DRUMURI NATIONALE

Page 7: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021 1

15 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN66 106+220 106+965 ASOCIEREA S.C. FREYROM S.A. - PROCONS GROUP S.R.L

REABILITARE DN66 PRIN

REAMENAJAREA SECTORULUI

CUPRINS INTRE KM 105+000 – KM

105+580 IN VEDEREA CONSTRUIRII

UNUI POD NOU PESTE JIU DE LA

MERI LA KM 105+250, REAMENAJARE

SECTOR KM 106+220 – KM 106+965

1.325 10.00% 8.39% 12.11.2020 12.07.2022 ANUL 2022 19.85 MIL. LEI FARA TVA

CONTRACT EXECUTIE LUCRARI SEMNAT IN DATA DE 02.11.2020

DURATA DE REALIZARE A INVESTITIEI: 12 LUNI (EXCLUSIV PERIOADA DE TIMP FRIGUROS, DE REGULA, CUPRINSA IN PERIOADA 15.11- 15.03 ), CU O

PERIOADA DE GARANTIE A LUCRARILOR ACORDATA DE EXECUTANT DE 96 LUNI (8 ANI).

APROBATA SITUATIA DE LUCRARI NR. 1 IN VALOARE DE 673.083,63 LEI FARA TVA. IN CURS DE APROBARE SITUATIA DE LUCRARI NR. 2 IN VALOARE DE

991.685,77 LEI FARA TVA.

16 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN2L 60+165 76+277MODERNIZARE DN 2L, SOVEJA -

LEPSA, KM 60+165 - KM 76+27716.112 PROIECTARE IN DERULARE

ORDINUL DE INCEPERE PENTRU

PROIECTARE A FOST EMIS IN DATA

DE 22.09.2020

DECEMBRIE 2023 DECEMBRIE 2023 106.54 MIL. LEI FARA TVA

CONTRACT DE PROIECTARE SI EXECUTIE LUCRARI SEMNAT IN DATA DE 24.07.2020.

VALOARE CONTRACT PROIECTARE + EXECUTIE LUCRARI: 126.778.219,70 LEI CU TVA, DIN CARE:

PROIECTARE: 3.655.098,42 LEI CU TVA

EXECUTIE LUCRARI: 123.123.121,28 LEI CU TVA

AVIZAT DTAC CTE DRDP IASI 16918/ 10.05.2021; AVIZAT DTAC CTE CNAIR SA - 08.06.2021

DURATA CONTRACTULUI ESTE: 30 LUNI PERIOADA DE PROIECTARE SI EXECUTIE A LUCRARILOR:

- 6 LUNI PROIECTARE;

- 24 LUNI EXECUTIE LUCRARI;

- 84 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.

PTE IN CURS DE REVIZUIRE.

17 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN7 256+675 258+950

PROIECTARE SI EXECUTIE "REALIZARE

BANDA A TREIA DN 7 VALEA OLTULUI

INTRE KM 256+675 – KM 258+950”

2.274 8.46 MIL. LEI FARA TVA

18 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN69 0+000 10+000 TODINI COSTRUZIONI GENERALI S.P.A. DRUM DE LEGATURA INTRE DN69 SI

AUTOSTRADA A110 CTR SEMNAT IN DATA DE 29.01.2021 2021 2023 ANUL 2023 189.95 MIL. LEI FARA TVA CONTRACT SEMNAT IN DATA DE 29.01.2021, CU O PERIOADA CONTRACTUALA DE 2 ANI (6 LUNI PROIECTAREA) ȘI ARE O GARANȚIE DE 84 DE LUNI.

19 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN7 0+000 14+300

DRUM DE LEGATURA A1 - DN7 (TITU)

(DJ 711A) - LARGIRE LA 4 BENZI DE

CIRCULATIE

14.3 OCTOMBRIE 2019 Aug-21 73.33 MIL. LEI FARA TVA

STUDIUL DE FEZABILITATE IN VARIANTA DRAFT PREDAT DE CATRE PRESTATOR IN CURS DE ANALIZA.

S-AU EMIS OBSERVATII ASUPRA VARIANTEI DRAFT A STUDIUL DE FEZABILITATE SI SE ASTEAPTA VARIANTA FINALA.

IN DATA DE 29.04.2021 PRESTATORUL A TRANSMIS STUDIUL DE FEZABILITATE. STUDIUL DE FEZABILITATE SE AFLA IN ANALIZA LA BENEFICIAR. IN DATA

DE 25.05.2021 AU FOST TRANSMISE OBSERVATIILE BENEFICIARULUI LA DOCUMENTATIA INAINTATA IN DATA DE 29.04.2021. PRESTATORUL

IMPLEMENTEAZA OBSERVATIILE FORMULATE PENTRU SF.

20 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DRUM TRANSREGIO GILAU - APAHIDA 0+000 38+800 GILAU - APAHIDA 38.8

CONTRACT SERVICII DE PROIECTARE

DERULAT IN BAZA UNUI PROTOCOL

DE CATRE UAT CLUJ NAPOCA

2345.52 MIL. FARA TVASTUDIU DE FEZABILITATE IN ELABORARE

FINALIZARE SF - TRIM. IV 2021

21 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN24C 106+650 142+250S.C. SEARCH CORPORATION S.R.L. - ELABORARE SF / S.C. BEST

CONSULTING & DESIGN S.R.L. BUCURESTI - REVIZUIRE S.F.MANOLEASA - RADAUTI PRUT 35.6 33.63% 0% 109.69 MIL. LEI FARA TVA

SF REVIZUIT IN ANUL 2016 / HG NR. 460/28.06.2018 PENTRU APROBAREA INDICATORILOR TEHNICO-ECONOMICI

LIPSA FINANTARE LUCRARI

22 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONALPOD PE DN13C PESTE RAUL TARNAVA MARE

LA VANATORI1+200 1+252

POD PE DN 13C PESTE RAUL

TARNAVA MARE LA VANATORI0.0521 5.45 MIL. LEI FARA TVA CONTRACT SEMNAT IN LUNA OCTOMBRIE 2020.

23 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN1H 6+000 12+000 SC MECANO BAU TRADING SRLREMEDIERE DEFECTIUNI PE DN1H KM

6+000 - KM 12+0006 90.50% 47.88% 15.10.2020 31.08.2021 ANUL 2021 12.761 MIL. LEI FARA TVA ORDINUL DE INCEPERE A FOST EMIS INCEPAND CU DATA DE 15.10.2020

24 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN51 2+600 43+783 ZIMNICEA - ALEXANDRIA 41.183 0.1953 MIL. LEI FARA T.V.A. DOCUMENTATIE INTOCMITA IN VEDEREA PROMOVARII SPRE LICITATIE.

25 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN2PASAJ SUPERIOR PE DN2, PESTE CF

LA ROMAN, KM 332+9612 841.094 MIL. LEI FARA TVA

26 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN57 152+990 200+745152+990 - 200+745 (ORAVITA -

MORAVITA)47.755 1.638 MII LEI FARA TVA DOCUMENTATIE PREDATA LA DIRECTIA ACHIZITI

27DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL

DN21 104+160 106+900PROIECTARE SI EXECUTIE PASAJ

SUPERIOR PE DN 21, KM105+5002.74 0% 0% 15.03.2021 01.09.2023 ANUL 2023 98.120 MIL LEI FARA TVA

S-A EMIS ORDINUL DE INCEPERE IN DATA DE 15.03.2021.

DURATA DE EXECUTIE CONTRACT :

- 360 ZILE PERIOADA DE PROIECTARE

- 540 ZILE PERIOADA DE EXECUTIE.

STADIU:IN CURS DE ELABORARE/ PREDARE DECLARATIE DE PROIECTARE (TERMEN PREDARE -120 ZILE DE LA ORDINUL DE INCEPERE.)

Page 8: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021 1

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

1 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE CENTURA BUCURESTISTRACO GRUP SRL - SC COMNORD SRL - SPECIALIST CONSULTING

SRL

PASAJ SUPRATERAN PE DJ 602

CENTURA BUCURESTI DOMNESTIDOMNESTI - DJ 602 0.536 33.57% 32.27%

15.01.2019 - PENTRU LUCRARILE

AUTORIZATE PRIN AC 140/

20.12.2018

16.09.2019 PENTRU LUCRARILE

AUTORIZATE PRIN AC 69/28.08.2019

23.09.2020 - PENTRU LUCRARILE

AUTORIZATE PRIN AC 54/23.09.2020

24 LUNI DE LA EMITEREA

AUTORIZATIEI DE CONSTRUIRE

(ESTIMAT LUNA 09.2022)

ANUL 2022 91.55 MIL. LEI FARA TVA

CONTRACTUL DE PROIECTARE SI EXECUTIE PASAJ DOMNESTI A FOST SEMNAT IN DATA DE 10.05.2017

AUTORIZATIA DE CONSTRUIRE NR. 140/ 20.12.2018, NR. 69/ 28.08.2019 SI NR. 54/ 23.09.2020

LUCRARI CE SE EXECUTA: GRINDA PARAPET SECTOR INEL CENTRAL CATRE DN 6, SUDARE ANTRETOAZA SI LONJERONI TABLIER METALIC - OBIECTELE ST2

SI ST3, MONTARE GRINZI PRINCIPALE TABLIER METALIC - OBIECT ST2, EPUISMENTE RETEA TRANSGAZ, CANALIZARE PLUVIALA, SAPATURA RAMPA

COBORARE PRELUNGIREA GHENCEA, EXECUTIE STRAT DE FUNDATIE DIN BALAST PE LARGIRE DN CB SECTOR INEL CENTRAL CATRE A1, EXECUTIE STRAT DE

FUNDATIE DIN BALAST LA PUNTUL DE INTOARCERE PRELUNGIREA GHENCEA, ASTERNERE STRAT DE BAZA DIN MIXTURI ASFALTICE AB 31,5, STABILIZARE

TEREN FUNDARE - RAMPA PAMANT ARMAT.

2 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE BACAU 0+000 30+842 SPEDITION UMB SRL – TEHNOSTRADE SRL BACAU

OBIECT 1: 0+000 -20+299,

OBIECT 2: 0+000 - 3+177

OBIECT 3: 0+000 -7+366

30.842 91.42% 96.81%

23.01.2019 - DATA DE INCEPERE

PERIOADA DE PROIECTARE

08.03.2019 - DATA DE INCEPERE A

LUCRARILOR IN BAZA AC

040/15.07.201503.07.2019 - DATA

DE INCEPERE A LUCRARILOR IN BAZA

AC 051/28.06.2019

IANUARIE 2022 ANUL 2020 668.33 MIL. LEI FARA TVA

DESCHIDERE TRAFIC

03.09.2020 - OBIECT 3

02.12.2020 - OBIECT 1

3 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE BARLAD 0+000 11+281 ASOCIEREA SC TEHNIC ASIST SRL – SC TASS INFRA LOGISTIC SRL BARLAD 1 11.281 22.50% 13.62%

05.12.2018

(DATA DE INCEPERE A ACTIVITATII

DE PROIECTARE) 06.08.2020 - DATA

DE INCEPERE A LUCARILOR)

ESTIMAT IUNIE 2022 132.051 MIL. LEI FARA TVA

CONTRACTUL A FOST SEMNAT IN DATA DE 24.10.2018. ORDINUL DE INCEPERE PENTRU PROIECTAREA LUCRARILOR A FOST EMIS.

A FOST AVIZAT PROIECTUL TEHNIC IN SEDINTA CTE DIN DATA DE 19.06.2020

AUTORIZATIE DE CONSTRUIRE A FOST EMISA.

ORDINULL DE INCEPERE A LUCRARILPR A FOST EMIS IN DATA DE 06.08.2020

AMPLASAMENTUL LUCRARILOR A FOST PREDAT CATRE ANTREPRENOR IN DATA DE 06.08.2020.

4 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE GALATI 0+000 33+600ASOCIEREA S.C. SA&PE CONSTRUCT S.R.L. – S.C. SPEDITION UMB

S.R.L. – S.C. TEHNOSTRADE S.R.L.GALATI 1 33.6 0% 0% IUNIE 2021 DECEMBRIE 2025 ANUL 2025 705.28 MIL. LEI FARA TVA

PRETUL PE KM ESTE DE CCA. 20.990.555 LEI FĂRĂ TVA, REPREZENTAND CCA. 4,327,949 EURO FARA TVA.

DURATA CONTRACTULUI ESTE DE 174 DE LUNI, DIN CARE:

• 12 LUNI PERIOADA DE PROIECTARE,

• 42 LUNI PERIOADA DE EXECUTIE A LUCRĂRILOR,

• 64 DE LUNI PERIOADĂ DE GARANȚIE A LUCRĂRILOR.

5 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE MIHAILESTI 0+000 3+180 S.C. VIAROM CONSTRUCT S.R.L. MIHAILESTI RELICITARE 3.18

30.7% - PROGRES IN CADRUL

CONTRACTULUI REZILIAT;

32% IN CADRUL NOULUI CONTRACT

31.94% - PROGRES IN CADRUL

CONTRACTULUI REZILIAT;

18.65% IN CADRUL NOULUI

CONTRACT

FEBRUARIE 2021 - DEMARARE

LUCRARI RAMASE DE EXECUTAT2022 36.9 MIL. LEI FARA TVA

CONTRACT REZILIAT IN DATA DE 04.04.2019 DE CATRE CNAIR SA PENTRU NEINDEPLINIREA DE CATRE ANTREPRENOR A MAI MULTOR INSTIINTARI DE

REMEDIERE.

EXPERTIZA TEHNICA REALIZATA - 2019

IN DATA DE 23.12.2020 CNAIR A SEMNAT CONTRACTUL AVAND CA OBIECT “CONSTRUCTIA VARIANTEI DE OCOLIRE MIHAILESTI - FINALIZARE LUCRARI”,

CU OFERTANTUL DECLARAT CASTIGATOR S.C. VIAROM CONSTRUCT S.R.L.

VALOAREA CONTRACTULUI ESTE DE 36.862.651,20 LEI FARA TVA.

SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE.

TRASEUL ARE O LUNGIME DE 3,18 KM.

DURATA CONTRACTULUI ESTE DE 72 DE LUNI, DIN CARE:

12 LUNI PERIOADA DE EXECUTIE A LUCRARILOR,

60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.

A FOST EMIS ORDINUL DE INCEPERE LUCRARI PENTRU DATA DE 15.02.2021. URMEAZA PREDAREA AMPLASAMENTULUI.

6 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE SATU MARE 0+000 19+540 ASOCIEREA ITINERA SPA COLLINI LAVORI SPA - VIA DESIGN SRL SATU MARE 1 19.54 67.50% 58.66%

30.06.2017 (SERVICII DE

PROIECTARE)

28.06.2018

(EXECUTIE LUCRARI)

ESTIMAT DECEMBRIE 2021 304.791 MIL. LEI FARA TVA

CONTRACTUL DE PROIECTARE SI EXECUTIA VARIANTEI DE OCOLIRE SATU MARE A FOST SEMNAT IN DATA DE16.11.2015

DATA DE INCEPERE A PERIOADEI DE PROIECTARE ESTE 30.06.2017.

DATA DE INCEPERE EXECUTIE LUCRARi ESTE 28.06.2019-ETAPA I.

DATA DE INCEPERE EXECUTIE LUCRARI ETAPA II ESTE 02.12.2020

7 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE TARGU JIU 0+000 19+987

"COLLINI LAVORI SPA - CONTRACT REZILIAT

CONTRACT RELICITAT - ASOCIEREA SECOL SOCIETA EDILE

COSTRUZIONI E LAVORI S.A."

TARGU JIU RELICITARE 19.987

40% PROGRES INREGISTRAT IN

CADRUL CONTRACTULUI DE LUCRARI

REZILIAT;

9.00% -IN CADRUL NOULUI

CONTRACT

37.5% PROGRES INREGISTRAT IN

CADRUL CONTRACTULUI DE LUCRARI

REZILIAT;

0% IN CADRUL NOULUI CONTRACT

14.10.2014 - CTR REZILIAT

NOV. 2020 - CONTRACT RELICITAT

SEMNAT

CONTRACT REZILIAT DE CATRE

ANTREPRENOR IN LUNA 05.2018.

CONFORM CONTRACT RELICITAT -

AUGUST 2022

207 MIL. LEI FARA TVA

IN DATA DE 24.11.2020 A FOST SEMNAT CONTRACTUL NR 92/79265.

A FOST EMIS ORDINUL DE INCEPERE LUCRARI PENTRU DATA DE 15.02.2021.

IN DATA DE 18.02.2021 A FOST PREDAT AMPLASAMENTUL.

8 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE TECUCI 0+000 6+945

ASOCIEREA S.C. MAVGO HOLDING S.R.L. – S.C. ANTREPRIZA DE

CONSTRUCȚII DRUMURI ȘI AUTOSTRĂZI S.R.L. (FOSTA S.C. AQUA

PARC S.R.L.) – S.C. BDU MAXI CONSTRUCT S.R.L. – HYDROSTROY AD

TECUCI (RELICITARE) RELICITARE 6.945

58% - PROGRES FIZIC INREGISTRAT

LA DATA REZILIERII

0% IN CADRUL NOULUI CONTRACT

29.63% - PROGRES INREGISTRAT IN

CADRUL CONTRACTULUI DE LUCRARI

REZILIAT

0% IN CADRUL NOULUI CONTRACT

03.08.2015

CONTRACT REZILIAT IN DATA DE

20.05.2019.CONTRACTUL PENTRU

"CONSTRUCTIA VARIANTEI DE

OCOLIRE TECUCI - REST DE

EXECUTAT” A FOST SEMNAT IN

16.04.2021. A FOST EMIS ORDINUL

DE INCEPE LUCRARI IN 20.05.2021.IN

21.05.2021 A AVUT LOC PREDAREA

AMPLASAMENTULUI

41.74 MIL. LEI FARA TVA

VINERI, 16.04.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL PENTRU "CONSTRUCTIA VARIANTEI DE OCOLIRE TECUCI - REST DE EXECUTAT”, CU

ASOCIEREA S.C. MAVGO HOLDING S.R.L. – S.C. ANTREPRIZA DE CONSTRUCTII DRUMURI SI AUTOSTRAZI S.R.L. (FOSTA S.C. AQUA PARC S.R.L.) – S.C. BDU

MAXI CONSTRUCT S.R.L. – HYDROSTROY AD.

VALOAREA CONTRACTULUI ESTE DE 41.735.534,38 LEI FARA TVA.

SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE.

VARIANTA DE OCOLIRE TECUCI ARE O LUNGIME DE 6,945 KM.

VARIANTA SE DESPRINDE DIN DN24, TRAVERSEAZĂ CU UN PASAJ SUPERIOR DN24 ȘI LINA CF MARASESTI - TECUCI LA KM 0+385,95, CONTINUA IN

ALINIAMENT PANA LA INTERSECTIA LA NIVEL CU DJ252H LA KM 2+490, TRAVERSEAZA CU PASAJ SUPERIOR LINIA CF FAUREI - TECUCI LA KM 6+416,29 SI

SE FINALIZEAZA LA KM 6+945 (ECHIVALENT CU KM 6+801,29), LA INTERSECȚIA CU DN25.

PERIOADA CONTRACTUALA DE EXECUTIE A LUCRARILOR ESTE DE 12 DE LUNI, IAR PERIOADA DE GARANTIE ESTE DE 60 DE LUNI.

9 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE TIMISOARA SUD 0+000 25+690 TIRRENA SCAVI S.P.A TIMISOARA - SECTOR SUD 25.69 30.24% 29,59%

29.01.2019 - DATA DE INCEPERE

PERIOADA DE PROIECTARE

25.03.2020 - ORDIN - INCEPERE

EXECUTIE LUCRARI

ESTIMAT 2022 ANUL 2022 272.43 MIL. LEI FARA TVA

PROIECT TEHNIC FINALIZAT

AUTORIZATIE DE CONSTRUIRE EMISA IN LUNA MARTIE 2020.

EXECUTIE LUCRARI IN DERULARE.

10 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE ZALAU 0+000 5+535ASOCIEREA SINOHYDRO CORPORATION LIMITED – SC GOOD

PROOD S.R.L.

ETAPA 2 - 7 KM INTRE DN 1F KM

79+625 - DJ 191C1

5.535 KM (5 VIADUCTE, 2 PODURI, 2

INTERSECTII TIP GIRATIE)1% 15% 2020 2023 185.54 MIL. LEI FARA TVA

ORDINUL DE INCEPERE A CONTRACTULUI A FOST COMUNICAT CA FIIND 25.09.2020 (PROIECTARE+EXECUTIE). PERIOADA DE PROIECTARE ESTE DE 6

LUNI (FINALIZARE 24.03.2021) SI 24 LUNI EXECUTIE LUCRARI (FINALIZARE 23.03.2023).

DECIZIA DE EXPROPRIERE NR. 1848 DIN 10.11.2020.

A FOST ACORDATA ANTREPRENORULUI POSESIA SANTIERULUI.

A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 17/26.03.2021.

A FOST EMISA HOTARAREA DE GUVERN NR.622 DIN 03.06.2021 PRIVIND SCOATEREA DEFINITIVA DIN FONDUL FORESTIER NATIONAL.

11 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOAREDRUM DE LEGATURA DN5 - SOSEAUA DE

CENTURA - POD PRIETENIEI0+000 5+720 PORR CONSTRUCT S.R.L.

DRUM DE LEGATURA DN5 - SOSEAUA

DE CENTURA - POD PRIETENIEI5.72 36.00% 24.29% APRILIE 2020 ESTIMAT 2022 ESTIMAT 2022 106.638 MIL. LEI FARA TVA

IN DATA DE 19.11.2019 A FOST SEMNAT CONTRACTUL DE PROIECTARE SI EXECUTIE AFERENT ACESTUI OBIECTIV.

IN DATA DE 05.03.2020 A FOST SEMNAT CONTRACTUL DE SUPERVIZARE AFERENT LUCRARILOR.

IN DATA DE 15.04.2020 A FOST EMIS ORDINUL DE INCEPERE PENTRU PROIECTARE

IN DATA DE 21.10.2020 A FOST EMIS ORDINUL DE INCEPRE PENTRU EXECUTIA LUCRARILOR

4.1. VARIANTE OCOLITOARE PROIECTE IN EXECUTIE - IUNIE 2021

4. VARIANTE OCOLITOARE

Page 9: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021 1

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

1 VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE LUCRARI VARIANTA OCOLITOARE VARIANTA OCOLITOARE SFANTU GHEORGHE 0+000 8+000 CONTRACT ELABORARE SF FINALIZAT SFANTU GHEORGHE 1 8 07.05.20182020 - FINALIZARE PROIECTARE,

ETAPA STUDIU DE FEZABILITATE41.47 MIL. LEI FARA TVA PROCEDURA DE ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE - IN DERULARE, ETAPA EVALUARE OFERTE.

2 VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE LUCRARI VARIANTA OCOLITOARE CENTURA BUCURESTI 35+600 55+465

LARGIRE LA 4 BENZI A CENTURII

RUTIERE A MUNICIPIULUI BUCURESTI

SUD INTRE A1 (KM 55+520) SI DN 5

(KM 40+000) - LOT 1 SI LOT 2

18,68

http://www.cnadnr.ro/

sites/default/files/DRU

MURI_NA%C8%9AIONA

LE_%C8%98I_VARIANTE

_DE_OCOLIRE_CALEND

AR.pdf

3 VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE LUCRARI VARIANTA OCOLITOARE VARIANTA OCOLITOARE SIGHISOARA 0+000 13+057PROCEDURA DE LICITATIE ATRIBUIRE CONTRACT PROIECTARE SI

EXECUTIE IN DERULARESIGHISOARA 13.057 0.00% 0.00% 6/14/2021 ESTIMAT 23.11.2021 ESTIMAT 2021 293.084 MIL LEI fara TVA 14.06.2021 - DATA PUBLICARII ANUNTULUI, 31.08.2021 DATA DE DEPUNERE A OFERTELOR, 23.11.2021 - DATA FINALIZARE PROCEDURA DE EVALUARE

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

2 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE RAMNICU VALCEA 0+000 21+837 SC SEARCH CORPORATION SRL RAMNICU VALCEA PROIECTARE 21.84 30% 0% 16.12.2019 2022 276.36 MIL. LEI FARA TVA

CONTRACT DE SERVICII DE PROIECTARE ACTUALIZARE A STUDIULUI INITIAL INCLUSIV DOCUMENTATII PENTRU AVIZE,OBTINERE AVIZE SI ACORDURI,

ELABORARE PROIECT TEHNIC INCLUSIV DTAC, DETALII DE EXECUTIE SI ASISTENTA TEHNICA PENTRU OBIECTIVUL VARIANTA DE OCOLIRE RM. VALCEA NR.

148 /04.10.2019, CU ORDIN DE INCEPERE ACTIVITATI EMIS IN DATA DE 16.12.2019, IN DERULARE. PRESTATOR SC SEARCH CORPORATION SRL.

VALOAREA CONTRACT PROIECTARE: 3,832,075.75 LEI FARA TVA.

DOCUMENT DE AVIZARE CTE-CNAIR NR. 4915/09.04.2020 - ACTUALIZARE SF - ALTERNATIVE DE TRASEU.

CERTIFICATUL DE URBANISM NR. 12/10054/06.08.2020 EMIS DE C.J. VALCEA ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI

NEFAVORABIL AL PRIMARIEI ORASULUI CALIMANESTI.

DOCUMENT DE AVIZARE CTE-CNAIR NR. 4992/19.10.2020 - ACTUALIZARE SF - ALTERNATIVE DE TRASEU (AMC ETAPA 4) - VARIANTE PENTRU

RACORDAREA LA CENTURA CALIMANESTI.

C.J. VALCEA A EMIS UN NOU CERTIFICAT DE URBANISM, NR. 70/16141/23.11.2020, CARE SPECIFICA FAPTUL CA ""NU POATE FI UTILIZAT IN SCOPUL

DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARULUI COMUNEI DAESTI.

DOCUMENT DE AVIZARE CTE-DRDP CRAIOVA NR. 3/20.01.2021 - STUDIUL ALTERNATIVELOR DE TRASEU IN ZONA LOCALITATII FEDELESOIU, COMUNA

DAESTI - ETAPA 5. DOCUMENTATIA TEHNICA A FOST INAINTATA LA CJ VALCEA CARE A EMIS CERTIFICATUL DE URBANISM NR. 05/19899/26.01.2021

CARE ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARULUI COMUNEI DAESTI.

S-A EMIS ORDIN DE SISTARE DIN DATA DE 29.01.2021. AU FOST INITIATE DEMERSURI IN VEDEREA ADRESARII INSTANTELOR JUDECATORESTI

COMPETENTE PENTRU CHEMARE IN JUDECATA A C.J. VALCEA SI A REPREZENTANTULUI UAT DAESTI.

3 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE REGHIN 0+000 10+440 SC TPF INGINERIE SRL REGHIN 1 10.44 05.12.2019 2021 108.11 MIL. LEI FARA TVACONTRACT PRESTARI SERVICII COMPLETARE STUDIU DE FEZABILITATE SEMNAT LA DATA DE 05.12.2019, IN DERULARE.

CONTRACT COMPLETARE SF IN DERULARE

4 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE TARGU MURES 0+000 11+643 TARGU MURES

RELICITAREA LUCRARILOR RAMASE

DE EXECUTAT SE VA REALIZA IN 2

ETAPE:

ETAPA 1: REVIZUIRE PROIECT TEHNIC

ETAPA 2: LICITATIE LUCRARI RAMASE

DE EXECUTAT, CORELATE CU

PROIECTUL TEHNIC REVIZUIT

11.643

34.26% -PROGRES INREGISTRAT IN

CADRUL CONTRACTULUI DE LUCRARI

REZILIAT

37.55% - PROGRES FINANCIAR

INREGISTRAT LA DATA REZILIERII

09.10.2014 (ORDIN DE INCEPERE

PENTRU CONTRACTUL REZILIAT)

ORDIN DE INCEPERE A LUCRARILOR -

PENTRU CONTRACTUL RELICITAT - VA

FI SPECIFICAT ULTERIOR SEMNARII

ACESTUIA

CONTRACT 1 INCETAT PE CALE

AMIABILA IN 29.12.2017 ANUL 2023 134.80 MIL. LEI FARA TVA

COPISA CONSTRUCTORA PIRENAICA SA - CONTRACT REZILIAT

LICITATIE ATRIBUIRE CONTRACT REST LUCRARI RAMASE DE EXECUTAT, CU TERMEN DEPUNERE OFERTE: 26.08.2020

PROCEDURA ANULATA ADMINISTRATIV PENTRU NEDEPUNERE DE OFERTE

DEMERSURILE IN VEDEREA ACTUALIZARII PROIECTULUI TEHNIC SUNT DEMARATE DE CATRE DRDP BRASOV.

IN DATA DE 23.02.2021, A FOST PUBLICAT IN SEAP ANUNTUL NR. CN1029446 CU PRIVIRE LA ACHIZITIA PUBLICA CARE VA AVEA CA SCOP ACTUALIZAREA

DOCUMENTATIEI TEHNICE PT+DDE VARIANTA DE OCOLIRE TARGU MURES.

PROCEDURA DE LICITATIE IN DERULARE LA NIVELUL DRDP BRASOV

5 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE ALTERNATIVA TECHIRGHIOL 0+000 28+833SC CONSITRANS SRL - CONTRACT PROIECTARE ELABORARE SF, PT SI

DTACTECHIRGHIOL 1 28.833 30% 0% FEBRUARIE 2020 DECEMBRIE 2021 DECEMBRIE 2021 5.372 MIL. LEI FARA TVA

"CONTRACTUL PENTRU ELABORARE SF, PT SI DTAC A FOST SEMNAT IN DATA DE 26.07.2019 .

ORDINUL DE INCEPERE A FOST EMIS IN LUNA FEBRUARIE 2020.

STUDIU DE FEZABILITATE FINALIZAT, URMEAZA PARCURGEREA PROCEDURII PRIVIND APROBAREA INDICATORILOR TEHNICO-ECONOMICI (AVIZ CTE

CNAIR, AVIZ MT, AVIZ CI SI HG). DUPA EMITEREA HG, TERMENUL CONTRACTUAL PENTRU EMITERE PT ESTE 3 LUNI.

AMC 1+2 A FOST AVIZAT IN CADRUL CTE CNAIR SA.

IN CURS DE FINALIZARE INVESTIGATIILE GEOTEHNICE DE TEREN."

6 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE VASLUI 0+000 14+940 CONTRACT REVIZUIRE SF IN DERULARE VASLUI 1 14.94 2019 2021 142.8 MIL. LEI FARA TVA

SF - 2006 (AVIZ MT 36/27/19.03.2007).

CONTRACT REVIZUIRE SF SI ELABORARE PT + DTAC SEMNAT IN LUNA MAI 2019 - IN DERULARE, CU TERMEN DECALAT FINALIZARE SEPTEMBRIE 2021

DURATA REVIZUIRE SF – 8 LUNI AVIZ CTE DRDP IASI NR. 16891/19.04.2021

DURATA ELABORARE PT – 6 LUNI

VALOARE CONTRACT PROIECTARE: 1.478.500 LEI

7 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE PITESTI VEST 0+000 20+000 TPF INGINERIE SRL PITESTI VEST 20 0% 0%

CONTRACT IN DERULARE.

A AVUT LOC SEDINTA NR. 1 DE PROGRES IN DATA DE 25.03.2021.

IN DATA DE 26.04.2021 PRESTATORUL A TRANSMIS STUDIUL DE PREFEZABILITATE CONFORM GRAFICULUI ACTIVITATILOR. AU FOST FORMULATE

OBSERVATII ASUPRA DOCUMENTATIE STUDIUL DE PREFEZABILITATE. PRESTATORUL A TRANSMIS SPF-ul REVIZUIT.

A FOST PREDAT STUDIUL DE TRAFIC REVIZUIT. IN CURS DE ANALIZA LA BENEFICIAR (TRANSMIS LA CESTRIN)

14.03.2018

2021 - FINALIZARE ETAPA DE

PROIECTARE.

DURATA DE EXECUTIE A LUCRARILOR

: 36 DE LUNI DE LA ORDINUL DE

INCEPERE, DUPA FINALIZAREA

SERVICIILOR DE PROIECTARE SI

OBTINEREA AUTORIZATIEI DE

CONSTRUCTIE

ANUL 2020

VALOARE PROIECT 1.6 MIL LEI FARA

TVA;

VALOARE LUCRARI CF. SF - VARIANTA

4 AVIZATA: TOTAL GENERAL - 343.36

MIL LEI FARA TVA

1

4.2. VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE LUCRARI - IUNIE 2021

4.3. VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC -- IUNIE 2021

CONTRACT PRESTARI SERVICII DE PROIECTARE FAZELE SF+PT+DE+DATC+AT SEMNAT IN DATA DE 14.03.2018

IN DATA DE 26.03.2018 S-A EMIS ORDINUL DE INCEPERE NR.3B/4773/26.03.2018 PENTRU SERVICII DE PROIECTARE IN FAZA SF.

SF FINALIZAT SI APROBAT PRIN HG INDICATORI TEHNICO-ECONOMICI NR. 58/24.02.2021.

ORDIN DE INCEPERE PENTRU PT+DTAC SI AVIZE - NR. 3B/4773/26.03.2018 - INCEPAND CU 01.10.2020.

PROIECTUL TEHNIC A FOST PREDAT IN 29.01.2021.

MAI SUNT DE ELABORAT : DETALII DE EXECUTIE 1 LUNA, PREGATIRE DOCUMENTATIE DE ATRIBUIRE PENTRU ACHIZITIA LUCRARI DE EXECUTIE: 2 LUNI,

DOCUMENTATIA CADASTRALA PENTRU HG DE EXPROPRIERI DE UTILITATE PUBLICA;

MAI SUNT DE OBTINUT: CTE CNAIR PENTRU PT+DTAC, AUTORIZATIA DE CONSTRUIRE SI HG DE EXPROPRIERI DE UTILITATE PUBLICA;

DOCUMENTATIA PENTRU PROMOVAREA HG DE EXPROPRIERI SI DOCUMENTATIA PT + DTAC SUNT CONDIȚIONATE DE UN PUNCT DE VEDERE AFIR CU

PRIVIRE LA SUPRAPUNEREA OBIECTIVULUI VO GIURGIU PESTE UN OBIECTIV PRIVAT FINANTAT PE FONDURI EUROPENE AFIR.

IN DATA DE 25.05.2021 A AVUT LOC O SEDINTA DE LUCRU LA SEDIUL MINISTERULUI TRANSPORTURILOR LA CARE PROIECTANTUL VO GIURGIU A

PREZENTAT O SOLUTIE DE PROIECTARE PRIN MODIFICAREA PROFILULUI TRANSVERSAL AL VO, PRIN CARE SE EVITA DEMOLAREA HALEI DE

PROCESARE(SERA DE LEGUME), DAR CARE VA AFECTA BAZINUL DE RETENTIE IMPREJMUIREA SI DOUA CONSTRUCTII ANEXE.

IN DATA DE 02.06.2021 AFIR A TRANSMIS ACORDUL CA BENEFICIARUL PRIVAT S-A MODIFICE AMPLASAMENTUL AFECTAT DE EXPROPRIERE NECESARA

REALIZARII VO GIURGIU CU CONDITIA MENTINERII CONDITIILOR DE ELIGIBILITATE SI SELECTIE INSCRISE IN CEREREA DE FINANTARE.

IN DATA 04.06.2021 A FOST AVIZATA IN CTE DRDP BUCURESTI DOCUMENTATIE PT+DTAC.

IN DATA DE 16.06.2021 A FOST INAINTATA LA CNAIR DOCUMENTATIA IN FAZA PT +DTAC PENTRU PROGRAMARE ANALIZA SI AVIZARE IN CTE CNAIR SI

PENTRU APROBAREA MODIFICARILOR NECESARE FATA DE SOLUTIA APROBATA LA FAZA SF .

IN DATA DE 25.06.2021 CA URMARE A SOLICITARII CNAIR - DEPARTAMENT OBTINERE FINANTARI PRIN ADRESA NR. 3B/ 2737/25.06.2021, DRDP

BUCURESTI A INAINTAT DOCUMENTATIILE TEHNICE IN FAZELE SF - FINAL AVIZAT, PT + DTAC IN VARIANTA INAINTATA LA CTE CNAIR, PENTRU A FI PUSE

LA DISPOZITIA CONSILIULUI JUDETEAN GIURGIU PENTRU INCHEIEREA UNUI PARTENERIAT PENTRU IMPLEMENTAREA OBIECTIVULUI IN TEMEIUL OUG

NR. 101/2020.

VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE GIURGIU 0+000 12+068CONTRACT ELABORARE FAZE DE PROIECTARE SF+PT+DE+DTAC+AT

IN DERULAREGIURGIU 1

12.068 CONFORM VARIANTEI DE

TRASEU APROBATA

70% - SF FINALIZAT SI APROBAT PRIN

HG INDICATORI TEHNICO -

ECONOMICI NR. 58/24.02.2021

57%

Page 10: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021 1

8 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE DOROHOI 0+000 13+900 SC NV CONSTRUCT SRL DOROHOI 13.9 0% 0% 429.22 MII LEI IN CURS DE FINALIZARE STUDIUL DE FEZABILITATE, DUPA APROBARE PUZ DOROHOI

9 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE TIMISOARA VEST 0+000 22+000 SEARCH CORPORATION SRL TIMISOARA 22 18.01.2021 18.04.2022 3.66 MIL. LEI FARA TVA

CONTRACT IN DERULARE.

IN DATA DE 20.05.2021 FOST AVIZAT IN CTE CNAIR SA - ANALIZA MULTICRITERIALA ETAPA 1.

IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA 2

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

1 VARIANTE OCOLITOARE IN PREGATIRE FAZA PROIECTARE VARIANTA OCOLITOARE VARIANTA OCOLITOARE BISTRITA 0+000 15+000 BISTRITA 1 152.33 MIL LEI FARA TVA (VALOARE

ESTIMATA CONTRACT S.F.)

PROCEDURA DE ACHIZITIE PUBLICA PENTRU CONTRACTUL DE SERVICII DE „ELABORARE STUDIU DE FEZABILITATE PENTRU VARIANTA DE OCOLIRE

BISTRITA”, A FOST ANULATA.

OBIECTIVUL FACE PARTE DIN ,,AUTOSTRADA NORDULUI” – FIIND SPECIFICAT IN STUDIUL DE FEZABILITATE CA DRUMUL DE MARE VITEZA BAIA MARE-

SUCEAVA: LOT 1 BAIA MARE-BISTRITA SI LOT 2 BISTRITA-VATRA DORNEI, VA INDEPLINI SI FUNCTIA DE VARIANTA DE OCOLIRE PENTRU LOCALITATILE

INTERSECTATE DE ACESTA.

2 VARIANTE OCOLITOARE IN PREGATIRE FAZA PROIECTARE VARIANTA OCOLITOAREDRUM DE LEGATURA DN6 - DRUM EXPRES

CRAIOVA-PITEȘTI (TRONSONUL 1)- -

INITIERE PROCEDURA DE ACHIZITIE ATRIBUIRE CONTRACT DE

PRESTARI SERVICII DE PROIECTARE- - 10 km - -

CNAIR SA A TRANSMIS CATRE MINISTERUL TRANSPORTURILOR SI INFRASTRUCTURII CEREREA DE FINANTARE PENTRU PROIECTUL: "ELABORARE STUDIU

DE FEZABILITATE, PROIECT TEHNIC DE EXECUȚIE INCLUSIV PAC, DETALII DE EXECUTIE, ASIGURAREA ASISTENTEI TEHNICE PE PARCURSUL EXECUȚIEI DE

LUCRARI SI IN PERIOADA DE GARANTIE A LUCRARILOR EXECUTATE PENTRU OBIECTIVUL DE INVESTIȚIE: DRUM DE LEGATURA PENTRU SPORIREA

CAPACITATII DE TRAFIC INTRE DN6 (ZONA UZINEI FORD) SI DRUMUL EXPRES CRAIOVA – PITESTI (TRONSONUL 1)".

DRDP CRAIOVA A INTOCMIT CAIETUL DE SARCINI PENTRU ACHIZITIA SERVICIILOR DE PROIECTARE AFERENTE PROIECTULUI, PRECUM SI REFERATUL DE

NECESITATE PENTRU INTRODUCEREA IN PAAP 2021 A PROCEDURII DE ACHIZITIE CU O VALOARE ESTIMATA A CONTRACTULUI DE 1.500.000 LEI

INCLUSIV TVA. OBIECTIVUL A FOST INCLUS IN PAAP PENTRU ANUL 2021 AL DRDP CRAIOVA.

DURATA ESTIMATA A PRESTARII SERVICIILOR ESTE DE 89 LUNI (3 LUNI – ELABORARE SF INCLUSIV DOCUMENTATII PENTRU OBTINERE AVIZE/ACORDURI;

2 LUNI – ELABORARE PT INCLUSIV DTAC SI DE; 24 LUNI – ASISTENTA TEHNICA PE PARCURSUL EXECUTIEI LUCRARILOR; 60 LUNI – ASISTENTA TEHNICA IN

PERIOADA DE GARANTIE A LUCRARILOR).

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

1 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 29+500 33+190 ITINERA SPA

LARGIRE LA 4 BENZI A CENTURII

RUTIERE A MUNICIPIULUI BUCURESTI

SUD INTRE A2 KM 23+600 SI A1 KM

55+520

AMENAJARE NOD RUTIER LOT 1:

OLTENITA - DN 43.69 22.00% 32.00%

31.07.2019 - DATA DE INCEPERE

PERIOADA DE PROIECTAREESTIMAT 2022 SEPTEMBRIE 2022 169.5 MIL. LEI FARA TVA

CONTRACTUL DE EXECUTIE LUCRARI A FOST SEMNAT IN DATA DE 20.06.2019/ AUTORIZATIE DE CONSTRUIRE VALABILA.

LUCRARI IN EXECUTIE: LA DRUM - EXCAVATII PE DN CB SI PE BRETELE TRANSPORT AGABARITIC AG 1 SI AG2, EXECUTIE STRAT DE FORMA PE DN 4, PE AG1

SI AG2 SI PE DNCB.

LA PASAJ - ARMARE SI COFRARE RIGLE P3B, P4B SI P4B1, ARMARE SI COFRARE RADIERE P5A, P4A SI SP1A, ARMARE SI COFRARE ELEVATII PILE P3A1, P2A

SI P2A1.

RELOCARE UTILITATI - RELOCARE DE RETELE ELECTRICE SI RETEA GAZ, CONTINUARE MONTARE CONDUCTA NOUA GAZ PE DNCB, TELECOM - INTREGIRE

TRASEU FIBRA OPTICA RELOCATA PE DNCB SI RELOCARE RETELE ELECTRICE PE AG2 SI MONTARE CABLU JT, CONTINUARE EXECUTIE CANALIZARE PE DN 4

CU PVC SI PE DNCB CU PAFSIN.

2 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 12+300 23+750 TIRRENA SCAVI S.P.A

MODERNIZAREA CENTURII RUTIERE A

MUNICIPIULUI BUCURESTI INTRE A1 -

DN7 SI DN2 - A2

SECTIUNEA DN 2 - A2 11.524 7.59% 17.61% 04.05.2020 ESTIMAT AUGUST 2021 ANUL 2022 235.75 MIL. LEI FARA TVA

1. CONTRACTUL DE EXECUTIE LUCRARI A FOST SEMNAT IN DATA DE 02.03.2020/ AUTORIZATIE DE CONSTRUIRE VALABILA.

LUCRARI IN EXECUTIE: DEMONTARE ESAFODAJ PILA P12, DECOFRARE CUZINETI SI OPRITOR ANTISEISMIC PILA Pila P12, DECOFRARE CUZINETI SI

OPRITOR ANTISEISMIC PILA P11, MONTARE ESAFODAJ PILA P1, EVACUARE APE DIN ZONA RADIERE CULEE C1, PILA P8 SI PILA P9

3 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 33+190 35+600

ASOCIEREA S.C. TRAMECO S.A. - VAHOSTAV -SK,

A.S. - CONSTRUCTII ERBASU S.A. - GRAFIC TENDS S.R.L. S.C. (LIDER

DE ASOCIERE TRAMECO S.A.)

LARGIRE LA 4 BENZI A CENTURII

RUTIERE A MUNICIPIULUI BUCURESTI

SUD INTRE A2 KM 23+600 SI A1 KM

55+520

AMENAJARE NOD RUTIER LOT 2:

BERCENI - DJ 4012.41 20.21% 13.87% 06.05.2019 ESTIMAT 2022 IUNIE 2022 146 MIL. LEI FARA TVA

CONTRACTUL DE PROIECTARE SI EXECUTIE PASAJ BERCENI A FOST SEMNAT IN DATA DE 19.03.2019.

LUCRARI CE SE EXECUTA: CANALIZARE PLUVIALA, STRAT DE FUNDATIE DIN BALAST, STRAT SUPERIOR DE FUNDATIE DIN BALAST STABILIZAT, RELOCARI

FIBRA OPTICA PE ZONA SOSEAUA BERCENI, MONTARE IZOLATORI SEISMICI, UMPLUTURI DIN PAMANT LA TERSAMENTE SI UMPLUTURI ARMATE DIN

BALAST LA RAMPE PASAJ, ASTERNERE STRAT DE BAZA AB31,5.

4 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 55+465 64+160ASOCIEREA S.C. DELTA A.C.M. 93 SRL & AZVIRT LLC & S.C.

MAXIDESIGN S.R.L. - CONTRACT REZILIAT

MODERNIZAREA CENTURII RUTIERE A

MUNICIPIULUI BUCURESTI INTRE A1 -

DN 7 SI DN 2-A2:SECTIUNEA A1 (KM

55+465) - DN 7 (KM 64+160)

SECTIUNEA A1 KM 55+465 - DN7 KM

64+1608.695

86.5% - PROGRES FIZIC LA DATA

REZILIERII

77.73% - PROGRES FINANCIAR LA

DATA REZILIERII2021 TRIM IV 2022 106.6 MIL. LEI FARA TVA

A FOST DEMARATA PROCEDURA DE ACHIZITIE PUBLICA PENTRU LUCRARI DE REMEDIERE SI FINALIZARE LUCRARI - REST DE EXECUTAT.

A FOST PUBLICAT ANUNTUL DE PARTICIPARE.

DETALII IN LINK-UL DE MAI JOS:

http://www.cnadnr.ro/

sites/default/files/DRU

MURI_NA%C8%9AIONA

LE_%C8%98I_VARIANTE

_DE_OCOLIRE_CALEND

AR.pdf

5 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI SC STRABAG SRL

PROIECTARE SI EXECUTIE PASAJ

MOGOSOAIA PE CENTURA

BUCURESTI PESTE DN 1A

MOGOSOAIA/ DN 1A 0.8 49.63% 37.29%04.12.2018 - PROIECTARE;

02.04.2020 - EXECUTIE

2021- CONFORM ASUMARI

ANTREPRENOR

ANUL 2022 CONFORM GRAFIC

CONTRACT32.26 MIL. LEI FARA TVA

CONTRACT SEMNAT IN DATA DE 23.10.2018.

AUTORIZATIA DE CONSTRUIRE NR. 13 DIN DATA DE 16.03.2020.

ORDINUL DE INCEPERE PENTRU PROIECTARE A FOST DAT IN DATA DE 04.12.2018.

ORDINUL DE INCEPERE PENTRU LUCRARI A FOST EMIS IN DATA DE 02.04.2020

LUCRARI CE SE EXECUTA: ARMARE GRINDA CORONAMENT RAMPA OTOPENI, ARMARE ANANTRETOAZA PILA P1, ARMARE PLACA DE SUPRABETONARE

INTRE PILA P3 SI CULEEA OTOPENI, UMPLUTURA RAMPA CHITILA, MONTARE ELEMENTE PREFABRICATE RAMPA CHITILA

6 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI

PENETRATIE PRELUNGIREA GHENCEA

– DOMNESTI SI SUPRALARGIRE

BULEVARDUL GHENCEA INTRE

STRADA BRASOV SI TERMINAL

TRAMVAI 41” CU PROIECTUL “PASAJ

SUPRATERAN PE DJ 602, CENTURA

BUCURESTI - DOMNESTI

1.1139.255 MII lei FARA TVA - VALOARE

PROIECTARE

4.4. VARIANTE OCOLITOARE IN PREGATIRE FAZA PROIECTARE - IUNIE 2021

4.5. VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE - IUNIE 2021

Page 11: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021 1

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

1VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE

LOCALEVARIANTA OCOLITOARE VARIANTA OCOLITOARE ALESD 0+000 16+840 ALESD 16.84

OBIECTIVUL A FOST TRANSFERAT CATRE CJ BIHOR IN VEDEREA REVIZUIRII DOCUMENTATIEI TEHNICE SI IMPLEMENTARII ACESTUIA IN BAZA OUG

101/2020.

DECEMBRIE 2020 - A FOST SEMNAT UN PARTENERIAT INTRE CNAIR SI CJ BIHOR IN ACEST SENS

IN DATA DE 20.05.2021 A FOST AVIZAT IN CADRUL CTE CNAIR SA STUDIUL DE FEZABILITATE.

IN DATA DE 21.05.2021 A FOST AVIZAT IN CADRUL CTE MTI STUDIUL DE FEZABILITATE

IUNIE 2021- URMEAZA AVIZAREA IN CADRUL CTE IM SI PROMOVAREA HG DE APROBARE A INDICATORILOR TEHNICO ECONOMICI

2VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE

LOCALEVARIANTA OCOLITOARE VARIANTA OCOLITOARE IASI

19+690

(SELGROS)

26+460

(DN28)

ETAPA I – VARIANTA SUD OBIECT 3 –

VARIANTA TRAFIC GREU6.77

126.88 MIL. LEI FARA TVA (VALOARE

ESTIMATA)

PENTRU IMPLEMENTAREA ACESTUI OBIECTIV PRIMARIA MUNICIPIULUI IASI A INAINTAT O PROPUNERE DE SCHIMBARE A TRASEULUI, CA URMARE A

IMPOSIBILITATII PASTRARII TRASEULUI PE BULEVARDUL POITIERS SI STRADA TREI FANTANI (KM 19+690 - KM 26+460).

PROPUNEREA A FOST ACCEPTATA DE CNAIR, URMAND A SE IDENTIFICA SURSA DE FINANTARE.

3VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE

LOCALEVARIANTA OCOLITOARE VARIANTA OCOLITOARE MEDIAS 0+000 8+500 MEDIAS 1 8.5 2022 2024

PENTRU IMPLEMENTAREA ACESTUI OBIECTIV A FOST SEMNAT UN PARTENERIAT DE IMPLEMENTARE INTRE CNAIR SA SI PRIMARIA MEDIAS IN BAZA

PREVEDERILOR OUG 101/2020.

OBIECTIVUL SE IMPLEMENTEAZA DE CATRE UAT MEDIAS.

A FOST SEMNAT CONTRACTUL DE REVIZUIRE A STUDIULUI DE FEZABILITATE DE CATRE PRIMARIA MEDIAS IN LUNA IUNIE 2021.

A FOST EMIS ORDINUL DE INCEPERE IN DATA DE 10.06.2021 - TERMEN PENTRU EMITEREA RAPORTULUI DE INCEPUT- 31.07.2021

4VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE

LOCALEVARIANTA OCOLITOARE VARIANTA OCOLITOARE STEI 0+000 27+230

COPISA CONSTRUCTORA PIRENAICA SA - CONTRACT REZILIAT

LICITATIE ATRIBUIRE CONTRACT REST LUCRARI RAMASE DE

EXECUTAT, CU TERMEN DEPUNERE OFERTE : 22.06.2020

STEI 1 27.23 0% 0%CONTRACT REZILIAT DE CATRE

ANTREPRENOR

CONTRACT REZILIAT DE CATRE

ANTREPRENOR

CONTRACT REZILIAT DE CATRE

ANTREPRENOR257.413 MIL. LEI FARA TVA

OBIECTIVUL A FOST TRANSFERAT CATRE CJ BIHOR IN VEDEREA REVIZUIRII DOCUMENTATIEI TEHNICE SI IMPLEMENTARII ACESTUIA IN BAZA OUG

101/2020.

A FOST SEMNAT IN LUNA DECEMBRIE 2020, PARTENERIATUL INTRE CNAIR SI CJ BIHOR IN ACEST SENS.

CONTRACT REVIZUIRE STUDIU DE FEZABILITATE IN DERULARE - ESTIMAT FINALIZARE TRIM. III 2021

4.6. VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE LOCALE - IUNIE 2021

Page 12: SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - IUNIE 2021 1

NR.

CRT.CATEGORIE DRUM RANG DRUM INDICATIV DRUM

DE LA

(km)

PANA LA

(km)ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL

STADIUL FINANCIAR

ACTUALDATA INCEPERII DATA FINALIZARII AN DESCHIDERE VALOARE PROIECT OBSERVATII

DETALII

PROCEDURA

1 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE RADAUTI 0+000 16+580 SPEDITION UMB - SC TEHNOSTRADE SRL RADAUTI 1 16.58 08.10.2018 20.11.2020 ANUL 2020 97.44 MIL. LEI FARA TVA

LUCRARI FINALIZATE - 20.11.2020

PENTRU ACEST PROIECT A FOST FINALIZAT PROCESUL DE ACCESARE A FINANTARII NERAMBURSABILE ALOCATE IN CADRUL POIM 2014-2020, FIIND

EMISA NOTA DE APROBARE A FINANTARII ACESTUIA DIN FONDURI NERAMBURSABILE IN LUNA DEC. 2020.

CONTRACT DE FINANTARE A LUCRARILOR EXECUTATE IN CADRUL POIM 2014-2020 SEMNAT IN LUNA IANUARIE 2021

2 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE SACUENI 0+000 7+620 SC ANTREPRIZA DE REPARATII SI LUCRARI ARL CLUJ SA SACUENI 7.62 10.09.2019 12.08.2020 DECEMBRIE 2020 42.83 MIL. LEI FARA TVA

LUCRARILE AU FOST FINALIZATE SI VARIANTA DE OCOLIRE SACUENI ESTE IN DATA IN CIRCULATIE INCEPAND CU 09.12.2020.

MOMENTAN SE AFLA IN PROCEDURA DE RECEPTIE LA TERMINAREA LUCRARILOR, FIIND REALIZATA INSPECTIA PRELIMINARA (10.06.2021) IN URMA

CAREIA ANTREPRENORUL ARE LA DISPOZITIE 30 ZILE PENTRU REMEDIEREA DEFECTIUNILOR CONSTATATE DE COMISIE. SE ESTIMEAZA CA R.T.L. SE VA

REALIZA IN LUNA IULIE 2021.

3 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE SUCEAVA 0+000 7+285

ASOCIEREA S.C. AUTOTEHNOROM S.R.L. (LIDER) – S.C.

OPERATIONAL AUTOLEASING S.R.L. – S.C. OPR ASFALT S.R.L. –

OBRAS PUBLICAS Y REGADIOS S.A. – S.C. FLORCONSTRUCT S.R.L. –

S.C. CALCARUL S.A.

SUCEAVA 1 7.285DESCHISA TRAFICULUI - IN DATA DE

27 SEPT. 201977% 01.10.2018

IUNIE 2021 - RECEPTIE LA

TERMINAREA LUCRARILOR

IUNIE 2028 - RECEPTIE FINALA

IUNIE 2021 - FINALIZARE LUCRARI

AUXILIARE63.85 MIL. LEI FARA TVA

4 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOAREVARIANTA OCOLITOARE CARACAL -

RELICITARE0+000 10+345 ASOCIEREA SECOL S.A. - S.E.C.O.L S.P.A. CARACAL 10.345 100% 97.05% 16.10.2014 RTL: 24.05.2018 41.69 MIL. LEI FARA TVA

24.05.2018 - A FOST REALIZATA RTL

IN DATA DE 10.11.2020 A FOST REALIZATA RECEPTIA FINALA

5 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE BRASOV 0+000 7+292ASOCIEREA CHIRULLI ANDREA IMPRESA INDIVIDUALE - ALEANDRI

SPA - SMART BUILDING PROJECT- PASQUALE ALO' SRLTRONSON I, DN1 - DN 11 LOT 1 - RELICITARE 100% 90.18% 16.12.2014

RTL: 28.11.2016;

RF:19.12.201959.56 MIL. LEI FARA TVA

IN DATA DE 29.11.2016 A AVUT LOC RECEPTIA LA TERMINAREA LUCRARILOR. LA DATA PREZENTEI CONTRACTUL SE AFLA IN PERIOADA DE NOTIFICARE A

DEFECTIUNILOR.

IN DATA DE 19.12.2019 A FOST APROBAT PROCESUL VERBAL DE RECEPTIE FINALA.

6 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE BRASOV 0+000 4+924ASOCIEREA SC VIAROM CONSTRUCT SA - SC BETA COPS SRL - SC

MAXIDESIGN SRLTRONSON II, DN11 - DN13 LOT 3 4.924 100% 98.77% 07.08.2014

RECEPTIE LA TERMINAREA

LUCRARILOR: 29.11.201964.42 MIL. LEI FARA TVA PROCESUL VERBAL DE RECEPTIE LA TERMINAREA LUCRARILOR A FOST APROBAT DE DIRECTORUL GENERAL AL CNAIR IN DATA DE 29.11.2019.

4.7. VARIANTE OCOLITOARE IN FOLOSINTA - IUNIE 2021