proiect mc
TRANSCRIPT
UNIVERSITATEA TEHNICĂ DIN CLUJ-NAPOCAFACULTATEA DE CONSTRUCŢII
SPECIALIZAREA INGINERIE ECONOMICĂAN III, GRUPA 3533
PROIECTMANAGEMENTUL IN CONSTRUCTII
AN UNIVERSITAR2010-2011
NEAGU ANA MARIA NECHITA VLASIN LIGIA PAISVANTE OANA FLORINA
Borderou
Piese scrise – Foaie de capăt- Borderou- Lista de lucrari- Antemăsurătoare- Note de calcul- Deviz
Piese desenate- Plan fundaţii- Plan subsol- Plan parter- Plan mansarda- Plan invelitoare- Secţiune transversală- Faţade
2
Lista de lucrari
Rezistenta suprastructura
-stalpi: cofraj,armatura ,beton-placa din beton armat: cofraj,armatura , beton-ziduri exterioare: caramida cu goluri verticale,mortar-ziduri interioare: caramida cu goluri verticale,mortar-scara: cofraj,armatura ,beton
Inchideri,compartimentari
-pereti despartitori-ferestre-usi
3
ANTEMĂSURĂTOARE
OBIECTIV: CASA DE LOCUIT
SUPRASTRUCTURA.COMPARTIMENTARI SI INCHIDERI
1.Suprastrucura NR.CRT.
SIMBOLARTICOLDENUMIRE ARTICOL
U.MCANTITATE
1
CB04B1Cofraje pt beton armat in placi, grinzi, stalpi, din panouri refolosibile, cu astereala din scanduri de rasinoase la ctii pana la 20 m
mp
2CB02CCofraje din panouri refolosibile cu astereala din scanduri pt : placi si grinzi exclusiv sustinerile la inaltimi pana la 20 m inclusiv
mp
3
CB05A1Cofraje in elemente turnate in interiorul constr. din panouri de scanduri cu H < 35 mCofraje pt scari
mp
4
CC02C1Montarea armăturilor din oţel-beton în elemente de construcţii, exclusiv cele din construcţiile executate în cofraje glisante la construcţii executate la o înălţime până la 35 m inclusiv, din bare fasonate având diametrul până la 18 mm inclusiv, in grinzi, stalpi, placi
kg
5CZ0302M1
kg
4
Montarea armaturilor pt placi inclusiv scari , podeste la constr. obisnuite in ateliere centralizate
6
CZ0302A1Confecţionarea armăturilor din oţel beton pentru beton armat în elemente de construcţii turnate în cofraje, exclusiv cele executate în cofraje glisante fasonarea barelor pentru pereţi, grinzi, stâlpi, placi şi diafragme la construcţii obişnuite, în ateliere centralizate
kg
7TRA02A10Transportul rutier al materialelor,semifabricatelor cu autocamionul pe dist.= 10 km.
tone
8
CZ0105A1Beton marca B 150, cu agregate grele, sortate cu granulaţia până la 16 mm (pentru beton simplu sau armat în plăci, grinzi, stalpi, diafragme, scări, elemente cu secţiuni mici la construcţii cu 2—3 nivele şi deschideri sub 5 m), preparat cu ciment M 30 in instal. centalizate
mc
9TRA06A10Transportul rutier al betonului-mortarului cu autobetoniera de 5,5mc dist. =10km
tone
10
CA02J1 corectatTurnare beton armat la ctii cu inaltimea pana la 35 m inclusiv in plansee(grinzi,stalpi, placi) cu grosimea placii > 10 cmTurnare beton in scari
mc
11
CD05A2Zidărie din cărămidă cu găuri verticale tip GVP la construcţii executate la o înălţime până la 35 m inclusiv, cu cărămizi format 240x115x88 mm, calitatea I
mc
12CZ0202F1Mortar de var - ciment pentru zidarie marca M 25-Z preparat cu ciment F 25 şi var hidratat, manual;
mc
5
13AUT 1325A1Ora pt pop metalic extensibil pe 3100 incl, teava 51x3.5 mm 3sch
ora
14CB44A1Sustineri cu popi metalici extensibili tip PE3100R
buc
15MDTC552025Transport utilaj 25 km- pop metalic tip PE-3100
buc
16CH03ATrepte din beton armat turnat monolit sau prefabricat executate brut pt a fi placate
mc
2.Compartimentari si inchideri
17
CD15APereti din panouri de gips-carton montate intr-un strat pe fiecare fata,pe structura metalica,schelet de sustinere intre montanti de 60 cm
mp
18CK52B+Ferestre din lemn stratificat, cu două canaturi (unul fix şi altul mobil), având suprafaţa tocului: intre 1mp şi 2,5 mp inclusiv;
mp
19CK58A+Uşi din lemn stratificat, cu doua canaturi , având suprafaţa tocului: între 1mp şi 2,5 mp inclusiv;
mp
Calcule
Cofraje planseu peste parter
6.30 * 8.05 - 3.35 * 2.15 = 43.51 mp ~ 44 mp
6
Cofraje pt balcoane
7.95 + 4.2 * 1.15 + 4.70 * 1.15 = 18.19 mp ~ 19 mp
Cofraje pt stalpi
0.25 * 2.83 = 0.70 mp0.70 * ( 11 + 4 ) = 10.50 mp * 4 = 42.00 mp0.30 * 2.83 = 0.85 mp0.85 * 2 = 1.70 mp * 4 = 6.80 mp0.25 * 2.05 = 0.513 mp0.513 * 4 = 2.052 mp * 4 = 8.208 mp
Total cofraje pt stalpi = 57.00 mp
Cofraje centura
Pereti exteriori :( 1.75 + 4.00 + 1.75 ) * 0.13 = 0.98 * 2 = 1.96 mp ( 3.75 + 2.25 ) * 0.13 * 2 = 1.56 * 2 = 3.12 mp1.75 * 0.13 * 2 = 0.46 * 2 = 1.04 mp4 * 0.13 = 0.52 * 2 = 1.04 mp1.70 * 0.13 * 2 = 0.44 * 2 =0.88 mpPereti interiori( 1.75 + 4.00 + 5.7 ) * 0.13 = 1.49 * 2 = 2.98 mp
Total cofraje centura = 10.94 mp
Cofraj grinda
4 * 0.32 *2 = 2.56 mp
TOTAL COFRAJE = 132.20 mp ~ 133 mp
Beton pt planseu peste parter
6.3*8.05*0.12=6.09 mc – 0.86 = 5.23 mc
Armatura planseu peste parter
2% * 5.23 = 0.10 mc0.10 mc * 7700 kg/mc = 770 kg
Beton pt stalpi
7
P: 0.30 * 0.30 * 2.83 = 0.25 mc * 2 = 0.50 mc 0.25 * 0.25 * 2.83 = 0.18 mc * 11 = 1.98 mcM: 0.25 * 0.25 * 2.73 = 0.17 mc * 4 = 0.68 mc 0.25 * 0.25 * 2.05 = 0.13 mc * 4 = 0.52 mc
Total = 3.72 mc
Armatura stalpi
Parter : 2% * 2.48 = 0.05 mcMansarda : 2% * 0.68 = 0.014 mc 2% * 0.52 = 0.010 mcTotal = 0.074 mc0.074 mc * 7700 kg/mc = 569.8 kg
Beton pt placa pt balcoane
7.95 * 0.12 = 0.95 mc4.2 * 1.15 * 0.12 = 0.58 mc4.7 * 1.15 * 0.12 = 0.65 mc
Total = 2.18 mc
Armatura placa pt balcoane
2% * 0.95 = 0.019 mc0.019 mc * 7700 kg/mc = 146.3 kg2% * 0.58 = 0.012 mc0.012 mc * 7700 kg/mc = 92.4 kg2% * 0.65 = 0.013 mc0.013 mc * 7700 kg/mc = 100.1 kg
Total = 338.8 kg
Beton pt trepte interioare
0.30 * 0.17 * 1.2 = 0.061 mc0.061 * 17 = 1.04 mc
Armatura trepte interioare
2% * 1.04 = 0.021 mc0.021 mc * 7700 kg/mc = 161.7 kg
Beton pt treptele exterioare
8
0.30 * 0.17 * 2.00 = 0.10 mc 0.10 * 4 = 0.40 mc
Armare trepte exterioare
2% * 0.40 = 0.008 mc0.008 mc * 7700 kg/mc = 61.60 kg
Beton centura
0.98 * 0.24 + 1.56 * 0.24 + 0.46 * 0.24 + 0.52 * 0.30 + 0.44 * 0.24 + 1.49 * 0.24 = = 1.34mc
Armatura centura
2% * 1.34=0.03 mc0.03 mc * 7700 kg/mc = 231 kg
Beton grinda
4.0 * 0.32 * 0.24 = 0.31 mc
Armatura grinda
2% * 0.31 = 0.006 mc0.006 mc * 7700 kg/mc = 46.2kg
TOTAL BETON = 14.22 mc ~ 15 mc TOTAL ARMATURA = 2179.1 kg ~ 2180 kg
Popi
Planseu : 43.51 mp rezulta 44 popiBalcoane: 7.95 mp rezulta 8 popi 4.83 mp rezulta 5 popi 5.41 mp rezulta 6 popi
TOTAL POPI= 63 popi
Zidarie 240x115x88 mm
P1: ( 0.55 + 1.20 + 2.15 + 1.00 + 1.10 ) * 2.90 * 0.24 = 4.12 mcP2: ( 0.25 + 0.70 + 1.50 +1.55 ) * 2.90 * 0.24 = 2.78 mc
Total = 6.90 mc
9
Pereti interiori despartitori
Parter :P1: ( 0.75 + 1.2 + 0.3 ) * 2.70 = 6.08 mpP2: 2.25 * 2.70 = 6.08 mpP3: 2.25 * 2.70 = 6.08 mpP4: ( 0.80 + 0.35 ) * 2.70 = 3.11 mpP5: 1.10 * 2.70 = 2.97 mp
Mansarda : P1: ( 0.90 + 0.90 + 2.05 ) * 2.73 = 10.951 mpP2: ( 1.10 + 1.00 + 0.05 ) * 2.73 = 5.87 mpP3: ( 1.10 + 1.00 ) * 2.73 = 5.73 mpP4: ( 0.225 + 1.00 + 2.83 ) * 2.73 = 11.07 mpP5: ( 0.30 + 1.00 + 2.80 ) * 2.73 = 11.19 mp
Total = 68.91 mp
Goluri – geamuri
Parter :G1: 2.20 * 1.20 = 2.64 mp * 0.24 = 0.63 mcG2: 0.60 * 1.20 = 0.72 mp * 0.24 = 0.17 mcG3: 2.20 * 1.20 = 2.64 mp * 0.24 = 0.63 mc G4: 1.20 * 1.20 = 1.44 mp * 0.24 = 0.35 mcG5: 0.45 * 1.20 = 0.54 mp * 0.24 = 0.113 mcG6: 0.60 * 1.20 = 0.72 mp * 0.24 = 0.17 mcG7: 0.90 * 1.20 = 1.08 mp * 0.24 = 0.26 mcG8: 4 * 1.00 * 1.20 = 4.8 mp * 0.30 = 1.44 mcG9: 0.85 * 1.20 = 1.02 mp * 2 = 2.04 mp
Mansarda :G1: 0.90 * 1.20 = 1.08 mp * 0.24 = 0.26 mcG2: 0.90 * 1.20 = 1.08 mp * 0.24 = 0.26 mcG3: 1.00 * 1.20 = 1.20 mp * 0.24 = 0.29 mcG4: 1.00 * 1.20 = 1.20 mp * 0.24 = 0.29 mcG5: 0.60 * 1.20= 0.72 mp * 0.24 = 0.17mc
Goluri – usi
Parter :U1: 1.00 * 2.10 = 2.10 mp * 0.24 = 0.50 mcU2: 1.60 * 2.10 = 3.36 mp * 0.24 = 0.81 mcU3: 1.00 * 1.20 = 1.20 mp * 0.24 = 0.29 mcU4: 1.20 * 2.10 = 2.52 mp * 0.10 = 0.25 mc
10
U5: 0.80 * 2.10 = 1.68 mp * 0.10 = 0.17 mc
Mansarda:U1: 1.00 * 2.05 = 2.05 mp * 0.24 = 0.50 mcU2: 0.90 * 2.05 = 1.85 mp * 0.24 = 0.44 mcU3: 0.90 * 2.05 = 1.85 mp * 0.24 = 0.44 mcU4: 0.90 * 2.05 = 1.85 mp * 0.24 = 0.44 mcU5: 0.90 * 2.10 = 1.89 mp * 0.10 = 0.19 mcU6: 0.90 * 2.10 = 1.89 mp * 0.10 = 0.19 mcU7: 1.00 * 2.10 = 2.10 mp * 0.10 = 0.21 mc
Goluri
Gol1: 1.20 * 2.60 = 3.12 mp * 0.24 = 0.75 mcGol2: 1.50 * 2.60 = 3.90 mp * 0.24 = 0.94 mc
TOTAL TAMPLARIE GEAMURI = 21.88 mp
Parter : 2.64 + 0.72 + 2.64 + 0.54 + 1.44 + 0.72 + 1.08 + 4.80 + 2.04 = 16.62 mpMansarda : 1.08 + 1.08 + 1.20 + 1.20 + 0.70 = 5.26 mp
TOTAL TAMPLARIE USI = 23.26 mp Parter :
Pereti exteriori :4.43 * 2 + 5.56 + 1.48 + 1.32 = 17.22 mc17.22 – (8 * 0.18 + 0.63 * 2 + 0.35 + 0.13 + 0.26 + 0.50 ) = 12.94 mc Pereti interiori4.03 + 2.69 = 6.72 mc6.72 – (3 * 0.18 + 0.75 + 0.94 + 0.29 ) = 4.20 mc
Mansarda :
Pereti exteriori5.62 + 3.36 + 3.36 + 5.62 = 17.96 mc17.96 – (4 * 0.13 + 4 *0.17 + 0.26 * 2 + 0.29 * 2 + 0.17 + 0.5 + 0.44 * 3 ) = =13.67 mc
TOTAL ZIDARIE 240x115x88 mm = 30.81 mc ~ 31 mc
12.94 + 4.2 + 13.67 = 30.81 mc
Turnare beton
12.43 + 1.34 + 0.31 = 14.08 mc
11
14.08 * 1.008 = 14.19 mc ~ 15 mc
Transport beton
15 mc * 2.4 tone/ mc = 36 tone
Ore de folosire popi metalici
Un pop se foloseste 10 zile.10 * 24 = 240 ore/ pop 240 * 63 popi = 15120 ore
Transport popi
63 bucati Mortar de var ciment
Transport semifabricate
12