p pentayya bs
TRANSCRIPT
-
8/11/2019 p Pentayya Bs
1/26
-
8/11/2019 p Pentayya Bs
2/26
2
The black start procedures should contain the
fol lowing minimum detai ls.1. Generation Securing
2. Generation build-up
Survival and Start-up Power of Power Plant(s).
Power Station(s) with Black-start facility.
3. Build-up of islands
4. List of black start facilities, inter-state/regional ties, synchronizing points and essential
loads to be restored on priority
5. Detailed State/Utility-wise Restoration
plans
-
8/11/2019 p Pentayya Bs
3/26
3
SYSTEM RESTORATION APPROACHES
1. In systems with a fair dispersal of Generating stations with black start
facilities, those generating stations where black start facilities are available,
should be started up and islands formed around these generating stations by
connecting essential loads. These islands are then interconnected at predefined
locations where synchronizing facilities are available. The speed of restoration
enhances with increase in number of black start facilities and their dispersal.
Gujarat, Chhattisgarh and M.P have considerable number of black start facilitieswhile Maharashtra suffers from lack of adequate number of black start
generators. It is required to carefully monitor the operation of the island (re-
integration with rest of the grid) due to small stiffness in islands. One engineer
shall be specifically assigned to monitor one island.
2. While adding loads, care should be taken to ensure step by step
addition keeping in view load characteristics, ie., variation of load with respect
to voltage and frequency and stiffness of island. During cold load pick up
sudden starting of motor loads or power plant auxiliaries like BFP, PA fan etc.,can cause voltage dips due to drawal of high starting currents. Essential loads
can be restarted in steps smaller than 5 MW. It is preferable to restore rotating
type loads which co~tributes to inertia of the island. In any case, load pick up
should not cause frequency excursions greater than 0.5 Hz in the island.
3. The second approach could be followed in case self start facilities
are available at only a few power stations or the stqrt up power has to be
imported from neighbouring regions at one0or two points. In this approach, the
start up power required to be extended to all the generating stations on prioritybasis while restoring few loads and transformers for voltage control. The start
up power available from neighbouring regions at various interconnections have
to be seriously explored since considerable assistance can be availed and the
restored system is connected to stable external systems. The procedures have to
be laid down for quickly harnessing these facilities.
The restoration through this approach could be delayed due to problems in
charging the lines, high voltage, lack of synchronising equipment at certain
substations etc. and may involve system disturbances during restoration.
-
8/11/2019 p Pentayya Bs
4/26
4
OPERATIONAL GUIDELINES.
1. Each SLDC will coordinate synchronisation of
units and transmission lines in its system in consultation with
WRLDC. For ISGS power stations , WRLDC will becoordinating for their synchronisation. WRLDC will
coordinate interstate/ inter-regional startup power availability
and also inter-state/inter-regionql synchronisation of the
system.
2. Minimum 25 MW power flow from West toNorth will be maintained on HVDC back to back link at
Vindhyachal during normal operating condition.
3. Black start generation usage priorities:-
a) provide startup power to hot units
b) provide startup power to units that are cool; but capableof rapid restart
c) restore stations auxiliary service to generating
stations0and sub-stations.
d) Pick up essential loads.
4. Transmission corridors used for startup power
should be isolated from any damaged/faulty equipment and
are of minimum length and minimum voltage level to reduce
line charging.
5. The constituent receiving assistance during
restoration process should restrict to the agreed quantum only
since this may have an adverse effect on healthysystem0rendering the assistance.
-
8/11/2019 p Pentayya Bs
5/26
5
GENERAL GUIDELINES
While each disturbance would be different and may require a different plan,
nevertheless it would be useful to formulate general guidelines for the benefit
of the load despatchers. These may be described as0below:
i. The operators at generating stations and substations should have the
knowledge of pre-planned synchronising locations and synchronising
procedures. Synchronising should be done preferably at generating stations.
ii. Switching procedures should be clearly laid down and periodicallyreviewed.
iii. The part systems should be reintegrated only after adequate
stabilization.
iv. The transformer taps should be checked for desired settings to
minimise voltage difference.
v. The substation operators and load despatchers sxould make a check of
the capacitor banks and reactors in service and accordingly to carry out the
switching operations for voltage control.vi. Energising long high voltage lines and cables should be avoided until
enough generating capacity is available.
vii. Provision of islanding schemes area-wise, power station-wise and unit-
wise would enhance the ability to restore faster. These should be fully
exploited.
viii. Some of the generating units might have been saved due to successful
islanding. Stabilization of such online generation is of top most priority.
ix. Provision of start up power to nuclear plants should be given priority aspoisoning of the reactors would delay restoration of nuclear units.
x. In case of failure of main communication channels, guidelines for
decision making should be given to all the major substations and generating
stations.
xi. Devising islands for power stations wherever small units could help in
faster restoration of the grid are available. One small unit at these power
stations can be islanded with radial loads and/or house load.
-
8/11/2019 p Pentayya Bs
6/26
6
REQUIREMENT OF SURVIVAL POWER /AUXILIARY POWER
Survival power can be defined as the powerneeded for avoiding the damage to the equipmentin case of supply failure. This power is requiredfor
Turbine emergency oil pump Jacking oil pumps Barring gear of the turbines Lubricating oil pumps Compressors for ABCB operation Emergency lighting Battery chargers of units, station, and
communication and telemetry system
The survival power required by 120 MW units isof the order of 250-350 kW while the requirementof 210 MW units is of the order of 350-500 KW.As a general rule, the survival power requirementwould be around 0.25-0.30% of the unit capacity.Nuclear power plants should be supplied withsurvival power on priority basis.
-
8/11/2019 p Pentayya Bs
7/26
7
REQUIREMENT OF START UP POWER
The start-up power is the power required for the
auxiliaries while the generating unit is restored. Therequirement of start-up power by various units is asfollows:-
Nuclear & : 7 to 8% of the unit capacityThermal
Hydro : 0.5 to 1% of the unitcapacity
Gas : 1.5 to 2% of the unitcapacity.
-
8/11/2019 p Pentayya Bs
8/26
8
Ukai (H) 4 x 75 Hydro Diesel 500 KVA One 75 MW
gen. house set
Mini Hydro 2 x 2.5 Hydro Diesel 50 KW
Kadana 4 x 60 Hydro Diesel 500 KVA
Dhuvaran 1 x 27
+ 4 x 63.5
+ 2 x 140
Gas
Thermal
Any one
unit out of
the units
1,2,3 & 4
1 x 63.5
MW
Islanding of
any one units
out of units 1,
2, 3, & 4 on to
house load
Diesel 1600 KVA
x2
700 KVA
GIPCL 3 x 32
+ 1 x45
+ 1x104
+ 1x5
Gas
Steam
Gas
Steam
All units
Diesel
141 MW
500 KVA
Islanding of
all units
A.E.Co.
Stn. C
Stn. D,E,F
4 x 15
2 x 30
3 x 110
Thermal
Thermal
Thermal
Stn-C
islands
Diesel
30 MW
500 KVA
Islanding of
0ne 30 MW
unit
GPEC 3x 138 Thermal Diesel 3000 KVA
Kawas 4 x 106
2 x 116
Gas Diesel 2700 KW
Gandhar 3 x 144
+ 1x225
Gas Diesel 3120 KW
CCPP, Vatwa 3 x 39+ 1 x 45
Gas
Essar
-
8/11/2019 p Pentayya Bs
9/26
9
wer Station Installed
Cap. (MW)
Survival
power
Auxiliary
Power
Diesel
Capacity
Synch. Facl.
B
ai (Hy) 4 x 75 100 KW 250 KW 500 KVA Yes
ai LBCH 2 x 2.5 5 KW 20 KW 50 KW Yes
dana (Hy) 4 x 60 7 KW 200 / 250 KW 500 KVA Yes
ai (Th) 2 x 120
+ 1 x 200
+ 2 x 210
1.447
MW
4.5/ 8 MW - Yes
ka (Th) 2 x 120 500 KW 12 MW 500 KW Yes
uvaran (Th) 1 x 27
+ 4x63.5
+ 2x140
500 KW 5 MW 500 KW Yes
ndhinagar 2 x 120+ 3 x 210
175/350KW P.U
7.2/10.7 MWP.U
500 KVAD.G.set
under
erection
Yes
nakbori 7 x 210 0.8 MW 13 MW P.U 3x400
KW
Yes
nandro 2 x70+1x75 360 KW 4.5 MW 1280 KW
& 500KW
Yes
E.Co
Stn. C 2 x 30 250 KVA 9 MW 1x500
KVA
Yes
D,E,F, + 3x110 2 x 125
KVA
+ 3x33
s 3 x 32 Nil 350 KVA 1x500
KVA
Yes
-
8/11/2019 p Pentayya Bs
10/26
10
1. REACTIVE POWER BALANCE
Objective
To keep system voltage within allowable range
Strategies
Energising fewer high voltage lines Operating generators at minimum voltagelevels (logging p.f) Deactivate switchable capacity Connect shunt reactors and tertiary reactors
Adjustment of transformer taps Pick up loads with lagging p.f Charge more transformers Charge shorter lines Operating synchronous condensers / SVCswhere available Avoid charging lines with series capacitors
Concerns
Self excitation of generators and run away
voltage rise.
-
8/11/2019 p Pentayya Bs
11/26
11
2 LOAD AND GENERATION BALANCE
Objective
To maintain system frequency within allowablelimits
Strategies
Restore loads in small increments (minimum &
essential) Smaller and radial loads to be restored prior tolarger and network loads Feeders with U/F relays are restored later (bypassuntil frequency stabilizes) Load restoration based on load characteristics
To get adequate inductive loading to compensatecapacitive effect while charging high voltage long line,a concentrated load of large town/city should bereleased along with that of Railways. Maintain frequency close to 50 Hz paying specialattention to traction and other fluctuating loads
Concerns
Size of load pick up depends upon the rate ofresponse of prime movers Load pick up in large increments led to collapse ofthe restored systemsTwice in Gujarat on 9.12.95Twice in Maharashtra on 9.12.95Once in MP on 9.12.95
-
8/11/2019 p Pentayya Bs
12/26
12
3 LOAD AND GENERATION CO-
ORDINATION PRIORITIES
Restart Stage
Priority to restore power supply to generatingstations and load dispatch centers. Priority to supply start up power to hydro andgas units Priority for providing backup/survival/startup
power to nuclear power stations Several load and generation islands formed Black starting of small hydro or gas units In each island, the objective is to supplystation auxiliary power and start up power The number of islands limited by sources of
black start units Each island should preferably be monitored
by one load despatcher till reintegration.
Re-integration stage
Load restoration stagevIn small stepsvObserve frequency charges (< 0.5 Hz) with loadadditionvPreferable to restore rotating type loads if
possiblevCold load pick up is the main concern
-
8/11/2019 p Pentayya Bs
13/26
13
4 MONITORING & CONTROL
Location of the fault and extent ofcollapse of the system should beascertained before restoration
It is dangerous to restore a faulty lineor faulty equipment
Ensure communication links between
control centers, power plants and sub-stations
SCADA system performanceInadequate displaysExcessive alarms
Protection tele-meteringEMS
-
8/11/2019 p Pentayya Bs
14/26
14
5 Communications
Establishing communication
between LDCs, Generating Stations
and major substations.
All important substations only to be
kept in touch with and links with
unimportant substations to0be cut off
to avoid draining of batteries. All communication channels
required for restoration process shall
be used for operatyonal
communication only till grid normalcy
is restored (IEGC 6.8.e)
-
8/11/2019 p Pentayya Bs
15/26
15
6 PROTECTIVE SYSTEMS /
SYNCHRONISATION
Check all interlocks
Sort out problems in closing of breakers dueto low gas/air pressure Avoid paralleling islands through weak ties. Synchronizing facilities at sub-stations Standing phase angles to be checked anddifference reduced by generation control.Synchronisation only through synchro-checkrelays Try to synchronise islands or part systems,
near the generating stations requires less co-ordination and easier to control Operate generators on lagging p.f Generators supplying start up power shouldnot be loaded beyond 80% The capacity of the island to sustain the
starting current of BFPs should be checked If sub-systems are to be synchronized awayfrom generating stations, be extremely cautiousof standing phase angle differences (systemoccurrence on 28.4.93 in Maharashtra)
-
8/11/2019 p Pentayya Bs
16/26
16
7 ENERGY STORAGE
Loss of back up power supplies like:
BatteriesBattery chargersUPSDiesel sets
Could affect
Operation of circuit breakers Motor operated isolators Communication SCADA
(one of the important causes of delays inrestoration)
-
8/11/2019 p Pentayya Bs
17/26
17
8 SWITCHING OVER VOLTAGES
Energise small sections of lines Energise lower voltage lines In case of parallel circuits, energise one ckt. Control high voltages during restoration to
avoid damage of Las/CVTs et.
9 Survival Power
Ensuring availability of back up power supplies such
as batteries, battery chargers, D.G sets to avoid effect
on non operation of circuit breakers, communication
systems etc., which can cause delay in restoration.
10 Awareness of Restoration Plans
Training and necessary documentation may be
provided to Load Despatchers by respective LDCs.
11 Exchange of Information
Exchange of information among SLDCs and between
RLDC and SLDCs is essential for proper co-
ordination.
-
8/11/2019 p Pentayya Bs
18/26
18
12 SYSTEM STUDIES FOR MAKINGRESTORATION PLANS
1 Power flow
Multiple islands Study voltage problems
Generator excitation limits Transformer taps
2 Dynamic stability
To study load generation co-ordination While load pick up, generation responsecould be studied
3 EMTP
To determine what lines to be charged Transient over voltages in switching
-
8/11/2019 p Pentayya Bs
19/26
19
13. RESTORATION PLAN
v Identification of collapsed powersystem components and equipment.
v Restart and supply start up power firstto hydro and gas stations
v Startup power to thermal stations,auxiliary power to sub-stations
v Co-ordination of power plant start upwith load pick up to bring generators totheir stable minimum generation levels
v Restore in sub-systems if multiple
sources of startup power available
v Energising transmission lines withacceptable transient and sustained overvoltages
v While load pick up, check frequencydecline
v Reintegration of sub-systems
v Ensure discipline and avoid overdrawals until proper stabilization
-
8/11/2019 p Pentayya Bs
20/26
20
14. ROLE OF LOAD DESPATCH CENTRES
v Determine severity of collapse
v Identify and initiate black start facilitiesv Import start up power from
neighbouring states or regionsv Import more power to meet essential
loads from neighbouring states or regionsv Decision making and guidancev Determine priority loadsv
Check unbalanced loading due to tractionv Getting start up power from captivepower plants, if possible
v Ensure communication links, SCADAfacilities
v Guidance to sub-station/generating
station operators from the results of EMSv Identify points of reintegration and
synchronizationv Reporting
-
8/11/2019 p Pentayya Bs
21/26
21
15. TRAINING AND ROUTINE EXERCISES
v Short time appreciation courses
v Review of targets for restoration as
soon as a black start facility or inter-state /inter-regional connection is stabilized.
v Review of restoration plants after everyoccurrence
v Updating of restoration manually andother documentation
v The strategies of restoration should havealternatives to enable flexibility
v Training by experts
v Interactive training and case studies
v All constituents should participate intraining programmes
v Formation of a command group
v Mock exercises
v Preparation of manuals on importanttelephone numbers etc.
-
8/11/2019 p Pentayya Bs
22/26
22
16. OVER VOLTAGE CONTROL DURING
RESTORATION
(A) Sustained power frequency overvoltages
v Due to lightly loaded linesv May cause under excitation ofgeneratorsv May lead to self excitation ofgeneratorsv Over fluxing of transformers
(generate harmonic distortions and causetransformer over heating)
(B) Transient voltage or switching surges
v caused by energisation and de-
energisation of linesorv switching of capacitive elementsv In conjunction with sustained o/v maycause arrestor failures
-
8/11/2019 p Pentayya Bs
23/26
23
Harmonic Resonance Voltages
v Oscillatory un damped or weaklydampedv
Of long durationv Originate from equipment nonlinearities and switching natural frequency ofseries resonance circuit formed by sourceinductance and line charging capacitance.v Magnetizing in rush due to transformer
energisationv Lightly damped due to light loading oflinesv Over fluxing of transformers (beyond1.1 pu)
2. Equipment limitations
Transformers and Arrestors
1.2 p.u for one minute
1.4 p.u for 10 seconds
Circuit breakers
v Will have reduced interruptingcapability
v Can interrupt line charging currentsupto 1.2 p.u
-
8/11/2019 p Pentayya Bs
24/26
24
3. Control of sustained over voltages
v Sufficient under excitationcapability on the generators
v Connect lagging p.f loads andshunt reactors
v Remove all sources of reactivepower and switch off capacitor banks
v Run generators at maximumpossible reactive power output to allow
margin to adjust for large chargingreactive power during line switching
v Tap staggering of transformers
v Avoid extra parallel lines
v Maintain low voltage profile onthe lines to reduce line charging
-
8/11/2019 p Pentayya Bs
25/26
25
4. Control of switching transients
v Switching o/v may cause flash over anddamage to equipment
v Switching transients on fast transient causedby ill timed closure of breakers
v To be controlled to 2.5 p.u for 400kV and 1.9p.u for 800kV and 2.3 p.u for others
v Usually of fast front, low energy or slow front,high energy transients.
v Keep steady state voltage below 1.2 p.u. Keep
generator terminal voltage around 0.8 p.u
-
8/11/2019 p Pentayya Bs
26/26
26
5. Harmonic Resonance
vTransformers may get over excited and
generate harmonicsvCombination of system inductance and linecapacitance forms a series resonance circuit whichis excited by harmonic distortions produced bytransformer saturationv
Harmonics generated by magnetic current inrush can also lead to harmonic resonancevSufficient load to be connected to theunderlying system at both ends to damposcillationsvLower order resonances produce higher over
voltages(3rd, 4th, 5th, 6thharmonics)vTo control over voltage due to transformer overexcitation, user lower taps (system studies)vHarmonic resonance can be damped byconnecting loads at both endsvConnect dead load on the transformer to beenergizedvReduce number of highly loaded lines (inparallel paths)