Persoana juridica achizitoare FORMULARUL F3SC. JAD GROUP SRL
Obiectivul : 67 INFIINTARE STRUCTURA DE SPRIJINIRE A AFACERILORObiectul : 2 LUCRARI DE CONSTRUCTII SI INSTALATII
Lista cu cantitati de lucrariPreturile sunt exprimate in LEICapitol de Lucrari U/M Cantitate Pret unitar M m u t TSimbol a)material Materiale Manopera Utilaj Transport TotalDenumire Resursa b)manopera (3x4a) (3x4b) (3x4c) (3x4d) (5+6+7+8)Liste Anexe c)utilajObservatii d)transport
SECTIUNEA TEHNICA SECTIUNEA FINANCIARA0 1 2 3 4 5 6 7 8 91 IZF18A1 82 MP 175.00 7.00 1225.00
2.00 350.003.00 525.004.00 700.00 2800.00
2 IZF18A1 82 MP 175.00 7.00 1225.002.00 350.003.00 525.004.00 700.00 2800.00
3 IZF18A1 82 MP 175.00 7.00 1225.002.00 350.003.00 525.004.00 700.00 2800.00
4 IZF18A1 82 MP 175.00 7.00 1225.002.00 350.003.00 525.004.00 700.00 2800.00
5 IZF18A1 82 MP 200.00 1.00 200.002.00 400.003.00 600.004.00 800.00 2000.00
6 IZF18A1 82 MP 200.00 100.00 20000.002.00 400.003.00 600.004.00 800.00 21800.00
7 IZF18A1 82 MP 50.00 1.00 50.002.00 100.003.00 150.004.00 200.00 500.00
Cheltuieli directe 25150.00 2300.00 3450.00 4600.00 35500.00M m U t T
CAS 478.40SOMAJ 11.50
SANATATE 119.60CONCEDII MEDICALE + INDEMNIZATII 19.55
FOND GARANTARE SALARII 5.75FOND DE RISC 6.417
TOTAL CHELTUIELI DIRECTE Mo mo Uo to To25150.00 2941.22 3450.00 4600.00 36141.22
Cheltuieli indirecte Io = To x % 3614.12
Nr. Crt.
STRAT EGALIZARE CU MORTAR CIMENT M100-T PE SUPRAF. ELEMENTE PREFABR. INGROSIME 0,5CM
STRAT EGALIZARE CU MORTAR CIMENT M100-T PE SUPRAF. ELEMENTE PREFABR. INGROSIME 0,5CM
STRAT EGALIZARE CU MORTAR CIMENT M100-T PE SUPRAF. ELEMENTE PREFABR. INGROSIME 0,5CM
STRAT EGALIZARE CU MORTAR CIMENT M100-T PE SUPRAF. ELEMENTE PREFABR. INGROSIME 0,5CM
STRAT EGALIZARE CU MORTAR CIMENT M100-T PE SUPRAF. ELEMENTE PREFABR.INGROSIME 0,5CM
STRAT EGALIZARE CU MORTAR CIMENT M100-T PE SUPRAF. ELEMENTE PREFABR.INGROSIME 0,5CM
STRAT EGALIZARE CU MORTAR CIMENT M100-T PE SUPRAF. ELEMENTE PREFABR.INGROSIME 0,5CM
Capitol de Lucrari U/M Cantitate Pret unitar M m u t TSimbol a)material Materiale Manopera Utilaj Transport TotalDenumire Resursa b)manopera (3x4a) (3x4b) (3x4c) (3x4d) (5+6+7+8)Liste Anexe c)utilajObservatii d)transport
Nr. Crt.
Profit Po = (To + Io) x % 3614.12TOTAL GENERAL Vo = To + Io + Po 43369.46
PROIECTANT CONTRACTANT (OFERTANT)SC PROIECT BUCOVINA SA