Lista cu cantitatile de lucrari

Deviz oferta B11118 ANALIZA PREŢ BOLOVANI DE RAU, PIATRĂ BRUTĂ

Categoria de lucrari: 0120

Preturile sunt exprimate in RON

Simbol Cantitatea UM VALOARE

Manopera Utilaj Transport GENERAL

0 1 2 3 4 5 6 7 8 9 10 11 12 13

001 ASA01A01 ADUNAT,SPART,SORTAT BOLOVANI DE RAU 1.000 M.C. 0.00 6.94 0.00 0.00 0.00 6.94 0.00 0.00 6.94

002 YC01 TAXĂ EXPLOATARE MATERIAL DIN ALBIE 1.000 M.C. 5.92 0.00 0.00 0.00 5.92 0.00 0.00 0.00 5.92

Cheltuieli directe din articole: MATERIALE 5.92 MANOPERA 6.94 UTILAJ 0.00 TRANSPORT 0.00 TOTAL 12.86

Detaliere transporturi:-Articole TRA 0.0000

Alte cheltuieli directe:-CAS: 0.2080 1.4431-SOMAJ: 0.0050 0.0347FOND CONCEDII MEDICALE 0.0085 0.0590SANATATE 0.0520 0.3608

0.0031 0.0212

GARANTARE SALARII 0.0025 0.0173

Total cheltuieli directe: MATERIALE 5.92 MANOPERA 8.87 UTILAJ 0.00 TRANSPORT 0.00 TOTAL 14.79

Cheltuieli indirecte: 0.05 0.7397Profit: 0.03 0.4660TOTAL GENERAL DEVIZ: 16.0000

Nr.crt.

Capitol de lucr. sau

P.U.(lei / U.M.) TOTAL

Subcapitol (norma comasata)Denumire

Material Material(col. 3 x col. 5)

Manopera(col. 3 x col. 6)

Utilaj(col. 3 x col. 7)

Transport(col. 3 x col. 8)

CONTRIBUTIA PENTRU ACCIDENTE DE MUNCA SI BOLI PROFESIONALE