R.0. demolare beton Armat (Reinforced Concrete demolition)
1 Demolare beton armat in fundatii - foundations reinforced concrete demolition
Fundatii / Foundations 55.00 m3
TOTAL 55.00 m3
2 Demolare beton armat in pereti - walls reinforced concrete demolition
Subsol2/Basement2 15.00 m3
Subsol1/Basement1 5.00 m3
Parter/G.F. 220.00 m3
Etaj1/1stFL 220.00 m3
TOTAL 460.00 m3
3 demolare beton armat in plansee si scari - slabs and stairs reinforced concrete demolition
Subsol2/Basement2 5.00 m3
Subsol1/Basement1 5.00 m3
Parter/G.F. 140.00 m3
Etaj1/1stFL 140.00 m3
TOTAL 290.00 m3
1 Demolare beton armat in fundatii - foundations reinforced concrete demolition
Fundatii / Foundations 0.00 m3
TOTAL 0.00 m3
2 Demolare beton armat in stalpi/pereti - column/walls reinforced concrete demolition
Subsol1/Basement1 3.00 m3
Parter/G.F. 30.00 m3
TOTAL 33.00 m3
3 demolare beton armat in plansee si scari - slabs and stairs reinforced concrete demolition
CORP SECUNDAR EXISTENT - EXISTING SECONDARY STRUCTURE
CORP DE PARCAJE EXISTENT - EXISTING PARKING
ANTEMASURATOARE/B.O.Q. LUCRARIDEDEMOLARE/DEMOLITIONWORKS
-
CLDIREDEBIROURIOFFICEBUILDINGBd.Pandurilor4446,TrguMure
FAZAPHASED.L.(BID)
Subsol1/Basement1 5.00 m3
Parter/G.F. 60.00 m3
TOTAL 65.00 m3
ANTEMASURATOARE/B.O.Q. LUCRARIDEDEMOLARE/DEMOLITIONWORKS
-
CLDIREDEBIROURIOFFICEBUILDINGBd.Pandurilor4446,TrguMure
FAZA/PHASE D.L.(BID)
RefDescriere
(Item Description)
Nivel Level Cantitate
QuantityUnitate
UnitPret Rate
TOTAL (EUR)
Excavatiiexcavations Fundatii / Foundations12350.00 m3
Umpluturicompactatemanualearthfill Fundatii / Foundations2150.00 m3
Foraj piloti 600- piles drilling 600/ boreholes length
Fundatii / Foundations
965.00 mBeton contaminat de spart din capetele pilotilor - contaminated concrete to be chopped off from the piles heads
Fundatii / Foundations
19.00 m3
PARAPETI EXTERIORI+SCARI EXTERIOARE/OUTDOOR PARAPETS+OUTDOOR STAIRS
Excavatiiexcavations Fundatii / Foundations685.00 m3
Umpluturicompactatemanualearthfill Fundatii / Foundations535.00 m3
R.1. Lucrari de terasamente, excavatii si perete de sprijin - Ground works, excavation and retaining wallCORP PRINCIPAL+CORP SECUNDAR+REZERVOR- MAIN STRUCTURE+SECONDARY STRUCTURE+WATER TANK
ANTEMASURATOARE/B.O.Q.TERASAMENTE,EXCAVATII,SPRIJINIRI/
GROUNDWORKS,EXCAVATION,RETAININGWALLS
-
CLDIREDEBIROURIOFFICEBUILDINGBd.Pandurilor4446,TrguMure
FAZA/PHASED.L.(BID)
Ref Descriere (Item Description)
Nivel Level Cantitate Quantity
Unitate Unit
Pret Rate
TOTAL (EUR)
R.2. Beton Armat (Reinforced Concrete)
1 Beton nearmat la fundatii - foundations unreinforced concreteBeton de egalizare C8/10, X0 - Leveling concrete Fundatii /
Foundations 225.00 m3
Beton nearmat racordare fundatii C12/15,X0 - Unreinforced concrete for fundation connection
Fundatii / Foundations 410.00 m3
TOTAL 635.00 m3
2 Beton armat in fundatii - foundations reinforced concreteBeton piloti C20/25, XC2 - Piles concrete Fundatii /
Foundations 310.00 m3
Beton grinda de coronament - C20/25, XC2 - Piles head beam
Fundatii / Foundations 55.00 m3
Beton radier C25/30,(XC2)XC4 - slab foundation concrete
Fundatii / Foundations 2753.00 m3
TOTAL 3118.00 m3
3Beton armat in pereti si bulbi, inclusiv grinzi de
cuplare locale - walls reinforced concrete (including local coupling beams)
C30/37XC4+XF1inperetiiperimetralifortheperimeterwalls
Subsol/Basement 155.00 m3
C30/37XC1 Subsol/Basement 369.00 m3
C40/50XC1 Subsol/Basement 16.00 m3
C30/37 - XC1 Parter/G.F. 220.00 m3C30/37 - XC1 Etaj1/1stFL 196.00 m3C30/37 - XC1 Etaj2/2ndFL 196.00 m3C30/37 - XC1 Etaj3/3rdFL 196.00 m3C30/37 - XC1 Etaj4/4thFL 196.00 m3C30/37 - XC1 Etaj5/5thFL 196.00 m3C30/37 - XC1 Etaj6/6thFL 196.00 m3C30/37 - XC1 Etaj7/7thFL 196.00 m3C30/37 - XC1 Etaj8/8thFL 196.00 m3C30/37 - XC1 Etaj
tehnic/Mech FL150.00 m3
TOTAL 2478.00 m3
4 BetonarmatinstalpicolumnsreinforcedconcreteC30/37 - XC1 Subsol/
Basement 5.00 m3C40/50 - XC4+XF1 Parter/G.F. 62.00 m3
C40/50 - XC1 Etaj1/1stFL 44.00 m3C40/50 - XC1 Etaj2/2ndFL 44.00 m3
C30/37 - XC1 Etaj3/3rdFL 44.00 m3C30/37 - XC1 Etaj4/4thFL 44.00 m3C30/37 - XC1 Etaj5/5thFL 44.00 m3
CORP PRINCIPAL - MAIN STRUCTURE
ANTEMASURATOARE/B.O.Q. BETON/CONCRETE
-
CLDIREDEBIROURIOFFICEBUILDINGBd.Pandurilor4446,TrguMure
FAZA/PHASED.L.(BID)
C30/37 - XC1 Etaj6/6thFL 44.00 m3C30/37 - XC1 Etaj7/7thFL 44.00 m3C30/37 - XC1 Etaj8/8thFL 44.00 m3C30/37 - XC1 Etaj
tehnic/Mech FL0.00
m3
TOTAL 419.00 m3
5 Beton armat in plansee - slabs reinforced concrete
C30/37 - XC4+XF3 Subsol/Basement 576.00 m
3
C30/37 - XC1 Parter/G.F. 475.00 m3C30/37 - XC1 Etaj1/1stFL 362.00 m3C30/37 - XC1 Etaj2/2ndFL 362.00 m3C30/37 - XC1 Etaj3/3rdFL 367.00 m3C30/37 - XC1 Etaj4/4thFL 367.00 m3C30/37 - XC1 Etaj5/5thFL 367.00 m3C30/37 - XC1 Etaj6/6thFL 395.00 m3C30/37 - XC1 Etaj7/7thFL 395.00 m3
C30/37 - XC4+XF3 Etaj8/8thFL 395.00 m3C30/37 - XC4+XF3 Etaj
tehnic/Mech FL35.00 m3
TOTAL 4096.00 m3
6 Beton armat in scari si rampe - slabs ans ramps reinforced concrete
C20/25 - XC1 Subsol/Basement 6.00 m
3
C20/25 - XC1 Parter/G.F. 7.00 m3C20/25 - XC1 Etaj1/1stFL 6.00 m3C20/25 - XC1 Etaj2/2ndFL 6.00 m3C20/25 - XC1 Etaj3/3rdFL 6.00 m3C20/25 - XC1 Etaj4/4thFL 6.00 m3C20/25 - XC1 Etaj5/5thFL 6.00 m3C20/25 - XC1 Etaj6/6thFL 6.00 m3C20/25 - XC1 Etaj7/7thFL 6.00 m3C20/25 - XC1 Etaj8/8thFL 3.00 m3C20/25 - XC1 Etaj
tehnic/Mech FL0.00 m3
TOTAL 58.00 m3
1 Beton simplu la fundatii - foundations unreinforced concreteBeton de egalizare C8/10, X0 - Leveling concrete Fundatii /
Foundations 3.00 m3
Beton simplu racordare fundatii C12/15,X0 - Unreinforced concrete for fundation connection
Fundatii / Foundations 35.00 m3
TOTAL 38.00 m3
2 Beton armat in fundatii - foundations reinforced concrete
CORP SECUNDAR - SECONDARY STRUCTURE
ANTEMASURATOARE/B.O.Q. BETON/CONCRETE
-
CLDIREDEBIROURIOFFICEBUILDINGBd.Pandurilor4446,TrguMure
FAZA/PHASED.L.(BID)
Beton C20/25, XC2 - Continuous footings Fundatii / Foundations 46.00 m
3
TOTAL 46.00 m3
3 Beton armat in stalpi- columns reinforced concrete
C25/30-XC1(85%)C25/30-XC4.XF1(15%) Subsol-1 3.00 m3
C25/30-XC1 Subsol-2 3.00 m3
C25/30-XC1 Parter 55.00 m3
C25/30-XC1 Etaj 1 55.00 m3
C25/30-XC1 Etaj 2 65.00 m3
TOTAL 181.00 m3
4 Beton armat in plansee grinzi si scari - slabs, beams and stairs reinforced concrete
C25/30-XC2 Subsol2/Basement2 3.00 m3
C30/37-XC4.XF3 Subsol1/Basement1 12.00 m3
C25/30-XC4(85%)C30/37-XC4.XF3(15%) Parter/G.F. 150.00 m3C25/30-XC1 Etaj1/1stFL 140.00 m3C25/30-XC1 Etaj2/2ndFL 130.00 m3
TOTAL 435.00 m3
1 Beton armat in stalpi- columns reinforced concrete
C25/30-XF1,XC4 Subsol1/Basement1 3.00 m3
C25/30-XF1,XC4 Parter/G.F. 22.00 m3C25/30-XF1,XC4 Etaj1/1stFL 39.00 m3
TOTAL 64.00 m3
2 Beton armat in plansee grinzi si scari - slabs, beams and stairs reinforced concrete
C30/37-XF3,XC4 Subsol1/Basement1 3.00 m3
C30/37-XF3,XC4 Parter/G.F. 77.00 m3C30/37-XF3,XC4 Etaj1/1stFL 78.00 m3
TOTAL 158.00 m3
1 Beton armat in pereti- walls reinforced concreteC30/37-XF1,(XC2)XC4,XD2-ciment hidrotehnic 82.00 m3
TOTAL 82.00 m3
2 Beton armat in radier+planseu - foundation slab,floor slab,
beton de egalizare/levelingconcrete -C8/10-X0 15.00 m3C30/37-XF3,(XC2)XC4,XD2-ciment hidrotehnic 105.00 m3
TOTAL 120.00 m3
PARAPETI EXTERIORI+SCARI EXTERIOARE/OUTDOOR PARAPETS+OUTDOOR STAIRS
1Beton armat in pereti exteriori(beton spalat cu agregate vizibile) - outdoor walls reinforced concrete(washed concrete with visible aggregates)
C25/30-XF1,(XC2)XC4 123.00 m3
TOTAL 123.00 m3
2 Beton armat in fundatii - foundations
REZERVOR APA - WATER TANK
CORP PARCAJE - PARKING CORP
ANTEMASURATOARE/B.O.Q. BETON/CONCRETE
-
CLDIREDEBIROURIOFFICEBUILDINGBd.Pandurilor4446,TrguMure
FAZA/PHASED.L.(BID)
beton de egalizare/levelingconcrete -C8/10-X0 15.50 m3C20/25-XC2 113.00 m3
TOTAL 128.50 m3
3Beton armat in plansee exterioare, trepte(dalele de parcare nu fac obiectul masuratorii) - outdoor slabs and outdoor stairs(parking slabs are not includet)
C30/37-XF3,(XC2)XC4 34.00 m3TOTAL 34.00 m3
ANTEMASURATOARE/B.O.Q. BETON/CONCRETE
-
CLDIRE DE BIROURI OFFICE BUILDINGBd.Pandurilor4446,TrguMure
FAZAPHASED.L.(BID)
RefDescriere
(Item Description)
Nivel Level Cantitate Quantity
Unitate
Unit
Pret Rate
TOTAL (EUR)
1 Cofraj la fundatii - foundations concrete formwork
Cofraj grinda de coronament - Piles head beam formwork
Fundatii / Foundations 150.00 m2
Cofraj lateral radier - slab fundation lateral formwork
Fundatii / Foundations 269.00 m2
TOTAL 419.00 m2
2 Cofraj lateral pereti/stalpi - walls/columns formwork(97%pereti si 3%stalpi/97%walls and 3%columns) Subsol/ 2540.00 m2
(78%pereti si 22%stalpi/78%walls and Parter/G.F. 1550.00 m2(80%pereti si 20%stalpi/80%walls and Etaj1/1stFL 1280.00 m2(80%pereti si 20%stalpi/80%walls and Etaj2/2ndFL 1280.00 m2(80%pereti si 20%stalpi/80%walls and Etaj3/3rdFL 1280.00 m2(80%pereti si 20%stalpi/80%walls and Etaj4/4thFL 1280.00 m2(80%pereti si 20%stalpi/80%walls and Etaj5/5thFL 1280.00 m2(80%pereti si 20%stalpi/80%walls and Etaj6/6thFL 1280.00 m2(80%pereti si 20%stalpi/80%walls and Etaj7/7thFL 1280.00 m2(80%pereti si 20%stalpi/80%walls and Etaj8/8thFL 1280.00 m2
(100%pereti/100%walls)Etaj tehnic/Mech FL 887.00 m2
TOTAL 15217.00 m2
3 Cofraj plansee si scari - slabs and stairs formwork
Subsol/Basement 1870.00 m
2
Parter/G.F. 1780.00 m2Etaj1/1stFL 1345.00 m2Etaj2/2ndFL
1345.00 m2
Etaj3/3rdFL 1363.00 m2Etaj4/4thFL 1363.00 m2Etaj5/5thFL 1363.00 m2Etaj6/6thFL 1380.00 m2Etaj7/7thFL 1380.00 m2Etaj8/8thFL 1394.00 m2Etaj tehnic/Mech FL
180.00 m2
TOTAL 14763.00 m2
1 Cofraje Beton armat in fundatii - foundations formworksCofraje Beton - Continuous footings formworks Fundatii /
Foundations 200.00 m2
TOTAL 200.00 m2
2 Cofraje Beton armat in stalpi- columns formworks
R.3. Cofraje - FormworksCORP PRINCIPAL - MAIN STRUCTURE
CORP SECUNDAR - SECONDARY STRUCTURE
ANTEMASURATOARE/B.O.Q. COFRAJ/FORMWORK
-
CLDIRE DE BIROURI OFFICE BUILDINGBd.Pandurilor4446,TrguMure
FAZAPHASED.L.(BID)
Subsol2/Basement2 15.00 m2Subsol1/Basement1 15.00 m2Parter/G.F. 330.00 m2Etaj1/1stFL 330.00 m2Etaj2/2ndFL
390.00 m2
TOTAL 1080.00 m2
3 Cofraje Beton armat in placi si grinzi - slabs and beams formworks
(100%placi/100%slabs) Subsol2/Basement2 15.00 m2
(100%placi/100%slabs) Subsol1/Basement1 15.00 m2
(40%grinzi si 60%placi/40%beams and 60%slabs) Parter/G.F. 870.00 m2(45%grinzi si 55%placi/45%beams and 55%slabs) Etaj1/1stFL 800.00 m2
(45%grinzi si 55%placi/45%beams and 55%slabs)Etaj2/2ndFL
770.00 m2
TOTAL 2470.00 m2
1 Cofraje Beton armat in stalpi- columns formworks
Subsol1/Basement1 15.00 m2Parter/G.F. 95.00 m2Etaj1/1stFL 350.00 m2
TOTAL 460.00 m2
2 Cofraje Beton armat in placi grinzi si scari - slabs, beams and stairs formworks
(100%placi/100%slabs) Subsol1/Basement1 15.00 m2
(45%grinzi si 55%placi/45%beams and 55%slabs) Parter/G.F. 350.00 m2(40%grinzi si 60%placi/40%beams and 60%slabs) Etaj1/1stFL 410.00 m2
TOTAL 775.00 m2
1 Cofraje in pereti- walls reinforced concrete formworks
540.00 m2
TOTAL 540.00 m2
2 Cofraje in radier+planseu - foundation slab and floor slab formworks
(20%radier si 80%placa/20%foundation slab and 80%slab)
175.00 m2
TOTAL 175.00 m2
PARAPETI EXTERIORI+SCARI EXTERIOARE/OUTDOOR PARAPETS+OUTDOOR STAIRS
1 Cofraje in pereti exteriori - outdoor walls reinforced concrete formworks
795.00 m2
REZERVOR APA - WATER TANK
CORP PARCAJE - PARKING CORP
ANTEMASURATOARE/B.O.Q. COFRAJ/FORMWORK
-
CLDIRE DE BIROURI OFFICE BUILDINGBd.Pandurilor4446,TrguMure
FAZAPHASED.L.(BID)
TOTAL 795.00 m2
2 Cofraje in fundatii - foundations formworks
25.00 m2TOTAL 25.00 m2
3
Cofraje in plansee exterioare, trepte(dalele de parcare nu fac obiectul masuratorii) - outdoor slabs and outdoor stairs formworks(parking slabs are not includet) 70.00 m2TOTAL 70.00 m2
ANTEMASURATOARE/B.O.Q. COFRAJ/FORMWORK
-
CLDIREDEBIROURIOFFICEBUILDINGBd.Pandurilor4446,TrguMure
FAZAPHASED.L.(BID)
Ref Descriere (Item Description)
Nivel Level Cantitate Quantity
Unitate Unit
Pret Rate
TOTAL (EUR)
1 Armatura in fundatii - foundations concrete reinforcementArmatura piloti - Piles concrete reinforcement Fundatii /
Foundations 42000.00 kgBst500s
Armatura grinda de coronament - Reinforcement for piles head beam
Fundatii / Foundations 5500.00 kg
Bst500s
Armatura radier - slab fundation concrete reinforcement
Fundatii / Foundations 355000.00 kg
Bst500s
TOTAL 402500.00 kg
2 Armatura in pereti/stalpi - walls/columns reinforcement
Bst500s Subsol/Basement
87000.00 kg
Bst500s Parter/G.F. 42000.00 kgBst500s Etaj1/1stFL 35000.00 kgBst500s Etaj2/2ndFL 30000.00 kgBst500s Etaj3/3rdFL 30000.00 kgBst500s Etaj4/4thFL 30000.00 kgBst500s Etaj5/5thFL 30000.00 kgBst500s Etaj6/6thFL 30000.00 kgBst500s Etaj7/7thFL 30000.00 kgBst500s Etaj8/8thFL 30000.00 kgBst500s Etaj tehnic/Mech
FL 17000.00 kg
TOTAL 391000.00 kg
3 Armatura in plansee si scari - slabs and stairs reinforcement
Bst500s Subsol/Basement
85000.00 kg
Bst500s Parter/G.F. 70000.00 kgBst500s Etaj1/1stFL 51000.00 kgBst500s Etaj2/2ndFL 51000.00 kgBst500s Etaj3/3rdFL 51000.00 kgBst500s Etaj4/4thFL 51000.00 kgBst500s Etaj5/5thFL 51000.00 kgBst500s Etaj6/6thFL 55000.00 kgBst500s Etaj7/7thFL 55000.00 kgBst500s Etaj8/8thFL 55000.00 kgBst500s Etaj tehnic/Mech
FL 5000.00 kg
TOTAL 580000.00 kg
1 Armatura in fundatii - footings reinforcementGrinzi continue - Continuous footings-Bst500s Fundatii/Foundati
ons 6500.00 KgTOTAL 6500.00 Kg
2 Armatura in stalpi- columns reinforcementBst500s Subsol2/
Basement2 800.00 Kg
R.4. Armatura -ReinforcementsCORP PRINCIPAL - MAIN STRUCTURE
CORP SECUNDAR - SECONDARY STRUCTURE
ANTEMASURATOARE/B.O.Q. ARMATURA/REINFORCEMENT
-
CLDIREDEBIROURIOFFICEBUILDINGBd.Pandurilor4446,TrguMure
FAZAPHASED.L.(BID)
Bst500s Subsol1/Basement1 800.00 Kg
Bst500s Parter/G.F. 8800.00 KgBst500s Etaj1/1stFL 8800.00 KgBst500s Etaj2/2ndFL 10400.00 Kg
TOTAL 29600.00 Kg
3 Armatura in plansee grinzi si scari - slabs, beams and stairs reinforcement
Bst500s Subsol2/Basement2 500.00 Kg
Bst500s Subsol1/Basement1 500.00 Kg
Bst500s Parter/G.F. 22000.00 KgBst500s Etaj1/1stFL 21000.00 KgBst500s Etaj2/2ndFL 19000.00 Kg
TOTAL 63000.00 Kg
1 Armatura in stalpi- columns reinforcementBst500s Subsol1/
Basement1 450.00 KgBst500s Parter/G.F. 3600.00 KgBst500s Etaj1/1stFL 6500.00 Kg
TOTAL 10550.00 Kg
2 Armatura in plansee grinzi si scari - slabs, beams and stairs reinforcement
Bst500s Subsol1/Basement1 500.00 Kg
Bst500s Parter/G.F. 12000.00 KgBst500s Etaj1/1stFL 12250.00 Kg
TOTAL 24750.00 Kg
1 Beton armat in pereti- walls reinforced concrete
C30/37-XF1,(XC2)XC4,XD2-ciment hidrotehnic Bst500s12000.00 Kg
TOTAL Bst500s 11500.00 Kg
2 Beton armat in radier+planseu - foundation slab,floor slab,
Bst500s 12500.00 KgTOTAL Bst500s 12500.00 Kg
PARAPETI EXTERIORI+SCARI EXTERIOARE/OUTDOOR PARAPETS+OUTDOOR STAIRS
1
Beton armat in pereti exteriori(beton spalat cu agregate vizibile) - outdoor walls reinforced concrete(washed concrete with visible aggregates)
Bst500s 12300.00 KgTOTAL Bst500s 12300.00 Kg
2 Beton armat in fundatii - foundations
Bst500s 9040.00 KgTOTAL Bst500s 9040.00 Kg
CORP PARCAJE - PARKING CORP
REZERVOR APA - WATER TANK
ANTEMASURATOARE/B.O.Q. ARMATURA/REINFORCEMENT
-
CLDIREDEBIROURIOFFICEBUILDINGBd.Pandurilor4446,TrguMure
FAZAPHASED.L.(BID)
3
Beton armat in plansee exterioare, trepte(dalele de parcare nu fac obiectul masuratorii) - outdoor slabs and outdoor stairs(parking slabs are not includet)
Bst500s 3500.00 KgTOTAL Bst500s 3500.00 Kg
ANTEMASURATOARE/B.O.Q. ARMATURA/REINFORCEMENT
-
CLDIREDEBIROURIOFFICEBUILDINGBd.Pandurilor4446,TrguMure
FAZAPHASED.L.(BID)
RefDescriere
(Item Description)
Nivel LevelCantitate Quantity
Unitate Unit
Pret Rate
TOTAL (EUR)
1 Profil metalic sustinere consola -S355JR- metallic parts for cantilever support
Subsol/Basement 0 kg
Parter/G.F. 0 kgEtaj1/1stFL 0 kgEtaj2/2nd 0 kgEtaj3/3rd kgEtaj4/4th 0 kgEtaj5/5th 0 kgEtaj6/6th 850 kgEtaj7/7th 850 kgEtaj8/8th 850 kg
Etaj tehnic/Mech
FL 0 kgTOTAL 2550.00 kg
2Profile metalice(gujoane tip JORDAHL) in placa -S500- metallic parts for slab-JORDAHL type
S500 Radier/Slabfoundation 27000 kg(10500buc.d=16mm,L=1300mm)
S500 Subsol/Basement 4600 kg(920 buc. d=16mm, L=230mm)
S500Parter/G.F.
2000 kg(400 buc. d=16mm, L=230mm)
S500Etaj1/1stFL
2000 kg(400 buc. d=16mm, L=230mm)
S500Etaj2/2nd
FL 2000 kg(400 buc. d=16mm, L=230mm)
S500Etaj3/3rd
FL 2000 kg(400 buc. d=16mm, L=230mm)
S500Etaj4/4th
FL 2000 kg(400 buc. d=16mm, L=230mm)
S500Etaj5/5th
FL 2000 kg(400 buc. d=16mm, L=230mm)
S500Etaj6/6th
FL 2000 kg(400 buc. d=16mm, L=230mm)
S500Etaj7/7th
FL 2000 kg(400 buc. d=16mm, L=230mm)
S500Etaj8/8th
FL 2000 kg(400 buc. d=16mm, L=230mm)
S500Etaj
tehnic/Mech FL 0 kg
TOTAL 49600.00 kg
CORP PRINCIPAL - MAIN STRUCTURER.5. Structuri si piese metalice / Metallic parts and structures
ANTEMASURATOARE/B.O.Q. STRUCTURIMETALICE/STEELSTRUCTURES
-
CLDIREDEBIROURIOFFICEBUILDINGBd.Pandurilor4446,TrguMure
FAZAPHASED.L.(BID)
3 Ancore chimice Hit-RE500/HVU- chemical anchors Hit-RE500/HVU
385.00 bucTOTAL 385.00 buc
4 Profile metalice etaj tehnic -S355 J2G3- metallic parts for tehnical storey
S355-J2G3-galvanizat Etaj tehnic/Mech
FL 29000.00 kg
TOTAL 29000.00 kg5 Spraituri metalice S355JR - steel struts
S355JR Subsol/Basement 2200.00 kg
TOTAL 2200.00 kg
1 Profile metalice scara- stairs metalic shapes
S355-J2G3-galvanizat 12000.00 KgTOTAL 12000.00 Kg
2 Suprafata tratata cu rasini epoxidice- epoxi surface treatement
SikaDur-30-tmin=3mm 80.00 mpTOTAL 80.00 mp
3 Ancore chimice Hit-RE500/HVU- chemical anchors Hit-RE500/HVU
75.00 bucTOTAL 75.00 buc
4 Profile metalice - metalic shapesS355JR Subsol2/
Basement2 500.00 KgS355JR Subsol1/
Basement1 5000.00 KgS355JR Parter/G.F.
0.00 KgS355JR Etaj1/1stFL
600.00 KgS355JR Etaj2/2nd
FL 600.00 KgTOTAL 6700.00 Kg
1 Profile metalice scara- stairs metalic shapes
S355JR-galvanizat Fundatii 2000.00 KgTOTAL 2000.00 Kg
2 Ancore chimice Hit-RE500/HVU- chemical anchors Hit-RE500/HVU
85.00 bucTOTAL 85.00 buc
3Profil metalic sustinere echipament tehnic -S355JR- metallic parts for tehnical equipment support
CORP SECUNDAR - SECONDARY STRUCTURE
CORP PARCAJE - PARKING CORP
ANTEMASURATOARE/B.O.Q. STRUCTURIMETALICE/STEELSTRUCTURES
-
CLDIREDEBIROURIOFFICEBUILDINGBd.Pandurilor4446,TrguMure
FAZAPHASED.L.(BID)
S355JR-galvanizat Parter/G.F.4500.00 Kg
TOTAL 4500.00 Kg
1 Profile metalice scara- stairs metalic shapes
S355-J2G3-galvanizat 350.00 KgTOTAL 350.00 Kg
REZERVOR APA - WATER TANK
ANTEMASURATOARE/B.O.Q. STRUCTURIMETALICE/STEELSTRUCTURES
-
CLDIREDEBIROURIOFFICEBUILDINGBd.Pandurilor4446,TrguMure
FAZAPHASED.L.(BID)
RefDescriere
(Item Description)Nivel Level
Cantitate Quantity
Unitate Unit
Pret Rate
TOTAL (EUR)
R.6. Profile etansare la rosturi - Waterstop at construction jointsCORP PRINCIPAL, REZERVOR APA- MAIN STRUCTURE,WATER TANK
ProfilSikaKAB125/WaterstopSikaKAB125Subsol / Basemant 180.00 ml
ProfilSikaV20/WaterstopSikaV20Subsol / Basemant 242.00 ml
Cordondeetansare/SwellingWaterstopSubsol / Basemant 110.00 ml
ProfilSikaTricomerD320/WaterstopSikatricomerD320Subsol / Basemant 190.00 ml
NOT:HIDROIZOLATIILESEVORESTIMACONFORMSPECIFICATIILORDINPROIECTULDEARHITECTURA.DENUMIRILEPRODUCATORILORSUNTDATEINFORMATIV,POTFIAPROVIZIONATESIDELAALTIPRODUCATORI,DARCUCALITATESIMILARACantitileprezentatenacestdocumentsuntcantitiestimate,lafazaactual.nfazeleulterioredeproiectare(PTh,DE),vortrebuiefectuateanalize,calculeiverificridetaliatelanivelulfiecruielementstructural.Cantitilereale,nfazadeproiecttehnic(PTh)iDetaliideExecutie(DDE)vorputeadiferideceleestimatenaceastetap.Sevorvizaanalizepentruoptimizareacantitiloriacosturilor.Toaterosturiletehnologicedeturnareforfitratatecutablaexpandata.
NOTE:Hydroisulationswillbeestimatedasspecifiedinarchitecturaldesign.Producerscanbestockedfromothermanufacturers,butsimilarqualitymustberespected.Designphasesassubsequently(PTH,DE)analysiswillbeperformed,detailedcalculationsandchecksineachstructuralelement.Realquantities,willbeinthetechnicalprojectphase(PTH)anddetailsexecutions(DDE)andmaydifferfromtheestimationsofthisstage,itwilloptimizequantitiesandcosts.Alltechnologicaljointsmustbetreatedwithexpandedmetalsheet.
ANTEMASURATOARE/B.O.Q. ALTEMATERIALE/OTHERMATERIALS