  • I. Introducere I. Introduction

    Cartea tehnica a constructiei se compune

    din ansamblul de documente referitoare la

    proiectarea, executia, receptia, exploatarea,

    intretinerea, repararea si urmarirea in timp a

    constructiei.

    Ea cuprinde documentatia de baza

    structurata pe patru capitole si doua anexe care,

    prin completarea lor, formeaza, in final , Cartea

    Tehnica a Constructiei in conformitate cu HG

    nr.273/1994 , si anume:

    Fisa de date sintetice

    Capitolul A : Documentatia privind proiectarea

    Capitolul B : Documentatia privind executia

    Capitolul C : Documentatia privind receptia

    Capitolul D : Documentatia privind exploatarea,

    intretinerea, repararea si urmarirea

    comportarii in timp

    Jurnalul evenimentelor

    The technical book of the building consist

    an overall documents refering to the design,

    execution, reception, exploitation, maintenance,

    repair and tracking of the building in time.

    It includes the base documentation that is

    structured in four chapters and two annexes

    which, from their completion form the Technical

    Book as per GD no.273/1994, in the end, as it

    follows:

    Index card of the synthetic dates

    Chapter A : The design documentation

    Chapter B : The execution documentation

    Chapter C : The reception documentation

    Chapter D : Documentation for exploitation,

    maintenance, repair and tracking of

    the behavior in time.

    Events journal

    Cap. A : Documentatia privind proiectarea Chip. A : Design documentation

    Documentatia privind proiectarea va

    cuprinde, conform HG nr.592 / 1993 (Regulament

    privind procedurile de organizare a licitatiilor) :

    1. Tema de proiectare, elaborata de investitor (beneficiar)

    2. Amplasarea obiectului judet, localitate, strada, numar

    3. Avize si acorduri: Avizele si acordurile emise de organele in drept,

    potrivit legislatiei in vigoare, privind:

    avizul ordonatorului principal de credite privind necesitatea si oportunitatea

    realizarii investitiei;

    certificatul de urbanism;

    avizele privind asigurarea utilitatilor: o energiei termice si electrice; o gaz metan; o apa, canal; o telecomunicatii o acordul Inspectiei de Stat in

    Constructii (ISC) privind

    The design documentation should include

    as per GD no.592/1993 (Rule of the the auction

    organization procedures) :

    1. Design theme, developed by the investor (owner)

    2. Location of the object county, locality, street, number

    3. Notifications and agreements: The notifications and agreements issued by the

    law enforcement, as per foree legislation, on :

    the principal credits sequencer notification on the necessity and opportunity of the

    investment accomplishment;

    urbanism cerficate

    notifications for utilities insurance: o thermic and electrical energy o marsh gas o water, sewer system o telecommunication o the agreement of the State

    Inspectorate in Constructions (SIC)

  • interventiile la constructiile

    existente etc.

    avizele pentru consumul de combustibil;

    avizele pentru protectia mediului si apelor;

    alte avize de specialitate potrivit dispozitiilor legale;

    acordul proprietarilor vecini pentru cazurile in care noua constructie intervine

    cu lucrari la imobilele acestora;

    aviz Aparare Civila.

    4. Documentatia tehnica

    4.1. Parti scrise

    4.1.1. Prezentarea generala a lucrarilor

    a. Elemente generale

    Proiectul tehnic trebuie sa fie verificat,

    avizat si aprobat potrivit prevederilor legale.

    El este format din documentatia scrisa si

    desenata.

    Proiectul tehnic se elaboreaza pe baza

    studiului de fezabilitate aprobat, etapa in care au

    fost stabilite elementele si solutiile principale ale

    lucrarii si au fost obtinute toate avizele, acordurile

    si aprobarile executiei lucrarii, in conformitate cu

    prevederile legale. Proiectul tehnic se verifica de

    catre specialisti atestati de MLPAT conform

    regulamentului aprobat prin HG nr. 731 / 1991

    (Regulament de atestare tehnico-profesionala a

    specialistilor cu activitate in constructii) si se

    avizeaza si se aproba de investitor.

    La lucrarile ce se executa din fonduri publice

    este necesar si studiul de prefezabilitate.

    b. Descrierea lucrarilor In aceasta sectiune se vor face referiri

    asupra urmatoarelor elemente:

    Amplasamentul;

    Topografia;

    Clima zonei;

    Geologia, seismicitatea;

    Prezentarea proiectului pe volume, brosuri, capitole;

    Organizarea de santier, descriere sumara,

    on the improvement at the existing

    constructions etc.

    notifications for fuel consuming;

    notifications for environment and water protection;

    another notifications as per legal dispositions;

    the agreement of the neighbours owner when the new construction intervene with

    works on their immobile;

    notification from Civil Defence.

    4. Technical documentation

    4.1. Written parties

    4.1.1. General view of the works

    a. General elements

    The technical project needs to be checked,

    noticed and approved as per legal previsions.

    It is composed by the written

    documentation and the drawn parts.

    The technical project is developed on the

    approved feasibility study, stage inside were

    established the elements and principal solutions of

    the construction and were obtained all the

    notifications, the agreements and approvals of the

    building execution, as per legal previsions. The

    technical project is checked by the certificate

    experts certified by MLPAT as per the rule

    approved by HG no. 731 / 1991 (Regulation that

    certified the experts technical-proffesional activity

    in constructions) and is notificated and approved

    by the investor.

    At the works that are executed with public

    funds it is necessary the fesability study also.

    b. Description of the works This section is referring at the followings:

    Emplacement;

    Topography;

    Zonal climate;

    Geology, seismicity;

    The presentation of the project on volumes, brochures, chapters;

    Site organization, summary description,

  • demolari, devieri de retele etc.;

    Sursele de apa, energie electrica, gaze, telefon;

    Caile de acces, caile de comunicatie;

    Trasarea lucrarilor;

    Protejarea lucrarilor executate si a materialelor din santier;

    Masurarea lucrarilor;

    Curatenia in santier;

    Serviciile sanitare;

    Relatiile intre proiectant, consultant si investitor;

    Memoriile tehnice pe specialitati.

    4.1.2. Caietele de sarcini

    Caietele de sarcini dezvolta in scris elementele

    tehnice mentionate in planse si prezinta informatii,

    precizari si prescriptii complementare planselor.

    Ele se elaboreaza de catre proiectant pe baza

    planselor deja terminate si se organizeaza in

    brosuri distincte pe specialitati.

    a. Tipuri si forme de caiete de sarcini

    In functie de destinatie pot fi:

    caiete de sarcini pentru executia lucrarilor;

    caiete de sarcini pentru receptii, teste, probe, verificari si puneri in functiune,

    urmarirea comportarii in timp a

    constructiilor;

    caiete de sarcini pentru furnizorii de materiale, utilaje, echipamente si confectii

    diverse etc.

    b. Continutul caietelor de sarcini Caietele de sarcini trebuie sa cuprinda:

    breviarele de calcul pentru dimensionarea elementelor de constructii si instalatii;

    nominalizarea planselor care guverneaza lucrarea;

    proprietatile fizice, chimice, de aspect, de calitate, tolerante, probe pentru materialele

    componente ale lucrarii

    dimensiunea, forma, aspectul si descrierea executiei lucrarii;

    ordinea de executie, probe, teste, verificari ale lucrarii;

    standardele, normativele si alte prescriptii care trebuie respectate la materiale, utilaje,

    demolitions, networks deviation;

    Water sources, electrical energy, gas, phone;

    Access roads, communication ways;

    Setting out of the works;

    Protection of the executed works and materials on site;

    Works measuring;

    Cleaning the site;

    Sanitary services;

    Relationships between the designer, consultant and investor;

    Technical prescription on activities.

    4.1.2. Technical Specifications

    The Technical Specifications develop in

    write the technical elements mentioned in the

    drawings and have information and drawing

    complementary specifications. These ones are

    issued by the designer on the drawings finished

    already and are organized in separate brochures on

    specialities.

    a. Types and forms of the technical specifications:

    Depending on the destination these can be:

    technical specifications for the works execution;

    technical specifications for reception, tests, events, verifications and start of regular

    productions, tracking the constructions in

    time;

    technical specifications for the material, equipment, machinery and for various

    manufacture suppliers etc.

    b. Technical specifications contents The technical specifications should include:

    Breviary calculation for admeasurements of the construction and plants elements;

    Nomination of the drawings that governs the work;

    Physical, chemical, estetique, quality, tolerence properties of the work

    components material;

    Dimension, form, aspect and description of the work execution;

    The order of execution, samples, tests, controls of the work;

    Standards, normative and other prescriptions that must be respected in the

  • confectii, executie, montaj etc.;

    conditii de receptie, aspect, culori, tolerante etc.

    4.1.3. Breviare de calcul pe specialitati (actiuni, ipoteze de calcul, rezultatele

    calculelor de dimensionare si

    verificare etc.)

    4.2. Parti desenate Partile desenate se compun din:

    4.2.1 Planurile generale

    planurile de amplasare a reperelor de nivelment planimetrice;

    planuri topografice principale;

    planurile de amplasare a forajelor si profilelor geotehnice;

    planurile principale privind sistematizarea verticala a terenului;

    planurile principale privind constructiile subterane;

    planurile de amplasare a reperilor ficsi si mobil de tasare.

    4.2.2. Plansele obiectului Plansele se organizeaza in volume pe specialitati

    a. Arhitectura Aceasta sectiune va cuprinde planse privind

    arhitectura fiecarui obiect, conform borderoului

    intocmit de proiectant:

    planul de amplasare;

    planurile de arhitectura ale nivelurilor subterane si supraterane, ale teraselor,

    acoperisurilor etc.;

    sectiuni, fatade, detalii etc.;

    tablouri de prefabricate, confectii;

    tablouri de tamplarii si tablouri de finisaje interioare si exterioare;

    etc.

    b. Structura Aceasta sectiune va cuprinde plansele privind

    alcatuirea si executia structurii de rezistenta

    pentru fiecare obiect, conform borderoului

    intocmit de proiectant:

    planurile infrastructurii si sectiunile caracteristice;

    planurile suprastructurii si sectiunile caracteristice;

    descrierea solutiilor constructive recomandate si a tehnologiilor de executie

    case of materials, equipments,

    manufactures, execution, montage etc.;

    Conditions for reception, aspect, colors, tolerance etc.

    4.1.3. Breviaries calculation on specialties (actions, calculation hypotheses,

    results of the admeasurements and

    checking calculation )

    4.2. Drawn parts The drawn parts consist:

    4.2.1. Master plans

    layout of marks lacation !!!!!!!!!!!!!!!

    principal topographic layout;

    layout for drilling locations and for the geotechnic profiles;

    principal layout concerning the vertical systematization of the area;

    principal layout for the underground constructions;

    layout for placement of the fixed and mobile compaction marks.

    4.2.2 Objects drawing The drawings are organized in volumes on

    specialities

    a. Architecture This section will include architecture drawings for

    every object, in conformity with the borderau

    issued by the designer:

    placement layout;

    architecture layout for the underground and areal levels, terrace, roofs etc.;

    sections, faade, details etc.;

    precast panels, manufactures;

    joinery panels and panels for interior and exterior finishing;

    etc.

    b. Structure This section will include drawings with the

    composition and execution of the resistance

    structure for each object, in conformity with the

    bordereau issued by the designer:

    layout of the infrastructure and his characteristic sections;

    layout of the superstructure and his characteristic sections;

    description of the recommended solution for the construction and execution

  • recomandate.

    c. Instalatiile Aceasta sectiune va cuprinde planse privind

    montajul instalatiilor fiecarui obiect, conform

    borderoului intocmit de proiectant:

    planurile de amplasare a utilajelor si echipamentelor;

    schemele de amplasare a utilajelor si echipamentelor;

    scheme ale instalatiilor;

    sectiuni, vederi, detalii.

    d. Dotari si instalatii tehnologice Aceasta sectiune va cuprinde planurile principale

    de tehnologie si montaj si anume:

    desene de ansamblu;

    scheme tehnologice ale fluxului tehnologic;

    scheme cinematice;

    schemele instalatiilor;

    diagrame, monograme, calculele ingineresti, tehnologice si de montaj;

    planuri de montaj, geometrii, dimensiuni de amplasare, scheme tehnologice de

    montaj;

    liste cu utilaje si echipamentele din componenta planurilor tehnologice.

    e. Dotari de mobilier, inventar gospodaresc, paza contra incendiilor, protectia muncii

    Aceasta sectiune va cuprinde:

    planurile de amplasare si montaj;

    listele cu dotari.

    4.2.3. Indicarea distinct a diferentelor fata de detaliile de executie initiale, cu

    precizarea cauzelor care au dus la

    aceste diferente.

    technologies.

    c. Plants This section will include drawings concerning the

    installations montage for each object, in

    conformity with the borderau issued by the

    designer:

    layout for machinery and equipments placement;

    sketch for machinery and equipments placement;

    plants sketch;

    sections, views, details.

    d. Endowment and technological plants This section will include the principal

    technological and montage layouts:

    overall designs;

    technological sketches for the technological flow;

    kinematic sketches;

    installation sketches;

    diagrams, monograms, engineering, technological and montage calculations;

    montage layouts, geometry, placement dimensions, technological montage

    sketchs;

    list with machinery and equipments from the technological layouts.

    e. Furniture endowment, inventory household, guard against fire, labor

    protection

    placement and montage layouts;

    endowment lists.

    4.2.3 Indicating the distinct differences against the initial execution details,

    with the clarification of the causes that

    leaded to those differences.

    Cap. B Documentatia privind executia

    Cph. B Execution documentation

    Documentatia tehnica privind executia cuprinde:

    1. Autorizatia de construire a obiectivului de investitie

    Documentatia pentru eliberarea autorizatiei de

    construire contine urmatoarele piese: (in

    conformitate cu prevederile art.5 si 6 din Legea

    nr. 50/1991) .

    Technical documentation concerning execution

    consist:

    1. Building permit of the investment objective

    The documentation for the building permit issue

    consist the followings pieces (as per law no.

    50/1991 art. 5 and 6) .

  • 1.1. Certificatul de urbanism pentru constructia in cauza. Certificatul este emis

    de autoritatile publice locale. Cererea tip

    se obtine de la sediul prefecturii sau

    primariei.

    1.2. Dovada titlului solicitantului asupra terenului si constructiilor (titlu de

    proprietate sau act de concesionare in

    copie legalizata).

    1.3. Proiectul pentru autorizatie de construire, in doua exemplare. Continutul proiectului

    pentru autorizatia de construire este

    prezentat in Anexa 14.

    Inceperea lucrarilor de construire se va

    face dupa obtinerea autorizatiei.

    2. Proces-verbal de predare primire a amplasamentului si a bornelor de repere

    (Anexa 1)

    3. Inregistrari de calitate cu caracter permanent efectuate pe parcursul

    executarii lucrarilor, precum si

    documentatii care atesta calitatea

    lucrarilor:

    Actele sunt de trei feluri:

    a. Acte referitoare la calitatea materialelor folosite la realizarea constructiei.

    Acestea sunt:

    certificate de calitate a materialelor;

    rezultatele incercarilor efectuate pe materialele, instalatiile si echipamentelor

    care au fost puse in lucrare.

    b. Acte care se completeaza de catre constructor, beneficiar si proiectant la

    fiecare etapa de lucru:

    Formularele sunt urmatoarele:

    Proces-verbal de predare-primire a amplasamentului si a bornelor de reper

    Proces-verbal de trasare lucrari

    Proces-verbal de lucrari ascunse Registrul proceselor-verbale de lucrari

    ascunse

    Proces-verbal faze determinante

    Proces-verbal aspect beton dupa decofrare

    Condica de betoane

    Proces-verbal de receptie a terenului de fundare, a fundatiilor si structurii de

    rezistenta

    1.1. Urbanism certificate for the respective construction. The certificate is issued by the

    local public authorities. The tip demand is

    obtained from the towmhall or prefecture

    office.

    1.2. The proof of the applicant title on the land and constructions (title of property or

    concession act in legalized copy).

    1.3. The project for the building permit, in two copies. The content of the project for the

    building permit is presented in 14th

    Annex

    The works will start after obtaining the

    building permit.

    2. Hand over for the placement and curbstone mark (1

    st Annex)

    3. Quality records with permanent character carried out on the works execution, as well

    as documentations that certificate the

    works quality:

    There are three forms of these acts:

    a. Acts referring to the quality of materials used at the building accomplishment:

    These are:

    quality certificate of the materials;

    the results of the attempts carried out on materials, installations and equipments that

    were uded in the work.

    b. Acts that are completed by the constructor, owner and designer for the each and every

    stage of work:

    The forms are the following:

    Hand over for the placement and curbstone marks

    Setting out hand over

    Hand over for the works which become hidden hand over register for hidden works

    Determinat phase hand over

    Hand over for the concrete aspect after the formwork removal

    Concrete ledger

    Hand over for the reception of the area, foundations and resistance structure

  • Proces-verbal de montarea instalatiilor de masurare din proiectul de urmarire a

    comportarii in exploatare

    Jurnalul principalelor evenimente (inundatii, cutremure, temperature

    excesive)

    c. Acte care nu folosesc formulare tip dar care trebuie sa existe in Cartea Tehnica:

    Registrul unic de comunicari si dispozitii de santier

    Nota de constatare a organelor de control

    Expertize tehnice ca urmare a unor greseli de executie sau ca urmare a unor accidente

    tehnice

    Caiete de atasament.

    Hand over for mounting the measurement installations included in the tracking

    project of the behavior in time

    The journal of the principal events (floods, earthquakes, high temperature)

    c. Acts that don`t use standard forms but witch must exist in the Technical Book:

    The unique communications and site dispositions register

    Establishment note for the control experts

    Technical examination that follows some execution error or some technical

    accidents

    Attachment specifications

    Cap. C Documentatia privind receptia lucrarilor

    Chp. C Execution documentation

    Receptia lucrarilor de constructii de orice

    categorie si instalatii aferente se efectueaza atat la

    lucrari noi cat si la interventiile in timp (reparatii

    capitale, consolidari, modificari, modernizari,

    extinderi etc.) asupra lucrarilor existente si se

    realizeaza in doua etape (conform Hotararii

    Guvernului HG nr. 273/1994 Regulamentul de receptie a lucrarilor de constructii si instalatii

    aferente acestora);

    receptia la terminarea lucrarilor;

    receptia finala le expirarea perioadei de garantie.

    Completarea datelor de la acest capitol se face

    numai dupa ce s-au completat datele de la

    capitolul B Executarea lucrarilor si Fisa de date tehnice punctele de la 1 la 7.

    1. Receptia la terminarea lucrarilor Participantii sunt:

    comisia de receptie;

    proiectantul lucrarii;

    executantul lucrarii.

    2. Receptia finala Participantii sunt:

    comisia de receptie;

    The reception of the construction works of

    any category and installations are carried out to

    the new construction but also at the changes made

    in time (capital repairs, consolidations, changes,

    improvements, extensions etc.) on the existing

    constructions and it`s realized in two stages (as

    per GD no. 273/1994 Reception rule of the construction works and installations afferent) ;

    reception at the finishing of the works

    final reception at the end of the guarantee period.

    The dates completion from this chapter is made

    after the dates from the chapter B Works execution and Technical dates sheet were completed !!!!!!!!!!!!!

    1. Reception at the end of the works The participants are:

    the reception commission;

    the designer;

    the executant.

    2. Final reception The participants are:

    the reception commission;

  • proiectantul lucrarii;

    executantul lucrarii.

    Comisia de receptie

    se numeste de catre investitor

    este formata din cel putin 5 membri dintre care:

    o unul este reprezentatul investitorului;

    o unul este reprezentant al ordinii publice locale;

    o ceilalti vor fi specialisti in domeniu.

    pentru constructiile de importanta exceptionala comisiile vor fi formate din

    minim 7 membri si numarul de specialisti

    va fi de minim 5.

    Pentru locuintele cu max. P+1 comisiile vor fi alcatuite din 2 membri:

    o investitorul; o delegatul administratiei locale.

    pentru constructiile cu inaltimea mai mare de 28 m sau cu sali de capacitate mai mare

    de 150 persoane, in comisie va exista si o

    persoana desemnata de Comandamentul

    Trupelor de Pompieri.

    Formularele care trebuie completate cu

    ocazia receptiei sunt urmatoarele:

    a. Proces-verbal de receptie la terminarea lucrarilor

    b. Proces-verbal de receptie finala b.1. Pentru constructiile cu max. P+1

    b.2. Pentru celelalte tipuri de constructii

    c. Alte acte suplimentare incheiate ca urmare a cererii comisiilor de receptie prin care se

    prevad verificari sau cercetari

    suplimentare cu indicarea rezultatelor

    obtinute si a modului de rezolvare.

    the designer;

    the executant.

    The reception commission

    it is named by the owner

    it has at least 5 members :

    o one of the is the owner representative;

    o one is the public and local administration representative;

    o the other ones will be experts in the respective activity.

    For the constructions with a exceptional importance the commissions will have 7

    members and the experts number will be

    at least 5

    For the buildings with max ground floor and floor the commissions will have 2

    members:

    o the owner; o the public and local administrative

    representative.

    For the constructions higher than 28 m or with meeting rooms for over 150 persons,

    the commission will have a person from

    the Fire brigade Commandament.

    The forms that needs to be completed for the

    reception are the followings:

    a. Hand over for the reception at the end of the works

    b. Hand over for final reception b.1. For constructions with ground floor and floor

    b.2. For the other types of construction

    c. Another additional acts concluded as a

    consequence of the reception commissions

    demand witch prevese checkings or additional

    controls with the indication of the results obtained

    and solution manner.

    Cap. D Documentatie privind urmarirea comportarii in exploatare si interventii in timp

    Chp. D The documentation for tracking the behavior in the exploitation and interventions in

    time

    Cuprinde urmatoarele documente (conform HG

    nr.273/1994)

    1. Prevederi ale proiectantului 1.1. Privind urmarirea comportarii constructiei 1.2. Instructiunile de exploatare si intretinere

    Consist the following documents (as per GD

    no.273/1994)

    1. Designer previsions 1.1. On the tracking of the construction

    behavior

  • 1.3. Lista prescriptiilor de baza care trebuie respectate in timpul executiei si

    exploatarii

    2. Proiectele in baza carora s-au efectuat, dupa receptia finala a lucrarilor, modificari ale

    constructiei fata de proiectul initial realizat.

    Documentatia care este necesara la acest

    punct este aceeasi ca la cap A Documentatie privind proiectarea.

    3. Proiectul de urmarire speciala a constructiei - daca este cazul

    4. Acte de constatare a unor deficiente aparute dupa receptia executarii lucrarilor si

    masurile de interventie luate.

    Aceste acte sunt:

    Nota de constatare

    Proces-verbal de remediere a defectelor

    5. Proces-verbal de predarea primire a instalatiilor de masurare prevazute prin proiectul

    de urmarire speciala a constructiei incheiat intre

    executant si beneficiar.

    6. Referatul cu concluziile anuale si finale asupra rezultatelor urmaririi speciale

    7. Procese-verbale de predarea primire a constructiei cand se schimba proprietarului.

    8. Jurnalul evenimentelor intocmit conform modelului de formular.

    1.2. Exploitation and maintenance instructions 1.3. The list with the base prescriptions that

    needs to be respected in the execution and

    exploitation

    2. The projects on witch were carried out, after the final reception, changes of the

    construction over the initial project.

    The necessary documentation at this point is the

    same as the one from the chapter A The design documentation

    3. The project for special tracking of the construction if it is necessary

    4. Establishment acts for some deficiency that occurs after execution reception and

    the intervention measures that were taken.

    These acts are:

    Finding sheet

    Hand over for the defect remedial

    5. Hand over for installation measurement from the special tracking project of the

    construction concluded between the

    executant and owner.

    6. Report with final and annual conclusions on the special tracking results.

    7. Hand over for construction when the owner is changing.

    8. Events journal issued as per the standard model of the form.

    Jurnalul evenimentelor

    Events journal

    Denumirea obiectului . . . . . . . . . . . . . . . . .

    Instructiuni de completare

    1. Evenimentele care se inscriu in jurnal se codifica cu urmatoarele litere in coloana

    categoria evenimentului UC rezultatele verificarilor periodice din cadrul urmaririi curente;

    US Rezultatele verificarilor si masuratorilor din cadrul urmaririi speciale, in cazul in care implica

    luarea unor masuri;

    M Masuri de interventie in cazul constatarii unor deficiente (reparatii, consolidari, demolari,

    etc.);

    E Evenimente exceptionale (cutremur, inundatii,

    The name of the object

    Completion instructions

    1. The events that are written in the journal are encoded with the following characters in the

    event category colum: CT the results of the periodical checking included in the current tracking;

    ST the results of the checking and measurement form the special tracking when it is necessary to

    take action;

    M intervention measurement when some deficiences are detected (repairs, consolidations,

    demolations, etc.);

    E exceptional events (earthquakes, floods, fire,

  • incendii, ploi torentiale, caderi masive de zapada,

    poluari sau alunecari de teren etc.);

    D Procese verbale intocmite de organele de verificare pe faze de executie lucrarilor;

    C Rezultatele controlului privind modul de intocmire si pastrare a Cartii Tehnice a Constructiei

    2. Evenimentele consemnate in jurnal si care au corespondent in actele cuprinse in

    documentatia de baza, se prevad cu trimiteri la

    dosarul respective, mentionanad natura actelor.

    3. Schimbarea proprietarului se va consemna si in jurnalul evenimentelor.

    Prezentarea capului de tabel:

    1. Numar curent: _______________ 2. Data evenimentului ___________ 3. Categoria evenimentului

    _________________________________

    4. Prezentarea evenimentului si a efectelor sale asupra constructiei cu trimiteri in actele din

    documentatia de baza

    ______________________________

    ______________________________

    ______________________________

    ______________________________

    ______________________________

    5. Numele, prenumele si unitatea persoanei care inscrie evenimentul si semnatura sa

    Numele ___________________________

    Prenumele _________________________

    Unitatea ___________________________

    Semnatura _________________________

    6. Semnatura responsabilului cu Cartea Tehnica a Constructiei Numele ___________________________

    Prenumele _________________________

    Semnatura _________________________

    torrent rain, heavy fall of snow, pollutions or

    landslides etc.);

    D hand over issued by the checking experts on execution stages of the work;

    C The results of the control made on the completion and storage manner of the Technical book of the construction.

    2. Events that are completed in the journal and witch have connection with the acts included

    in the base documentation, these one have

    references to the respective file, with the acts

    origin mentioned.

    3. When the owner will be changed it will be written in the events journal too.

    The head of the table:

    1. Current number: ______________ 2. Event date: __________________ 3. Event`s category

    _________________________________

    4. Event`s presentation and his effects on the construction with references on the acts from the

    base documentation

    __________________________________

    __________________________________

    __________________________________

    __________________________________

    __________________________________

    5. Name, surname and the unit of the person that is writing the event and his signature

    Name _____________________________

    Surname __________________________

    Unit ______________________________

    Signature __________________________

    6. The signature of the Construction technical book responsible

    Name ____________________________

    Surname _________________________

    Signature __________________________

    Modul de intocmire a Cartii tehnice a Constructiei

    Technical book of the Construction preparation

    method

    Cartea tehnica a constructiei se intocmeste de

    catre investitor pentru toate obiectele de

    constructii definitive, supuse regimului de

    autorizare a constructiilor (conform HG nr.

    273/1994).

    The Technical book of the construction is

    issued by the investor for all the final construction

    objects, on the building permit rule (as per GD

    no.273/1994)

  • Cartea tehnica se definitiveaza inainte de

    receptia finala.

    Cartea tehnica, dupa constituire, se

    completeaza si se pastreaza de catre investitor sau

    de catre proprietar.

    Actele ce formeaza documentatia de baza a

    cartii tehnice a constructiei vor fi indosarite pe

    capitolele respective in ordinea de mai jos cu file

    numerotate si parafate pe masura incheierii lor:

    Fisa de date sintetice

    Capitolul A Proiectare

    Capitolul B Executie

    Capitolul C Receptie

    Capitolul D Exploatare

    Jurnalul evenimentelor Fiecare dosar va cuprinde borderoul dosarului si

    va purta un indicativ format din litera

    corespunzatoare capitolului (A, B, C, D) si

    numarul de ordine al dosarului, in cifre arabe.

    Centralizatorul cartii tehnice va cuprinde

    borderoul general al dosarelor documentatiei de

    baza si copiile borderourile cu cuprinsul fiecarui

    dosar.

    Cartea tehnica a constructiei se intocmeste intr-un

    exemplar.

    Cartea tehnica se intocmeste pentru constructii noi de catre investitor impreuna cu proiectantul astfel:

    Proiectantul obiectului de constructie intocmeste si preda investitorului pe masura

    elaborarii si cel mai tarziu pana la data receptiei

    finale a lucrarilor documentatiei prevazuta la

    capitolul A- documentatie privind proiectarea si in

    capitolul D documente privind exploatarea

    Comisiile de receptie la terminarea lucrarilor de constructii si de receptie finala a

    constructiei predau investitorului documentatia

    prezentata la capitolul B - documentatia privind

    executia, imediat dupa intocmirea ei

    Investitorul obiectului de constructie primeste toate actele ce cad in sarcina

    proprietarului si a comisiilor de receptie , le

    completeaza cu actele ce cad in sarcina sa (cele

    prevazute la capitolul B), le indosariaza pe

    capitole; dupa receptia finala, investitorul retine

    un exemplar complet.

    Proprietarul sau utilizatorul completeaza Cartea Tehnica a Constructiei cu documentatia

    prevazuta in Jurnalul Evenimentelor.

    Proprietarul sau administratorul va asigura

    The Technical book must be completed before

    the final reception.

    The Technical book, after the constitution, is

    kept and completed by the investor or by the

    owner.

    The acts that form the technical book base

    documentation will be filed on the respective

    chapters in the below order, and the pages will be

    numbered and stamped as they will be finished:

    Index card of the synthetic date

    Chapter A Design

    Chapter B Execution

    Chapter C Reception

    Chapter D Exploitation

    Events journal Each file will include the dossier bordereau and

    will have a code base on the character of the

    chapter (A, B, C, D) and the number of the dossier

    in arabic numeral.

    The master table of the technical book includes

    the general bordereau of the dossiers of the base

    documentation and the copies of the bordereaus

    from each dossier.

    The technical book of the construction is

    issued in a single copy.

    The technical book - is issued for new

    constructions by the investor together with the designer as it follows:

    The designer of the construction object issues and deliver to the investor as per

    elaboration and latest up to final reception date of

    the works, the documentation from chapter A (The design documentation) and D (The

    exploitation documentation);

    Reception commission, at the end of the work and final reception of the construction hand

    over to the investor the documentation form

    chapter B the execution documentation, immediately after they were issued

    The construction object investor receive all the owner and reception commission acts,

    completes them, (the one from chapter B), filed

    them on chapters, after the final reception, and

    the investor keeps a full copy.

    The owner or user completes the Technical book of the Construction with the Events journal

    documents.

  • activitatea de urmarire a comportarii constructiei

    in exploatare si investitii in timp asupra acesteia.

    Modul de intocmire si completare a cartii

    tehnice a constructiei se controleaza in mod

    obligatoriu astfel:

    - de catre comisiile de receptie finala a obiectelor de constructie, cu ocazia

    receptiei;

    - de catre organele de control imputernicite in acest domeniu

    Rezultatele controlalelor se vor consemna in

    mod obligatoriu in Jurnalul Evenimentelor.

    Cartea Tehnica a Constructiei se pastreaza pe

    toata durata de executie a obiectului pana la

    demolarea sa; dupa demolare; investitorul preda

    exemplarul complet la arhiva unitatilor

    administrativ-teritoriale pentru pastrare. Inainte de

    predare, ea va fi completata cu modul de

    desfasurare a actiunii de postutilizare pe baza

    instructiunilor elaborate de proiectant.

    The owner or administrator will ensure the

    tracking activity of the construction behavior in

    exploitation and investements on this in time.

    The way of issue and completion of the

    technical book of the construction is checked

    obligatory as it follows:

    - by the final reception of the construction commissions, at the reception;

    - by the control organs empowered from the area

    The control results will be obligatory written in

    the Events journal.

    The Technical book of the Construction is kept on

    all the execution period until his demolition , after

    the demolition, the investor hands the full copy to

    the territorial administrative units that keep these

    documents. Before the hand over, it is completed

    with the post service activities on the designer

    instructions.

    Obligatii si raspunderi ale partilor implicate in

    realizarea Cartii Tehnice a Constructiei

    Obligatiile si raspunderile sunt prezentate conform

    Legii nr. 10/1995

    Liabilities and responsabilities for the implicated

    parts in the Technical book of Construction

    completion

    The liabilities and responsabilities are presented

    as per Law no. 10/1995

    1. Obligatii si raspunderi ale investitorilor

    Investitorii sunt persoane fizice sau juridice care

    finanteaza si realizeaza investitii sau interventii la

    constructiile existente in sensul legii si au

    urmatoarele obligatii principale referitoare la

    calitatea lucrarilor:

    Stabilirea nivelului calitativ ce trebuie realizat prin proiectare si executie pe baza

    reglementarilor tehnice, precum si a studiilor si

    cercetarilor efectuate;

    Obtinerea acordurilor si a avizelor prevazute de lege, precum si a autorizatiei de

    construire;

    Asigurarea verificarii proiectelor prin specialisti verificatori de proiecte atestati;

    Asigurarea verificarii executiei corecte a lucrarilor de constructii prin diriginti de

    specialitate sau agenti economici de consultanta

    specializati, pe tot parcursul proiectelor;

    Actionarea in vederea solutionarii

    1. Liabilities and responsabilities of the investors

    Investors are individuals or juridical person that

    funds and make investments or is intervening at

    the existing constructions in the name of law and

    have the following liabilities:

    Establishment of the quality level that has to be realized through design and execution on the

    technical regulations, as well as studies and

    examinations carried out;

    Obtaining the agreements and notifications, as well as building permit;

    Ensuring the checking of the projects through the attested project experts;

    Ensuring the checking of the correct execution of the works through site managers or

    consultancy economic agents on the entire

    projects;

    Solving the unconformities, defects that appeared in the execution and also the projects

  • neconformitatilor, a defectelor aparute pe

    parcursul executiei lucrarilor, precum si a

    deficientelor proiectelor;

    Asigurarea receptiei lucrarilor de constructii la terminarea lucrarilor si la expirarea

    perioadei de garantie;

    Intocmirea cartii tehnice a constructiei si predarea acesteia catre proprietar;

    Expertizarea constructiilor de catre expertii tehnici atestati si obtinerea acordului ISC,

    in situatiile in care la aceste constructii se executa

    lucrari de reconstruire, consolidare, transformare,

    extindere etc.

    deficiencies;

    Ensuring the construction works reception at the end of the works and at the expiration of the

    guarantee period;

    Elaboration of the Technical book of the Constructionand his handing over to the owner;

    Constructions examination made by the attested experts and obtaining the SIC agreement,

    in the situation when are executed reconstruction,

    transformation, consolidation and extension

    works etc.

    2. Obligatii si raspunderi ale proiectantilor

    2. Liabilities and responsabilities of the designer

    Proiectantii de constructii raspund de

    indeplinirea urmatoarelor obligatii principale

    referitoare la calitatea constructiilor:

    Precizarea prin proiect a categoriei de importanta a constructiei;

    Asigurarea prin proiecte si detalii de executie nivelului de calitate corespunzator

    cerintelor, cu respectarea reglementarilor tehnice

    si a clauzelor contractuale;

    Prezentarea proiectelor elaborate in fata specialistilor verificatori de proiecte atestati,

    stabiliti de catre investitor precum si solutionarea

    neconformitatilor si neconcordantelor semnalate;

    Elaborarea caietelor de sarcini, a instructiunilor tehnice privind executia lucrarilor,

    exploatarea, intretinerea si reparatiile, precum si,

    dupa caz, a proiectelor de urmarire privind

    comportarea in timp a constructiilor.

    Documentatia privind post utilizarea constructiilor

    se efectueaza numai la solicitarea proprietarului;

    Stabilirea, prin proiect, a fazelor de executie determinate pentru lucrarile aferente

    cerintelor si participarea pe santier la verificarile

    de calitate legate de acestea;

    Stabilirea modului de tratare a defectelor aparute in executie, din vina executantului, la

    constructiile la care trebuie sa asigure nivelul de

    calitate corespunzatoare cerintelor, precum si

    urmarirea aplicarii pe santier a solutiilor adoptate,

    dupa insusirea acestora de catre specialistii

    verificatori de proiecte atestati, la cererea

    investitorului;

    Participarea la intocmirea cartii tehnice a constructiei si la receptia lucrarilor executate.

    The designers of the constructions have the

    following principal responsabilities related to the

    construction quality:

    Project specification on the importance of the construction;

    Ensuring throught project and execution details the quality level as per requirements, also

    respecting the technical rules and contractual

    clauses ;

    The presentation of the issued projects in the front of the experts that are checking the

    projects and also the solving of the unconformities

    and incongruity that appeard;

    The elaboration of the technical specification regarding the works execution , the

    exploitation, the maintenance and repairs also

    when it is necessary of the tracking projects

    regarding the behavior in time. Documents

    regarding post service of the construction is issued

    only at the owner demand.

    Estabilisment, through project, of the execution stages for the afferent works, demands

    and participation at the quality checkings on the

    site related on this.

    Establishing the way to treat the defects appeard in the execution, because of the

    executant, at the construction that needs a quality

    level as per requirements, and also the tracking of

    the solutions appliance, after those were learned

    by the attested expert in project, at the owner

    demand;

    The participation at the Technical book of the construction elaboration and at the reception

  • of the completed works.

    3. Obligatii si raspunderi

    ale executantilor

    3. Liabilities and responsabilities

    of the executant

    Executantul lucrarilor de constructii are

    urmatoarele obligatii principale:

    Sesizarea investitorilor asupra neconformitatilor si neconcordantelor constatate

    in proiecte, in vederea solutionarii;

    Inceperea executiei lucrarilor numai la constructii autorizate in conditiile legii si numai

    pe baza si in conformitate cu proiecte verificate de

    specialisti atestati;

    Asigurarea nivelului de calitate corespunzator cerintelor printr-un sistem propriu

    de calitate conceput si realizat prin personal

    propriu, cu responsabili tehnici cu executia

    atestati;

    Convocarea factorilor care trebuie sa participe la verificarea lucrarilor ajunse in faze

    determinante ale executiei si asigurarea conditiilor

    necesare efectuarii acestora, in scopul obtinerii

    acordului de continuare a lucrarilor;

    Solutionarea neconformitatilor, a defectelor si a neconcordantelor aparute in faze de

    executie, numai pe baza solutiilor stabilite de

    proiectant cu acordul investitorului;

    Utilizarea in executia lucrarilor numai a produselor si a procedeelor prevazute in proiect,

    certificate sau pentru care exista agremente

    tehnice, care conduc la realizarea cerintelor,

    precum si gestionarea probelor-martor; inlocuirea

    produselor si a procedeelor prevazute in proiect cu

    altele care indeplinesc conditiile precizate si

    numai pe baza solutiilor stabilite de proiectanti cu

    acordul investitorului;

    Respectarea proiectelor, a detaliilor de executie si a dispozitilor de santier pentru

    realizarea nivelului de calitate corespunzator

    cerintelor;

    Sesizarea, in termen de 24 h, a inspectiei de stat in constructii, in cazul producerii unor

    accidente tehnice in timpul executiei lucrarilor;

    Supunerea la receptie numai a constructiilor care corespund cerintelor de calitate

    si pentru care a predate investitorului documentele

    necesare intocmirii cartii tehnice a constructiei;

    Ducerea la indeplinire, la termenele

    The executant of the works has the following

    principal liabilities:

    Owner notification on about the unconformities and unconcordant that were

    estabilished in the project, for solving them;

    Start of the execution only on the authorized constructions in the law conditions and

    only on base and conformity with the projects that

    were checked by the attested experts;

    Ensuring the quality level appropriate to the demands thought a personal quality concept

    realized throught personal staff, with technical

    responsible in execution that were attested;

    Convocation of the factors that needs to participate at the checking for the works found in

    determinat phase and ensuring the necessary

    conditions to perform, for obtaining the work

    continuation;

    Solving the unconformities, defects and unconcordances that appeard in the execution

    phases, only on the solutions established by the

    project with the owner`s agreement;

    Utilisation only the products and process from the projects in the execution, certified or for

    how exist technical agreements that leads at the

    requirements completion, also the management of

    the witness samples, replacing the products and process from the project with outher that meet

    with the project, based on the designer

    establismed solution with the owner agreement;

    Respecting the projects, execution details and site dispositions for obtaining the quality level

    as per requirements;

    Notice, in 24 h, the state inspectorate in construction, in case of some technical accidents

    that occured in the execution;

    Reception only at the construction that are in accord with the quality requirements and for

    who the necessary documents were handed to the

    owner for the technical book of the construction

    completion;

  • stabilite, a masurilor dispuse prin actele de control

    sau prin documentele de receptie a lucrarilor de

    constructii;

    Remedierea, pe propria cheltuiala, a defectelor calitative aparute din vina sa, atat in

    perioada de executie cat si in perioada de garantie

    stabilita potrivit legii;

    Reducerea terenurilor ocupate temporar la starea lor initiala, la terminarea executiei

    lucrarilor;

    Stabilirea raspunderilor tuturor participantilor la procesul de productie factori de raspundere, colaboratori, subcontractanti in conformitate cu sistemul propriu de asigurare a

    calitatii adoptat si cu prevederile legale in vigoare.

    Completion, at the established terms, of the measures in the control acts or through the

    reception documents of the construction works;

    Remedy, on his own expense, of the quality defects that occured by his fault, in the

    execution period as well as the guarantee period

    as per law;

    Compression of the land temporary used at their initial status, at the end of the works;

    Establishing the responsabilities for all the participants at the product process responsibility factors, contributors, subcontractors in conformity with the personal ensurement quality

    system adapted with the legal previsions in force.

    4. Obligatii si raspunderi

    ale proprietarilor constructiilor

    4. Liabilities and responsabilities

    of the construction owners

    Proprietarii constructiilor au urmatoarele

    obligatii principale:

    Efectuarea la timp a lucrarilor de intretinere si de reparatii care revin, prevazute

    conform normelor legate in cartea tehnica a

    constructiei si rezultate din activitatea de urmarire

    a comportarii in timp a constructiilor;

    Pastrarea si completarea la zi a cartii tehnice a constructiei si predarea acestei, la

    instrainarea constructiei, noului poprietar;

    Asigurarea urmaririi comportarii in timp a constructiilor, conform prevederilor din cartea

    tehnica si reglementarilor tehnice;

    Efectuarea, dupa caz, de lucrari de reconstituire, consolidare, transformare, extindere,

    desfiintare partiala, precum si de alte lucrari de

    reparatii ale constructiei numai pe baza de

    proiecte intocmite de catre persoane fizice sau

    persoane juridice autorizate si verificate potrivit

    legii;

    Asigurarea realizarii lucrarilor de investitii asupra constructiilor,impuse prin reglementarile

    legale;

    Asigurarea efectuarii lucrarilor din etapa de postutilizare a constructiilor, cu respectarea

    prevederilor legale in vigoare.

    The owners of the construction have the

    following liabilities:

    Carry out of the maintenance and repair works in time, as per legal norms included in the

    technical book of the construction and the results

    from behavior tracking in time of the construction;

    Storage and completion up to date of the technical book of the construction and handing

    her, at the alientation to the new owner;

    Ensure the tracking of construction behavior in time, as per technical book and the

    technical regulations;

    Carry out, if is necessary, of reconstruction, consolidations, transformations,

    extension, partial suppression and also other repair

    works of the construction issued by individual or

    juridical persons authorized and checked as per

    law;

    Ensure the achievement of the investition works for constructions, imposed by the legal

    regulations;

    Ensure the completion of the works from the post service stage of the construction, in

    conformity with the legal regulations.

    5. Obligatii si raspunderi ale administratorilor si

    ale utilizatorilor constructiilor

    5. Liabilities and responsabilities of the

    administrators and users of the construction

  • Aministratorii si utilizatorii constructiilor au

    urmatoarele obligatii principale:

    Folosirea constructiilor conform instructiunilor de exploatare prevazute in cartea

    tehnica a constructiei;

    Efectuarea la timp a lucrarilor de intretinere si de reparatii care la revin conform

    contractului;

    Efectuarea de lucrari de investitie la constructia existenta de reconstruire, consolidare,

    transformare, extindere etc., numai cu acordul

    proprietarului si cu respectarea prevederilor

    legale;

    Efectuarea urmaririi comportarii in timp a costructiilor conform cartii tehnice a constructiei

    si contractului incheiat cu proprietarul;

    Sesizarea in termen de 24 de ore, a inspectiei de stat in constructii, in cazul unor

    accidente tehnice la constructiile in exploatare.

    The administrators and users of the construction

    have the following principal liabilities:

    Use of the construction as per exploitation instructions on the technical book of the

    construction;

    Accomplishment in time the maintaining and repair works as per contract;

    Investment works accomplishment at the existing construction reconstruction, consolidation, transformation, extension etc., only

    with the owner`s agreement and as per legal

    previsions;

    Accomplishment of the tracking of behavior for construction as per technical book of

    the construction and the contract concluded with

    the owner;

    Notice in 24 hours, the state inspectorate in construction in case of some technical accidents

    at the constructions that are in exploitation